Hihn-Hammond Lumber Co. v. Elsom

154 P. 12, 171 Cal. 570, 1915 Cal. LEXIS 664
CourtCalifornia Supreme Court
DecidedDecember 17, 1915
DocketS. F. No. 6707.
StatusPublished
Cited by15 cases

This text of 154 P. 12 (Hihn-Hammond Lumber Co. v. Elsom) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hihn-Hammond Lumber Co. v. Elsom, 154 P. 12, 171 Cal. 570, 1915 Cal. LEXIS 664 (Cal. 1915).

Opinion

SHAW, J.

A number of persons, each claiming a mechanic’s lien on the same property, began separate actions to foreclose the liens. These actions were consolidated for trial and resulted in a joint judgment of foreclosure. The building, on account of which the liens accrued, was erected prior to the enactment of the amendment of 1911 to the mechanic’s lien law, in pursuance of a contract which was valid under the prior law. The liens amounted to more than the balance found due from the owner to the contractor. This made it necessary to apportion the balance to the respective claimants, and to declare the rank of each lien and the order of its payment out of the fund. Six of the lien claimants, namely, Thomas J. Guilfoy, Waterhouse-Price Company, Floodberg & McCaffery, W. W. Montague & Company, N. Clark & Sons, and Ford & Malott, being dissatisfied with the rank assigned to them by the judgment, have appealed from the judgment and from an order denying their motion for a new trial.

The court found that each of these appellants was a subcontractor, and, for that reason, assigned them a rank sub *572 ordinate to that of laborers and materialmen. The provisions of section 1194 of the Code of Civil Procedure, as it then existed, declared that laborers and materialmen should have preference over subcontractors in participation in the amount applicable to liens under that law.

The first point urged by the appellants is that section 1194, in so far as it gives such preference to laborers and material-men, is unconstitutional. This question was considered by this court in Miltimore v. Nofziger etc. Co., 150 Cal. 790, [90 Pac. 114]. It was there declared that the section did not violate the constitution by reason of this preference, but only so far as it gave laborers a preference over materialmen. Some members of the court dissented on the ground that the priorities given to laborers over materialmen was valid. But there was no difference of opinion regarding the power of the legislature to prefer these two classes to subcontractors. We are not disposed to go over the ground again to demonstrate the soundness of this decision. Upon the authority thereof we hold that the point is not well taken.

Another proposition advanced in support of the appeal is that the findings of the court, with respect to each of the appellants, that it was a subcontractor and not a materialman, are contrary to the evidence.

The facts relating to each of them are as follows: The building erected was a large two-story dwelling-house. The contract price was $27,635.20. R. W. Elsom & Company were the contractors for the erection of the building. Guilfoy agreed to furnish and set in place in the building “all tin, galvanized iron, and copper work, including copper sash bars, galvanized iron caps, coppper flashings at back of wall, two rows of cross-bars and a half bar at wall line, the full length, ’ ’ all according to the plans and specifications of the building prepared by the architect. The cost of the material for this work amounted to $943.50. The cost of the labor was $247.50. The Waterhouse-Price Company agreed to furnish the tile for the walls of four bathrooms and a toilet and set the same in the building, the setting to be done by experienced workmen from San Francisco, all as required by the plans and specifications. The material therefor amounted to $227.50 and the labor, $37.50. Floodberg & McCaffery agreed to furnish the material and labor necessary to complete the lathing and plastering upon the building according to specifications at *573 taehed to the contract. The material amounted to one thousand six hundred dollars, and the labor to $1,363.20. Montague & Company agreed to furnish and place in the building 360 square feet of tile for the front porch, 250 square feet of tile and the cove around the walls with plinth blocks at doors, for four bathrooms and floors of toilets on the second floor; also to furnish the materials and place in the building four fireplaces made of brick or tile in different rooms in the building and to place 75 square feet of tile and wire spaces in the pantry. For all this the material amounted to five hundred dollars and the labor to $423. Clark & Sons agreed to deliver and lay in place the tile roof with scalloped iron at the eaves, in accordance with the plans and specifications. The material amounted to $1,350 and the labor $335. Much of the tile had to be cut and fitted on the premises. Ford & Malott agreed to lay the fiber stone flooring and furnish the material therefor in the breakfast-room and on the south and west lower porches. The material amounted to $340 and the labor to three hundred dollars.

