Consolidated Engineering Co. v. Southern Steel Co.

699 S.W.2d 188, 28 Tex. Sup. Ct. J. 506, 1985 Tex. LEXIS 1469
CourtTexas Supreme Court
DecidedJune 19, 1985
DocketC-3433
StatusPublished
Cited by50 cases

This text of 699 S.W.2d 188 (Consolidated Engineering Co. v. Southern Steel Co.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Engineering Co. v. Southern Steel Co., 699 S.W.2d 188, 28 Tex. Sup. Ct. J. 506, 1985 Tex. LEXIS 1469 (Tex. 1985).

Opinion

GONZALEZ, Justice.

This is a suit for damages for breach of contract. The primary issue on appeal is whether the court of appeals properly interpreted the jury answers to certain special issues.

Southern Steel Company sued Consolidated Engineering Company, Inc. for damages due to alleged defaults on several construction contracts. Consolidated filed a counterclaim for damages alleging that Southern had itself breached the contracts. The trial court rendered judgment for Consolidated on its counterclaim and denied all recovery sought by Southern. Both parties appealed. The court of appeals reversed and remanded the cause to the trial court for a new trial. 677 S.W.2d 97. We reverse the judgment of the court of appeals and reform the judgment of the trial court to include attorney’s fees. As reformed, the judgment of the trial court is affirmed.

PACTS

Southern is a Texas corporation which manufactures jail facilities. Consolidated is a Tennessee corporation whose principle business is erecting steel materials and equipment. Between 1975 and 1978, Southern and Consolidated entered into twelve contracts in Texas which provided that Consolidated was to erect and install detention equipment provided by Southern in several states. One of these projects was the Shelby County Justice Center in Memphis, Tennessee. Since storage facilities were unavailable at the jobsite, Southern agreed to ship the prefabricated parts to the jobsite in a timely and orderly manner. Southern further agreed to pay Consolidated $1,014,950 for its work.

After the parties commenced performance under the contract, a dispute arose concerning Southern’s delays in shipping the materials and Consolidated’s resulting delays in installation. Consolidated expressed its dissatisfaction in a letter dated January 19, 1979, which advised Southern that:

You have left us with no choice but to consider you in absolute breach of our SUBCONTRACT AGREEMENT and to advise you that, due to that breach, we cannot and will not continue under the existing arrangement beyond Friday, January 26, 1979. While we would feel justified in an action for our cost overruns and anticipated profits, we prefer to reach some agreement with you that will result in completion of the CENTER as soon as possible.

Thereafter, representatives of Southern and Consolidated met several times in an attempt to resolve the problem. On February 28, 1979, the president of Southern wrote the president of Consolidated a letter in which he stated:

*190 [w]e are both proceeding on this joint course of action to try and get the job done for the owner and demonstrate our attitude of cooperation. By this, you and I agree that we are not changing the contract or otherwise giving up any legal rights. (Emphasis added.)

The letter also provided that Consolidated was to be reimbursed for additional work crews it had been forced to hire as a result of Southern’s failure to deliver the materials as scheduled.

Consolidated remained on the job for the next three months. However, it continued to complain of unsatisfactory delivery of materials. Consolidated finally quit on June 15, 1979, and Southern hired another company to complete the job.

Southern brought suit in Texas against Consolidated alleging that Consolidated had breached several of the contracts. It sought $1,585,571 in damages as costs to complete the Shelby project, plus attorney’s fees under Tex.Rev.Civ.Stat.Ann. art. 2226. Consolidated filed a counterclaim alleging that Southern had breached the contract by not delivering the component parts in sequence. Consolidated alleged that it was forced to abandon the project in order to mitigate its damages. It prayed for damages amounting to its cost overruns, lost profits and attorney’s fees.

Prior to the trial, the parties stipulated that they had settled all claims except the Shelby project, and that Southern owed Consolidated $26,000 on the other jobs. The jury answered the special issues as follows:

1. The “reasonable and necessary” amount expended by Southern to complete the project was $508,860.
2. Southern failed to cooperate in the fabrication and delivery of the parts.
2a. Following Southern’s failure to cooperate, Consolidated remained on the project and insisted on Southern’s performance.
3. Such failure of cooperation prevented Consolidated from performing the contract to completion.
4. The amount of loss sustained by Consolidated prior to 6/15/79 which resulted solely from Southern’s failure to cooperate was $345,998.
5. Consolidated would have realized a profit but for Southern’s failure to cooperate.
6. Consolidated would have made $215,-575 in profit had it completed the project.

The parties agreed that the issue of attorney’s fees would be tried to the court. The trial court found that the prevailing party would be entitled to attorney’s fees in the following amounts: $75,000 in the trial court, $5,000 in the court of appeals, and $2,500 in the supreme court.

The trial court disregarded the jury’s answers to issues 2a, 5 and 6, granted Consolidated judgment for damages in the amount of $362,421, 1 denied attorney’s fees, and rendered a take nothing judgment as to Southern.

On appeal, the court of appeals held that the jury’s finding in issue 2a deprived Consolidated of an excuse for abandoning the contract. The court of appeals stated that Consolidated could not use Southern’s prior breach as an excuse for nonperformance because Consolidated had elected to affirm the contract and continue performance even after declaring a breach in its letter of January 19, 1979. The court of appeals held that the entire cause had to be remanded for new trial because, in its opinion, there was no jury finding that Southern breached the contract subsequent to Consolidated’s affirmance. 2

*191 Both sides have appealed to this court. Southern asserts that the court of appeals erred in failing to render judgment that Consolidated take nothing on its counterclaim and in failing to render judgment for Southern in the net sum of $18,359. 3 Southern attacks the lack of a jury finding of “excuse” for Consolidated’s abandonment of the contract. In the alternative, Southern contends that there is no evidence to support the jury’s answers to issues 3 and 4. Consolidated alleges that the court of appeals erred in reversing the ease and that the trial court erred in failing to award lost profits and attorney’s fees.

SOUTHERN’S CLAIM

Southern contends that Consolidated breached the contract by unjustifiably refusing to complete its performance. Essential to Southern’s claim is a finding that Consolidated did in fact breach the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yazdani-Beioky v. Sharifan
550 S.W.3d 808 (Court of Appeals of Texas, 2018)
Weird Times, LLC v. Sharon Ma
Court of Appeals of Texas, 2017
David Ohrt, Sandra Hester, and Judy Sinast v. Union Gas Corporation
398 S.W.3d 315 (Court of Appeals of Texas, 2012)
Epps v. Fowler
351 S.W.3d 862 (Texas Supreme Court, 2011)
Myriad Development, Inc. v. Alltech, Inc.
817 F. Supp. 2d 946 (W.D. Texas, 2011)
DDB Technologies, L.L.C. v. MLB Advanced Media, L.P.
676 F. Supp. 2d 519 (W.D. Texas, 2009)
DDB Technologies, L.L.C. v. MLB Advanced Media, L.P.
517 F.3d 1284 (Federal Circuit, 2008)
Guerrero v. Guerra
165 S.W.3d 778 (Court of Appeals of Texas, 2005)
Candelario Marroquin v. State
112 S.W.3d 295 (Court of Appeals of Texas, 2003)
Walden v. Affiliated Computer Services, Inc.
97 S.W.3d 303 (Court of Appeals of Texas, 2003)
Traylor Bros., Inc. v. Garcia
49 S.W.3d 430 (Court of Appeals of Texas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
699 S.W.2d 188, 28 Tex. Sup. Ct. J. 506, 1985 Tex. LEXIS 1469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-engineering-co-v-southern-steel-co-tex-1985.