Giddy Holdings, Inc. v. Alpha Five Construction, Inc.; Harley Winters; And Cris W. Craft

CourtCourt of Appeals of Texas
DecidedAugust 28, 2025
Docket03-23-00659-CV
StatusPublished

This text of Giddy Holdings, Inc. v. Alpha Five Construction, Inc.; Harley Winters; And Cris W. Craft (Giddy Holdings, Inc. v. Alpha Five Construction, Inc.; Harley Winters; And Cris W. Craft) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Giddy Holdings, Inc. v. Alpha Five Construction, Inc.; Harley Winters; And Cris W. Craft, (Tex. Ct. App. 2025).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-23-00659-CV

Giddy Holdings, Inc., Appellant

v.

Alpha Five Construction, LLC; Harley Winters; and Cris W. Craft, Appellees

FROM THE COUNTY COURT AT LAW NO. 2 OF TRAVIS COUNTY NO. C-1-CV-22-003708, THE HONORABLE TODD T. WONG, JUDGE PRESIDING

OPINION

Appellant Giddy Holdings, Inc. challenges the trial court’s final order granting

appellee Alpha Five Construction, LLC’s plea to the jurisdiction and dismissing without

prejudice Giddy Holdings’ claims against all appellees. In its plea to the jurisdiction, Alpha Five

argued that unambiguous language in Giddy Holdings’ original petition confirmed that Giddy

Holdings was seeking damages in excess of the county court at law’s statutory jurisdiction. See

Tex. Gov’t Code § 25.0003(c)(1) (establishing that statutory county court has concurrent

jurisdiction with district court in civil case in which amount in controversy “exceeds $500 but

does not exceed $250,000, excluding interest, statutory or punitive damages and penalties, and

attorney’s fees and costs, as alleged on the face of the petition”). Because we conclude that

Giddy Holdings’ original petition did not unambiguously plead for damages above the trial

court’s jurisdiction, we hold that the trial court did not lack jurisdiction over this case, and we

reverse its order dismissing Giddy Holdings’ claims and remand the case. BACKGROUND 1

In April 2022, Giddy Holdings and Alpha Five entered into a contract (the

“Renovation Contract”) for the renovation of a building located in Austin, Texas (the “Project”)

for the amount of $200,000. After the parties agreed to and executed a change order, Giddy

Holdings’ obligation to pay Alpha Five increased to $295,375. Appellee Harley Winters, Alpha

Five’s president, signed the change order on behalf of Alpha Five on April 20, 2022. Brett

Jacobson, Giddy Holdings’ CEO, signed the change order on behalf of Giddy Holdings on

May 16, 2022.

On May 18, 2022, Winters signed a “certificate of contract completion and

contractor’s affidavit” and a “final waiver of lien and contractor’s affidavit” that were sent to

Giddy Holdings.2 These documents stated that the total amount of the Renovation Contract,

including extras, was $295,375 and that Alpha Five had received full payment of that amount. 3

In addition to certifying that Alpha Five and its subcontractors had been paid in full, Winters

certified that no liens had attached against the property and waived and released any and all liens

or rights of lien.

On September 28, 2022, Giddy Holdings filed suit against Alpha Five, Winters,

and appellee Cris W. Craft. Giddy Holdings alleged in its original petition that not long after

1 The facts in this section are drawn from the parties’ pleadings, motions, and the documents attached to those pleadings and motions. 2 Although Winters certified that the work had “been satisfactorily completed” in the “certificate of contract completion and contractor’s affidavit,” both parties agree that the work had not been completed and that Alpha Five continued to work on the Project until sometime in June 2022. 3 In its petition, Giddy Holdings alleges that between April 18, 2022, and May 17, 2022, it paid $293,175 to Alpha Five under the Renovation Contract. 2 Winters signed the contractor’s affidavits, Giddy Holdings and Alpha Five “entered a dispute

about Defendant Alpha Five’s unreasonable delays in performing its duties, as well as the overall

poor quality of work that Defendant Alpha Five was performing in the Project,” despite Giddy

Holdings’ advance payments for the work. Giddy Holdings further alleged that the parties’

“dispute finally came to a head on or about June 30, 2022, when Defendant Alpha Five notified

Giddy that it would be pausing its services on the Project. Simultaneously, Giddy fired

Defendant Alpha Five from the Project and barred Defendants from entering the Property any

further.” Giddy Holdings asserted that the work was not finished, so it hired the same

subcontractors Alpha Five had been using and subsequently discovered that those subcontractors

had not been fully paid by Alpha Five for their previous services, and Giddy Holdings then had

to make the subcontractors whole so that they would finish the work.