The question whether one who claims a lien upon a building is a contractor or materialman has been several times considered by the court. A brief statement of the cases in which the decisions have been rendered will assist in elucidating the principles to be applied. In Hinckley v. Field’s Biscuit etc. Co., 91 Cal. 139, [27 Pac. 594], it was held that one who constructs, before delivery, “a steam plant consisting of boilers, engine, heater, feed-pipe, etc.,” for a cracker factory, delivers them and puts them in place in the factory building, is a materialman, and not a contractor. It was said that the work of putting these materials in place “was only the completion of their contract to deliver such finished machinery.” In Roebling’s Sons Co. v. Humboldt Electric Light etc. Co., 112 Cal. 290, [44 Pac. 568], the same rule was made concerning a contract to make and set up ready for use in a building an electrical plant “consisting of dynamos, converters, switchboard, lamps, etc., with the necessary wiring and connections,” although in order to set them up it was necessary to put in the building a foundation for the dynamos and to install the wires and lamps. In Bennett v. Davis, 113 Cal. 337, [54 Am. St. Rep. 354, 45 Pac. 684], the same rule was followed with respect to a contract to furnish mantels, tiles, and grates and set them in a building under construction. Each tile pertain *574 ing to the mantels had to be set in separately and some bricklaying around the mantels was necessary as a part of the setting thereof. In Bryson v. McCone, 121 Cal. 153, [53 Pac. 637], the court held that a person contracting to build ice tanks, including steel molds, pipes, pumps, and connections, and to set them up in an ice factory, was a materialman, and not an original contractor.

In Smith v. Bradbury, 148 Cal. 41, [113 Am. St. Rep. 189, 82 Pac. 367], it was held that one who contracted to do the plastering in a building at a stated price per yard was a subcontractor, and not a materialman. So in La Grill v. Mallard, 90 Cal. 373, [27 Pac. 294], one who contracted to paper and decorate a number of rooms in a dwelling-house, where the actual work was done by employees, was held to be an original contractor. The only rule of general application announced in any of the above-mentioned decisions was stated in Bennett v. Davis, 113 Cal. 339, [54 Am. St. Rep. 354, 45 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eggers Industries v. Flintco, Inc.
201 Cal. App. 4th 536 (California Court of Appeal, 2011)
O. G. Sansone Co. v. Department of Transportation
55 Cal. App. 3d 434 (California Court of Appeal, 1976)
Benson Elec. Co. v. Hale Bros. Assoc., Inc.
246 Cal. App. 2d 686 (California Court of Appeal, 1966)
Theisen v. County of Los Angeles
352 P.2d 529 (California Supreme Court, 1960)
Phillips & Edwards Electric Corp. v. Shintaffer
299 P.2d 912 (California Court of Appeal, 1956)
J. T. Weybrecht's Sons Co. v. Hartford Accident & Indemnity Co.
161 Ohio St. (N.S.) 436 (Ohio Supreme Court, 1954)
Arcweld Manufacturing Co. v. Burney
121 P.2d 350 (Washington Supreme Court, 1942)
Harris & Stunston, Inc. v. Yorba Linda Citrus Ass'n
26 P.2d 654 (California Court of Appeal, 1933)
J. Watts Kearny & Sons v. Perry
141 So. 13 (Supreme Court of Louisiana, 1932)
Gallagher v. Campodonico
5 P.2d 486 (Appellate Division of the Superior Court of California, 1931)
Morley v. McCaskey
1928 OK 604 (Supreme Court of Oklahoma, 1928)
Indiana Limestone Co. v. Cuthbert
267 P. 983 (Supreme Court of Kansas, 1928)
Vander Horst v. Kalamazoo Apartments Corp.
215 N.W. 57 (Michigan Supreme Court, 1927)
Riggen v. Perkins
246 P. 962 (Idaho Supreme Court, 1926)
Bird v. American Surety Co. of New York
166 P. 1009 (California Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
154 P. 12, 171 Cal. 570, 1915 Cal. LEXIS 664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hihn-hammond-lumber-co-v-elsom-cal-1915.