Southern Steel Co. v. Consolidated Engineering Co.

677 S.W.2d 97
CourtCourt of Appeals of Texas
DecidedJune 29, 1984
DocketNo. 04-81-00330-CV
StatusPublished
Cited by3 cases

This text of 677 S.W.2d 97 (Southern Steel Co. v. Consolidated Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Steel Co. v. Consolidated Engineering Co., 677 S.W.2d 97 (Tex. Ct. App. 1984).

Opinion

OPINION

DIAL, Justice.

This is an appeal from a judgment for breach of a construction contract.

Appellant Southern Steel Company (Southern) won the bid for a contract to provide and install jail equipment in the construction of the Shelby County Justice Center in Memphis, Tennessee. Southern entered into a subcontract with appellee Consolidated Engineering Company, Inc. (Consolidated), whereby Consolidated was to actually erect and install at the job site in Memphis the jail equipment which Southern would manufacture in San Antonio, and ship by truck to Tennessee.

Work began on the project in September of 1978. By December a dispute had arisen concerning delays in shipment by Southern and delays in installation at the job site by Consolidated. By letter dated [100]*100January 19, 1979, Consolidated advised Southern as follows:

You have left us with no choice but to consider you in absolute breach of our SUBCONTRACT AGREEMENT and to advise you that, due to that breach, we cannot and will not continue under the existing arrangement beyond Friday, January 26, 1979. While we would feel justified in an action for our cost overruns and anticipated profits, we prefer to reach some agreement with you that will result in completion of the CENTER as soon as possible.

Several meetings were held between Southern and Consolidated in late January and early February to try to resolve the growing problem. On February 28, 1979, the president of Southern wrote the president of Consolidated a letter containing the following:

We are both proceeding on this joint course of action to try and get the job done for the owner and demonstrate our attitude of cooperation. By this, you and I agree that we are not changing the contract or otherwise giving up any legal rights.

The letter also provided for reimbursement to Consolidated for adding additional crews to work. For the next three months work progressed on the job, but Consolidated continued to complain of unsatisfactory delivery of materials by Southern. On June 15, 1979, Consolidated shut down the job and quit the job site. Southern then hired United Erectors, an independent corporation owned by the management of Southern, to complete the job.

Southern sued Consolidated for defaulting in the performance of the subcontract. Consolidated filed a counterclaim alleging that Southern had breached the contract. A jury trial ensued.1 The trial judge, partly on the jury’s verdict and partly disregarding it, rendered judgment for Consolidated on its counterclaim in the amount of $362,421.85, and denied all recovery to Southern. Southern brings ten points of error in its appeal; Consolidated urges eight counterpoints and two cross-points.

Appellant’s first point of error is that the jury’s answer to question number 1 was contrary to the great weight and preponderance of the evidence, and the trial court should have granted appellant’s motion for new trial. Question number 1 inquired as to “the reasonable and necessary amount of money expended by Southern to complete the project in question after Consolidated abandoned the job on June 15, 1979.” The jury’s answer was $508,860.00. Southern had offered evidence that it had paid $1,882,368.00 to United Erectors as direct costs for completion of the erection subcontract. Southern also offered evidence that it was required to pay $11,663.00 to an electric company for work ordered by Consolidated, and it incurred $95,276.00 in interest expense to complete the contract. This allegedly resulted in a total cost to Southern of $1,989,307.00 to complete the project.2

Appellant has cited no Texas case involving a suit on a construction contract, nor have we been able to find one, where a jury verdict for more than nominal damages was set aside as insufficient. Most of the reported cases are suits involving personal injury with allegations on appeal that the damages are excessive. We have authority under TEX.R.CIV.P. 328 to grant a new trial when the damages are manifestly too small or too large. The weight of authority from other jurisdictions and from leading writers in the field is that the principles underlying the determination of ex-cessiveness in damages are alike in great part to those underlying the determination of inadequacy of damages. Texas cases [101]*101generally hold that before a verdict can be said to be excessive, there must be some proof, circumstantial or direct, of bias or prejudice on the part of the jury. Absent such proof an appellate court is required to give every inference to the evidence in favor of the verdict. Roberts v. Tatum, 575 S.W.2d 138, 141 (Tex.Civ.App.—Corpus Christi 1978, writ ref d n.r.e.).

The appellant points out nothing but the size of the verdict to indicate that the jury applied the wrong measure of damages or acted out of improper bias or prejudice. The correct measure of damages in a suit where a contractor claims that a subcontractor defaulted in the performance of a construction contract is the reasonable and necessary costs of completion over and above the unpaid portion of the contract price. Freeman v. Shannon Construction Co., 560 S.W.2d 732, 735 (Tex.Civ.App.—Amarillo 1978, writ ref’d n.r.e.). This was the basis for the jury instructions given in the present case. We note that the amount of damages was not a mere matter of computation. The jury was not asked how much had Southern expended to complete the project, but what was the reasonable and necessary amount of money expended. Where the amount of the recovery rests partially or entirely in the discretion of the jury, the propriety of the award must depend on the particular facts involved. The damages here could not be measured mathematically, and considerable discretion and latitude must necessarily have been vested in the jury. Broesche v. Bullock, 427 S.W.2d 89, 97 (Tex.Civ.App.—Houston [14th Dist.] 1968, writ ref’d n.r.e.).

Where there is not a legal measure of damages, and where they are unliqui-dated, and the amount thereof is referred to the discretion of the jury, the court will not ordinarily interfere with the verdict. It is the peculiar province of the jury to decide such cases under appropriate instructions from the court, and the law does not recognize in the latter the power to substitute its own judgment for that of the jury. Although the verdict may be considerably more or less than in the judgment of the court it ought to have been, still it will decline to interfere unless the amount is so great or small as to indicate that the jury must have found it while under the influence of passion, prejudice, or gross mistake.

Southerland on Damages quoted in Laney v. Hardy, 265 S.W.2d 609, 609-10 (Tex.Civ.App.—El Paso 1954, no writ).

We do not know how the jury arrived at the sum of $508,860.00 in response to question number 1. Southern did not conclusively prove 1.8 million dollars, the amount they contend the jury should have found. Question number 1 correctly states the measure of damages. The jury made a finding that is supported by the evidence. We cannot disturb the finding merely because we might have found a different amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Myriad Development, Inc. v. Alltech, Inc.
817 F. Supp. 2d 946 (W.D. Texas, 2011)
Wesley Dahl v. Morris L. Beall
Court of Appeals of Texas, 1994
Consolidated Engineering Co. v. Southern Steel Co.
699 S.W.2d 188 (Texas Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
677 S.W.2d 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-steel-co-v-consolidated-engineering-co-texapp-1984.