Ely v. Bottini

179 Cal. App. 2d 287, 179 Cal. App. 287, 3 Cal. Rptr. 756, 1960 Cal. App. LEXIS 2231
CourtCalifornia Court of Appeal
DecidedMarch 29, 1960
DocketCiv. 18486
StatusPublished
Cited by14 cases

This text of 179 Cal. App. 2d 287 (Ely v. Bottini) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ely v. Bottini, 179 Cal. App. 2d 287, 179 Cal. App. 287, 3 Cal. Rptr. 756, 1960 Cal. App. LEXIS 2231 (Cal. Ct. App. 1960).

Opinion

DOOLING, J.

I. J. Ely, a general contractor, sued Mario Bottini on a written subcontract entered into between the parties on June 6, 1955, whereby the latter had agreed to do certain construction work for Ely. Plaintiff alleged that Bottini had failed to provide timely performance, and that as a result of this delay heavy rains had damaged the work. He further alleged that he had been compelled to do certain portions of Bottini’s work. The court overruled a demurrer and defendant answered the complaint, alleging that plaintiff himself had breached the contract by failing to make progress payments and that no damages had resulted to plaintiff. During the trial of this cause without jury, two supplemental complaints were allowed to be filed. The court filed findings of fact and conclusions of law, including a finding that although Bottini had earned $27,953, he was chargeable with damages in the amount of $18,934.70. Consequently, the court ordered plaintiff to pay defendant $7,318.30 plus interest. Both parties now appeal from the decree granting the above-mentioned relief.

On June 12, 1955, I. J. Ely contracted to perform certain work at Loch Lomond Subdivision, Unit Number 2, in Marin County, for Robert McCarthy Company, Inc. This contract provided that the work must be completed within 60 working days, or by September 12, 1955. It contained a liquidated damages clause requiring Ely to pay McCarthy $50 per day for each calendar day of delay beyond September 12.

This contract provided for the installation of sewers, curbs, gutters, and sidewalks, for which work Ely had previously let a subcontract to Mario Bottini on June 6, 1955. By the terms of the June 6 contract, Bottini was to complete his work within 40 working days after the signing of the Ely-McCarthy contract. Also, by the terms of the June 6 contract, Ely was to pay Bottini a bonus of $300 in exchange for the latter’s bonding of his work directly to the McCarthy Company. Bottini, in fact, did execute such a bond dated June 22, 1955.

The June 6 contract and the bond both referred to 9,240 square feet of sidewalk which Bottini was to install. Ely testified that he mentioned to Bottini the possibility that this *291 portion of the work might be eliminated. The McCarthy Company later did eliminate it, Ely testifying that this cancellation was by authority of a provision of the June 12 contract permitting McCarthy to do so. Bottini testified that it would cost about 15 cents per lineal foot less to install curbs and gutters when installing sidewalks at the same time and that he had contemplated installing all three at the time he bid for the June 6 contract. He also testified that he was told not to install sidewalks only after he had begun to do so, sometime between August 18-20.

Bottini began work on July 21, 1955, but on about August 14, he had completed only about 20-25 per cent thereof. By September 12, 1955, he had completed only about 35 per cent of his job. Ely could not proceed with street paving under the June 12 contract until Bottini had finished.

McCarthy testified that he had observed that Bottini was working too slowly, and that he had written several letters to Ely and had spoken to Bottini many times concerning this. Ely testified that he had made many telephone calls to Bottini, starting as early as the latter part of July, complaining that the work was behind schedule. Ely’s vice president and supervisor of the Bottini contract, Ralph C. Noah, also had numerous conversations with Bottini on the same subject. Noah testified, however, that despite this Bottini frequently used no more than two or three men at a time on the job, and these worked only sporadically during August. McCarthy corroborated this, stating that he didn’t remember ever seeing more than two or three men on the job at any time. Bottini denied that he had had an insufficient crew.

