Vaughn Materials Co. v. Security Pacific National Bank

170 Cal. App. 3d 908, 216 Cal. Rptr. 605, 1985 Cal. App. LEXIS 2287
CourtCalifornia Court of Appeal
DecidedJuly 31, 1985
Docket24467
StatusPublished
Cited by1 cases

This text of 170 Cal. App. 3d 908 (Vaughn Materials Co. v. Security Pacific National Bank) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vaughn Materials Co. v. Security Pacific National Bank, 170 Cal. App. 3d 908, 216 Cal. Rptr. 605, 1985 Cal. App. LEXIS 2287 (Cal. Ct. App. 1985).

Opinion

Opinion

CARR, J.

Plaintiff Vaughn Materials Company, Inc. appéals from summary judgment entered in favor of defendant Security Pacific National Bank. We shall affirm.

Facts

Plaintiff was the owner and operator of a business which sold building materials. Donald Kistler (hereafter Kistler) was the owner of real property *911 upon which an office complex was constructed. Kistler applied to plaintiff for credit and thereafter plaintiff delivered building materials to the job site. All materials were billed to Kistler, as he was the only individual connected with the construction of the complex with whom plaintiff had any type of contractual relationship.

On June 3, 1981, Kistler recorded a “Notice of Completion,” reflecting a project completion date of May 29, 1981. On July 13, 1981, approximately 40 days after recordation of the notice of completion, plaintiff recorded its mechanics’ lien on the subject property.

Upon nonpayment by Kistler, plaintiff filed suit against Kistler and Security Pacific Bank and in January 1982, filed a first amended complaint “for foreclosure of mechanic’s lien, breach of contract and for monies due.” Defendant Security Pacific Bank had provided the financing for the construction project and secured its loan by a construction deed of trust against the subject property. It moved for summary judgment, 1 asserting plaintiff did not have a valid lien because of failure to comply with certain procedural requirements, in particular, that the lien was untimely as it was not filed within the 30-day period required by Civil Code section 3116 for subcontractors and materialmen, but was in fact filed 40 days after recordation of the notice of completion.

Plaintiff opposed the summary judgment, contending it was an “original contractor” within the meaning of Civil Code section 3095, and therefore entitled to the 60-day period provided by Civil Code section 3115 within which to record its lien.

The trial court granted summary judgment in favor of defendant, ruling that plaintiff was a materials supplier and not an original contractor. The amended order for summary judgment stated in part:

“[Tjhere is no triable issue of fact that plaintiff ... is other than a materialman, as that term is defined in Civil Code §3090.[ 2 ] A ‘materialman’ as defined in Civil Code §3090 is not the same as a ‘contractor’ as that term is used in Civil Code §3095. Therefore, even though plaintiff . . . may have had a direct contractual relationship with the owner of the subject real property, plaintiff was not an ‘original contractor’ within the meaning of Civil *912 Code §3095, because plaintiff is not ‘contractor’ within the meaning of Civil Code §3095. [¶] . . . The owner of the subject real property . . . [Kistler], recorded a Notice of Completion with respect to the subject real property on May 29, 1981. Plaintiff . . . recorded its mechanics lien on July 13, 1981, forty (40) days after recordation of the Notice of Completion. Because plaintiff ... is not an original contractor, it is governed by the provisions of Civil Code §3116, which requires that its mechanics lien be recorded within thirty (30) days after recordation of a Notice of Completion. Therefore, plaintiff[’s] mechanics lien is invalid because it was not filed within the thirty-day time limit of Civil Code §3116.”

Discussion

Civil Code section 3116 (hereafter all statutory citations are to the Civil Code unless otherwise indicated) provides: “Each claimant other than an original contractor, in order to enforce a lien, must record his claim of lien after he has ceased furnishing labor, services, equipment, or materials, and before the expiration of (a) 90 days after completion of the work of improvement if no notice of completion or cessation has been recorded, or (b) 30 days after recordation of a notice of completion or notice of cessation. ” (Italics added.)

In turn, section 3115 states: “Each original contractor, in order to enforce a lien, must record his claim of lien after he completes his contract and before the expiration of (a) 90 days after the completion of the work of improvement as defined in Section 3106 if no notice of completion or notice of cessation has been recorded, or (b) 60 days after recordation of a notice of completion or notice of cessation.” (Italics added.)

Section 3095 defines an “original contractor” as “any contractor who has a direct contractual relationship with the owner.”

Relying on the foregoing statutes, plaintiff asserts its contract to supply materials was a contract directly with Kistler, the owner of the property on which the office building was constructed, and he thus qualifies as an original contractor with 60 days after the filing of the notice of completion within which to record its claim of lien. We disagree.

Plaintiff has cited no case for the contention that one who supplies materials to a construction site, but who does not provide any labor or engage in any construction work at all, qualifies as either an original contractor or subcontractor within the meaning of the mechanics’ lien law. Our research indicates a materialman such as plaintiff does not so qualify.

*913 In Theisen v. County of Los Angeles (1960) 54 Cal.2d 170 [5 Cal.Rptr. 161, 352 P.2d 529], Theisen was the prime contractor on a county fire station job. Petterson agreed to supply 64 custom-made doors conforming to the specifications of the architect. Petterson contracted with Durand for 20 of the doors for $1,148. Durand, unpaid, claimed relief under the equivalent of the mechanics’ lien law. 3 Theisen claimed Durand had no mechanics’ lien rights because neither Petterson nor Durand delivered to the job site, or even visited the job site and, in fact, Theisen had picked up the doors at Petterson’s plant.

The court held Petterson was a subcontractor. Durand, as his supplier of materials, was therefore entitled to a mechanics’ lien though Petterson had never been on the job site. The court found the essential feature that constitutes one a subcontractor rather than a materialman is that he constructs a definite, substantial part of the work of improvement in accordance with plans and specifications, whether or not he enters the job site and does construction work. Durand fabricated the doors for Petterson according to the specifications of the prime contractor and was entitled to assert a mechanics’ lien as a subcontractor of Petterson. (54 Cal.2d at p. 183.)

Theisen contravenes the assertion that a materialman who contracts directly with the owner is an original contractor. To so hold would necessarily require a finding that a materialman who contracts with the original contractor is a subcontractor. 4 The essential holding of Theisen

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jimenez v. Superior Court
98 Cal. Rptr. 2d 587 (California Court of Appeal, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
170 Cal. App. 3d 908, 216 Cal. Rptr. 605, 1985 Cal. App. LEXIS 2287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vaughn-materials-co-v-security-pacific-national-bank-calctapp-1985.