Ybarra v. Saldana

624 S.W.2d 948, 1981 Tex. App. LEXIS 4458
CourtCourt of Appeals of Texas
DecidedNovember 25, 1981
Docket16674
StatusPublished
Cited by16 cases

This text of 624 S.W.2d 948 (Ybarra v. Saldana) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ybarra v. Saldana, 624 S.W.2d 948, 1981 Tex. App. LEXIS 4458 (Tex. Ct. App. 1981).

Opinion

OPINION

Before KLINGEMAN, CLARK and BAS-KIN, JJ.

KLINGEMAN, Justice.

Appellees Carlos Saldana, Miguel Salda-na, and Antonio Saldana, filed suit to recover damages from the commission of deceptive trade practices by appellant, A. Ybarra, pursuant to the Deceptive Trade Practices-Consumer Protection Act, Tex.Bus. & Com. Code Ann. § 17.50(a) (Vernon Supp. 1976-1977). 1 In a non-jury trial, the court found the appellee sustained actual damages of $11,098.74 which consisted of $6,098.74 as the reasonable and necessary amount spent by appellee over and above the contract price in order to complete the construction as per the original plans; and $5,000 as the value of appellee’s services in supervising the construction work. The trial court trebled the actual damages, 2 awarding the total of $33,296.22, plus attorney’s fees. In addition, the court found that appellee suffered mental pain and anguish to the extent of $6,000 as a direct result of appellant’s deceptive trade practices, but denied such recovery. Appellant appeals said judgment; appellee cross-appeals as to the denial of recovery for mental pain and anguish. No findings of fact or conclusions of law were filed by the trial court. 3 There are no points of error complaining of the trial court’s failure to file findings of fact or conclusions of law.

Appellant and appellee entered into a written contract on July 18, 1977, under which appellant agreed to construct a house for appellee for a total consideration of $44,730. It was agreed that construction would be complete on or before 120 days from July 23, 1977, the date the contract was executed and acknowledged. By the end of the contract period (late November) construction was only half complete. By letter of December 21, 1977, appellee informed appellant of his intention to file this *951 suit. In response, the appellant requested an extension of 8 weeks from January 2, 1978, in which to complete construction. After granting the extension, appellee advanced $1,200 to appellant notwithstanding the terms of the extension agreement with respect to deferral of future draws. Thereafter, appellant failed to continue to work. This suit was then filed on April 23, 1978.

In the absence of findings of fact, the trial court’s judgment must be viewed as impliedly finding all necessary facts in support of its judgment. Lassiter v. Bliss, 559 S.W.2d 353 (Tex.1977); Buchanan v. Byrd, 519 S.W.2d 841 (Tex.1975); Renfro Drug Co. v. Lewis, 149 Tex. 507, 235 S.W.2d 609 (1951). Where findings of fact and conclusions of law are not properly requested and subsequently filed, the judgment of the trial court must be affirmed if it can be upheld on any legal theory supported by the evidence. Seaman v. Seaman, 425 S.W.2d 339, 341 (Tex.1968). In seeking to determine whether there is any evidence to support the judgment and the implied findings of fact incident thereto, it is proper to consider only the evidence most favorable to the issue and to disregard entirely that which is opposed to it or contradictory in its nature. Renfro Drug Co. v. Lewis, supra.

Appellant’s first point of error asserts that the trial court reversibly erred in finding a violation of “the Act,” when appellee failed to plead and prove that appellant acted with an intent to deceive. Appellant submits that the specific acts set forth by appellee in its original petition as constituting appellant’s deceptive trade practices are not included in the legislatively proscribed acts of § 17.46(b) or § 17.50(a)(4). Therefore, the alleged deceptive trade practices must fall within §§ 17.46(a), 17.50(a)(2), or 17.50(a)(3). Appellant contends that these three sections require proof of the intent to deceive the consumer. Appellee having failed to prove such intent to deceive, appellant argues that the trial court reversibly erred in finding a violation of the Act.

Appellant’s contention is without merit. Section 17.46(b) sets forth a list of “false, misleading, or deceptive acts or practices” which are unlawful as a matter of law. This is not an exclusive list, because § 17.46(b) states that “the term ‘false, misleading, or deceptive acts and practices’ includes, but is not limited to the following acts: .... ” Where an unlisted act or practice is alleged there must be two factual findings: (1) that the act or practice occurred; and (2) that it was a deceptive trade practice. Spradling v. Williams, 566 S.W.2d 561, 564 (Tex.1978). As hereinbefore noted, there are no findings of fact or conclusions of law filed with this appeal.

The record sufficiently supports the trial court’s implied finding that (A) appellant was guilty of a violation of the Texas Deceptive Trade Practices Act, and (B) an intent to deceive is not required under the Act as it applies to this case. Even if we assume that an intent to deceive is required, 4 the evidence sufficiently supports an implied finding that appellant acted with intent to deceive appellee.

Appellant’s second point of error alleges that the trial court reversibly erred in including $5,000 as part of the $11,098.74 actual damages awarded to appellee. This amount was attributed to the value of ap-pellee’s services in supervising the construction work. 5 Since appellee is not a contractor by profession and at all times in question was employed and paid by the U. S. Army for his professional services as a den *952 tist, appellant contends that appellee suffered no economic detriment and was not entitled to such recovery under the Act.

“The actual damages suffered under § 17.50(b)(1) are determined by the total loss sustained by the plaintiff as a result of the deceptive trade practices.” Smith v. Baldwin, 611 S.W.2d 611, 617 (Tex.1980). While the Act does not define actual damages, the term has been construed to mean common law damages. Smith v. Kinslow, 598 S.W.2d 910, 913 (Tex.Civ.App.—Dallas 1980, no writ) 6 One common law measure of damages is direct economic loss determined by the costs of replacement and repairs. Nobility Homes of Texas, Inc. v. Shivers, 577 S.W.2d 77, 78 n.l (Tex.1977). Therefore, “[w]hen an owner, upon failure of the contractor to perform takes over the job and completes the work himself, he may recover from the contractor the excess of the reasonable and necessary cost of completion over and above the unpaid portion of the contract price.” McKnight v. Renfro, 371 S.W.2d 740

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker & Associates Surveying, Inc. v. Austin
301 S.W.3d 909 (Court of Appeals of Texas, 2010)
Perez v. Hung Kien Luu
244 S.W.3d 444 (Court of Appeals of Texas, 2007)
Beaston v. State Farm Life Insurance Co.
861 S.W.2d 268 (Court of Appeals of Texas, 1993)
Milt Ferguson Motor Co. v. Zeretzke
827 S.W.2d 349 (Court of Appeals of Texas, 1991)
Feinman v. State
717 S.W.2d 106 (Court of Appeals of Texas, 1986)
Cactus Utility Co. v. Larson
709 S.W.2d 709 (Court of Appeals of Texas, 1986)
Brown Foundation Repair & Consulting, Inc. v. McGuire
711 S.W.2d 349 (Court of Appeals of Texas, 1986)
Ashley v. Bizzell
694 S.W.2d 349 (Court of Appeals of Texas, 1985)
Vick v. George
671 S.W.2d 541 (Court of Appeals of Texas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
624 S.W.2d 948, 1981 Tex. App. LEXIS 4458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ybarra-v-saldana-texapp-1981.