Ely testified that he had first warned Bottini that the latter’s delay would make it necessary to hire other subcontractors at Bottini’s expense sometime between August 25 and September 5. On October 7, 1955, Ely sent Bottini a registered letter reminding him of the June 6 contract obligations, warning him of the damages which further delay would cost him, and stating that the expense of another contractor, already hired, would be charged against him.

Ely actually employed several subcontractors to complete various portions of the June 6 contract. Some of Bottini’s work had not met contract specifications. The city required a compaction of 90 per cent relative density around the sewer line. Tests showed that Bottini had not complied with this requirement. Ely paid the J. D. O’Connor Company and a *292 concrete supplier a total of $4,748.32 for work done during October and November of 1955. He informed Bottini of the hiring of the O’Connor Company at the time the latter began work, Bottini having already advised him to find someone else to do the job if he could. Ely also hired Ghilotti Brothers, Inc., to install catch basins, again informing Bottini of such and receiving his concurrence at the time Ely first contacted Ghilotti. The latter began that work on November 12, 1955.

Ely did not recall having informed Bottini that this employment of other subcontractors would be on an overtime basis, but he testified that such was necessary in order to mitigate damages. Noah testified that Bottini must have known of this week-end work because he could see its results when he returned to the job on Monday mornings. Bottini denied having known that he was being charged overtime rates for O’Connor’s work until he received the bills for it in January or February.

Heavy rains began falling on November 13, 1955, and continued through December 24 of that year. The resulting floods washed mud and gravel down from surrounding higher ground, causing extensive damage to the entire job, which was still uncompleted. On December 24, 1955, Ely again wrote to Bottini, insisting that he take immediate steps to alleviate the damages being caused by the rain, and to complete his contractual obligations. Ely also again stated that Bottini would be charged for all repairs necessitated and damages caused by his breach of contract. Ely testified that although Bottini subsequently sent men to clean out sewer manholes, he failed to clean the clogged drainpipes as requested in the above-mentioned letter. On December 27, 1955, and on March 12, 1956, Ely sent additional letters giving similar notice to Bottini.

The Ely-McCarthy contract called for 90 per cent progress payments. McCarthy made two of these to Ely prior to November, but held up subsequent payments amounting to about $15,500 because the work was progressing too slowly.

Bottini testified that before he signed the June 6 contract, either Ely or Noah had promised him monthly progress payments. He submitted his first invoice to Ely on September 1, 1955, for $8,925.50. Ely did not make payments to Bottini as the latter’s work progressed except for one payment of $1,200, but did give credit to Bottini on other debts owing by Bottini to Ely.

Noah testified that some of the delay was caused by the *293 absence of survey stakes, which were the responsibility of McCarthy’s engineer, but that this delay was not substantial, amounting to a few hours only.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Visa Inc. v. Sally Beauty Holdings, Inc.
Court of Appeals of Texas, 2021
Archdale v. American International Specialty Lines Insurance
64 Cal. Rptr. 3d 632 (California Court of Appeal, 2007)
Burnett & Doty Development Co. v. Phillips
84 Cal. App. 3d 384 (California Court of Appeal, 1978)
Mann v. Glens Falls Insurance
418 F. Supp. 237 (D. Nevada, 1974)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Whitney Investment Co. v. Westview Development Co.
273 Cal. App. 2d 594 (California Court of Appeal, 1969)
Dulien Steel Products, Inc. v. A. J. Industries, Inc.
264 Cal. App. 2d 540 (California Court of Appeal, 1968)
Reichert v. General Insurance of America
442 P.2d 377 (California Supreme Court, 1968)
B. C. Richter Contracting Co. v. Continental Casualty Co.
230 Cal. App. 2d 491 (California Court of Appeal, 1964)
Weaver v. Bank of America National Trust & Savings Ass'n
380 P.2d 644 (California Supreme Court, 1963)
A. I. Gage Plumbing Supply Co. v. Local 300 of International Hod Carriers
202 Cal. App. 2d 197 (California Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
179 Cal. App. 2d 287, 179 Cal. App. 287, 3 Cal. Rptr. 756, 1960 Cal. App. LEXIS 2231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ely-v-bottini-calctapp-1960.