According to Giddy Holdings, on September 16, 2022, it received a demand letter

from Alpha Five demanding payment for an unpaid balance of $234,000 with no further

information or detail about how or when this debt accrued. Included with the letter was a Lien

Affidavit that had been filed by appellee Cris Craft as “Limited Agent of Alpha 5 Construction,

LLC” in the Travis County Clerk’s Office and recorded against the Property as an encumbrance.

The lien affidavit averred that the remodeling work was last performed on July 1, 2022, and that

the total amount owed to Alpha Five is $195,000.

Giddy Holdings alleged claims for breach of contract, breach of the duty of good

faith and fair dealing, fraud, tortious interference with contract, unjust enrichment, and statutory

violations of Texas Civil Practice & Remedies Code Chapter 12, which governs fraudulent liens.

In addition, Giddy Holdings sought a declaratory judgment that Alpha Five’s lien is

unenforceable and invalid.

3 For each of its claims, Giddy Holdings sought the following types of damages:

• Breach of contract — “unliquidated damages within the jurisdictional limits of this Court” and attorneys’ fees under Texas Civil Practice & Remedies Code Chapter 38;

• Breach of duty of good faith and fair dealing — damages and exemplary damages;

• Fraud — damages and exemplary damages;

• Tortious interference with contract — “an undetermined amount of damages to its business in the form of loss of further business opportunities”;

• Unjust enrichment — “restitution and payment for all benefits Defendants unlawfully obtained, in an amount to be determined by the trier of fact”;

• Chapter 12 fraudulent-lien violations — statutory penalties in the amount of $20,000, court costs, attorneys’ fees, and “exemplary damages in an amount determined by the court,” Tex. Civ. Prac. & Rem. Code § 12.002(b)(4);

• Declaratory judgment — “reasonable and necessary attorney fees that are equitable and just under Texas Civil Practice and Remedies Code § 37.009”;

• Exemplary damages under Texas Civil Practice & Remedies Code Section 41.003;

• Attorneys’ fees Texas Civil Practice & Remedies Code Section 38.001- .006 (Attorney’s Fees) and Sections 134.001-.005 (Texas Theft Liability Act); and

• Damages “within the jurisdictional limits of the Court”— “monetary relief of over $100,000 but less than $1,000,000.”

After Alpha Five and Winters had been served with the petition and failed to

answer, Giddy Holdings filed a motion for default judgment against them.4 In its motion, Giddy

4 An affidavit of general denial had been filed on behalf of Alpha Five by a non-attorney. 4 Holdings sought to have the lien declared invalid and sought $203,950.10 in actual damages

based on the alleged breach-of-contract and fraudulent-inducement claims. After a hearing on

the motion, at which Alpha Five and Winters failed to appear, the trial court granted the default

judgment against Winters, finding that he fraudulently induced Giddy Holdings into the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Thomas v. Long
207 S.W.3d 334 (Texas Supreme Court, 2006)
United Services Automobile Ass'n v. Brite
215 S.W.3d 400 (Texas Supreme Court, 2007)
Bland Independent School District v. Blue
34 S.W.3d 547 (Texas Supreme Court, 2000)
Texas Ass'n of Business v. Texas Air Control Board
852 S.W.2d 440 (Texas Supreme Court, 1993)
Dubai Petroleum Co. v. Kazi
12 S.W.3d 71 (Texas Supreme Court, 2000)
Continental Coffee Products Co. v. Cazarez
937 S.W.2d 444 (Texas Supreme Court, 1997)
Kitchen Designs, Inc. v. Wood
584 S.W.2d 305 (Court of Appeals of Texas, 1979)
City of Harker Heights v. Sun Meadows Land, Ltd.
830 S.W.2d 313 (Court of Appeals of Texas, 1992)
Peek v. Equipment Service Co. of San Antonio
779 S.W.2d 802 (Texas Supreme Court, 1989)
Lehmann v. Har-Con Corp.
39 S.W.3d 191 (Texas Supreme Court, 2001)
Tune v. Texas Department of Public Safety
23 S.W.3d 358 (Texas Supreme Court, 2000)
Beeman v. Worrell
612 S.W.2d 953 (Court of Appeals of Texas, 1981)
Pecos & Northern Texas Railway Co. v. Rayzor
172 S.W. 1103 (Texas Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
Giddy Holdings, Inc. v. Alpha Five Construction, Inc.; Harley Winters; And Cris W. Craft, Counsel Stack Legal Research, https://law.counselstack.com/opinion/giddy-holdings-inc-v-alpha-five-construction-inc-harley-winters-and-texapp-2025.