Friberg v. Elrod

296 P. 1061, 136 Or. 186, 1931 Ore. LEXIS 81
CourtOregon Supreme Court
DecidedOctober 17, 1930
StatusPublished
Cited by12 cases

This text of 296 P. 1061 (Friberg v. Elrod) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friberg v. Elrod, 296 P. 1061, 136 Or. 186, 1931 Ore. LEXIS 81 (Or. 1930).

Opinion

*189 BEAN, C. J.

Section 5 of the contract provides as follows:

“The'engineer shall be the sole judge of the sufficiency of the force employed, the suitability and capacity of any plant and the quality of the work done by the contractor or his employees.”

Section 5 of the specifications, which are made a part of the contract, provides:

“All corrections of errors or omissions in the specifications or plans may be made by the engineer when such correction is necessary for the proper fulfillment of their intention as construed by him.”

Section 11 of the specifications reads as follows:

“All disputes or disagreements between the parties hereto shall be submitted to and decided by the engineer and his decision shall be binding upon both parties.”

*190 It also contains the following provision:

“Any reasonable modification of the proposed plans which does not materially add to the cost of the work to the contractor or any work required because of omissions or incomplete plans shall be performed at the prices bid and without extra payment on account of such changes or omissions.”

The plaintiff contends that by the express provisions of the contract the engineer’s authority was limited and circumscribed to the general supervision of the work. Plaintiff further contends that the partnership failed to comply with their contract by neglecting to supply plaintiff with materials when required and failed to deliver the material on the floor of the dock as provided by the contract, resulting in great delay and expense to the plaintiff; that during the construction the plans and specifications were arbitrarily changed and altered so as to include extensive and costly additions to the work not originally contracted for; that defendants delayed the completion of certain preliminary work, such as the installation of piling and making of certain fills and laying of the dock floor, which delayed plaintiff in the construction of the buildings; that a roadway to the structure was not completed until about the 20th of September, .1927; that certain plans required for the apple storage bouse were not delivered by the partnership until the 20th of September, 1927, which delayed the construction of the apple storage house; that when the buildings were approximately one-half completed the defendants ordered plaintiff to discontinue the construction under the old plans and specifications, and thereupon new plans and specifications were substituted; that structural iron and roof joists were not delivered when required; that construction was caused to be *191 discontinued on account of the settling of fills; that certain changes were made in the bulkhead wall during construction, necessitating the reconstruction of forms; that extensive and costly changes were required to be made during the construction of a retaining wall; that defendants’ conflicting orders interfered with the construction; that improper and inferior materials were supplied by defendants; that the plans were incomplete, all of which caused delay, great expense and damage to plaintiff.

The plaintiff contends that the contract has been materially modified by the parties in so many particulars as to be no longer controlling. We do not so find. Defendants contend the parties are bound by the express terms and conditions of their written contract.

The contract provided that any “supplemental agreements covering such work which may be made from time to time” are made a part of the contract. The contractor commenced the work about the 28th of August, 1927. The contract provided that the first payment should be made September 10, and payments should be made on each Saturday thereafter for the work done up to and including Thursday of the particular week. The estimated cost of the building was $62,000. Mr. Friberg rendered a bill September 17, 3927, for extra work done to that date, and it was paid. The foreman furnished some items of extra work of different dates at different times, but no statement of the cost plus work was rendered until about December 19, when the building was nearly completed. Plaintiff presented a bill claiming cost plus for several items, many of which were rejected by the engineer who, by the terms of the contract, was to pass on such matters, and a claim of lien was filed in which *192 the price per item was materially reduced. Friberg, in explaining why he presented claims to the partnership and afterwards filed a lien for different amounts, said it was done by his son, and stated: “A party told my son that you were dealing with a horse trader now and you had better make your bills accordingly, and you had better make them about double, so you can settle for half; and my son asked me whether he should do that or not. ‘Well,’ I says, ‘that is poor policy to do it, but,’ I says, ‘you can try it.’ ”

On November 18 and November 21,1927, Elrod and Trimble wrote Friberg that all bills for extras must be presented to Brown, the engineer, not later than Friday night of the week of November 18, and that thereafter all bills for extras must be presented to Brown for approval or rejection within three days of the performance of the work.

One of the main contentions of plaintiff is that the written contract made between the parties is not controlling for the reason that it has been deviated from in so many particulars, and so many changes, alterations and additions thereto were made and acquiesced in by the parties that there was a departure from the original contract.

The plaintiff’s lien embraced in this foreclosure suit is based upon the written contract dated August 23, 1927, between plaintiff and Elrod and Trimble. The contract provides for the manner of arriving at the amount to be paid for the work to be performed by plaintiff. The plaintiff now claims that he is entitled to recover for work done which is not mentioned in the contract of the parties, on the quantum meruit. The contract is, for work not coming within the unit price called for in the contract, that plaintiff should be compensated for the cost thereof plus 10 per cent.

*193 Plaintiff’s contention that the contract was so changed that the same was abandoned and abrogated, cannot be upheld. Plaintiff cites and quotes from Hayden v. Astoria, 74 Or. 525 (145 P. 1072), to sustain such contention. In that case, based upon the allegations of the complaint, this court followed the rule that where the original contract has been deviated from in so many matters that it cannot be regarded as controlling it must be considered as abrogated and the parties relegated to their implied rights, for a subsequent departure from the terms of a written contract by the parties, mutually acquiesced in, abrogates it to that extent. (Citing 4 Elliott, Contracts, § 3697.) The facts in the Hayden case are entirely different from those in the case at bar. Here provision is made in the contract that extra work should be paid for at cost, plus 10 per cent. No such provision was contained in the contract mentioned in the Hayden case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. McCollom
958 P.2d 207 (Court of Appeals of Oregon, 1998)
Valenti v. Hopkins
926 P.2d 813 (Oregon Supreme Court, 1996)
Lincoln Construction, Inc. v. Thomas J. Parker & Associates, Inc.
602 P.2d 676 (Court of Appeals of Oregon, 1979)
Krieg v. UNION PACIFIC LAND RESOURCES CORPORATION
525 P.2d 48 (Oregon Supreme Court, 1974)
McHorse v. Portland General Electric Company
521 P.2d 315 (Oregon Supreme Court, 1974)
State Highway Commission v. Heintz Construction Co.
423 P.2d 175 (Oregon Supreme Court, 1967)
Drury Et Ux v. Pekar
355 P.2d 598 (Oregon Supreme Court, 1960)
Rueda v. Union Pacific Railroad Co.
175 P.2d 778 (Oregon Supreme Court, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
296 P. 1061, 136 Or. 186, 1931 Ore. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friberg-v-elrod-or-1930.