Corrections Products Company, LTD v. Gaiser Precast Construction

394 S.W.3d 818, 2013 WL 351077, 2013 Tex. App. LEXIS 850
CourtCourt of Appeals of Texas
DecidedJanuary 30, 2013
Docket08-10-00319-CV
StatusPublished
Cited by2 cases

This text of 394 S.W.3d 818 (Corrections Products Company, LTD v. Gaiser Precast Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corrections Products Company, LTD v. Gaiser Precast Construction, 394 S.W.3d 818, 2013 WL 351077, 2013 Tex. App. LEXIS 850 (Tex. Ct. App. 2013).

Opinion

OPINION

GUADALUPE RIVERA, Justice.

Appellant, Corrections Products Company, Ltd. (CPC), appeals from the trial court’s confirmation of an arbitrator’s award in favor of Appellee, Gaiser Precast Construction (Gaiser). 1 In Issue One, CPC contends the trial court lacked jurisdiction to render a judgment under the Texas General Arbitration Act (TAA). See Tex. Civ. Prac. & Rem. Code Ann. §§ 171.001-171.098 (West 2011). In Issue Two, CPC complains that the arbitrator committed a gross mistake that implies a lack of honest judgment in calculating equitable damages under a quantum meruit recovery. In Issue Three, CPC asserts the arbitration award should be vacated or modified under Section 171.088(a)(3)(A) of the Texas Civil Practice and Remedies Code because the arbitrator allegedly exceeded his powers. Tex. Civ. Prac. & Rem. Code Ann. § 171.088 (West 2011). We affirm.

BACKGROUND

On June 3, 2004, CPC, as owner, and Gaiser, as contractor, entered into a contract for the turnkey construction of an 18,000 square-foot office building. Gaiser thereafter filed suit against CPC on June 16, 2006, seeking: (1) an order foreclosing a mechanic’s and materialman’s lien on the subject property; (2) the recovery of damages arising from CPC’s breach of contract and CPC’s termination of the contract while owing Gaiser $200,000 for work performed; (3) an order of sale and writ of possession of the property, (4) pre- and post-judgment interest; (4) attorney’s fees through appeal; and (5) costs of court and other relief. 2 Gaiser alternatively sought quantum meruit relief in the amount of $200,000.

The construction contract included this arbitration provision:

15. Arbitration
Except as otherwise expressly provided in this agreement, any dispute or claim arising under or with respect to this agreement will be resolved by arbitration in San Antonio, Bexar County, Texas, in accordance with the rules of *821 the American Arbitration Association [AAA] before a panel of three (3) arbitrators, one appointed by the contractor, one appointed by the owner, and the third appointed by said association. The decision or award of a majority of the arbitrators shall be final and binding upon the parties. Any arbitral award may be entered as a judgment or order in any court of competent jurisdiction. The arbitrators may award reasonable attorney’s fees for the services rendered the party or parties prevailing in any such action or proceedings.

On June 27, 2007, CPC sought to compel arbitration under Section 15 of the contract “pursuant to the Texas Arbitration Act [TAA] or, in the alternative, under the Federal Arbitration Act [FAA],” affirmatively stated that the arbitration agreement was valid, and contended that “all claims made by [Gaiser] in this lawsuit fall within the scope of the parties’ arbitration agreement and must be submitted to arbitration.” On July 6, 2007, the trial court issued an agreed order granting the motion to compel, which recited that the order was made after considering both CPC’s motion and “the agreement of counsel.” The agreed order specified that the parties agreed to amend their agreement to arbitrate to require only one arbitrator (rather than a panel of three) to serve as arbitrator, and appointed Judge Rene Diaz as arbitrator.

The parties thereafter proceeded to arbitrate CPC’s claims. No evidence exists in the record to show that forms were ever filed with AAA or that AAA was involved with the administration of the arbitration. Mr. Mark Randolph, CPC’s original counsel, eventually withdrew and was replaced by William W. Sommers on July 24, 2008. Judge Diaz held prehearing conferences, inspected the subject property, and then conducted the arbitration between May 5 and 14, 2009.

On May 14, 2009, Judge Diaz asked Gaiser to file its closing brief by May 22, 2009, and requested that CPC file its reply brief by May 29, 2009. Judge Diaz then stated, “Rule 55 gives me 30 days from the 29th in order to complete my work. I’ll try to do it more quickly, but that’s the rule that I will be following.” No party objected to Judge Diaz’ recitation of “Rule 55.” 3

On July 29, 2009, more than 30 days from May 29, 2009, Judge Diaz issued his Arbitrator’s Award with Reasoned Opinion, in which he found that Gaiser was not entitled to any recovery based upon the theory of substantial completion. However, Judge Diaz determined that Gaiser had performed extra work beyond the terms of the contract which met the legal and factual criteria for seeking recovery under the theory of quantum meruit. Judge Diaz also found that Gaiser was the first to breach the construction contract and had wrongfully terminated the contract while in material breach of its obligations thereunder. Implementing the analysis for determining quantum meruit damages set out in Beeman v. Worrell, 612 S.W.2d 953, 955-57 (Tex.Civ.App.-Dallas 1981, no writ), Judge Diaz determined that while CPC had established that the proper cost of replacing Gaiser’s failed roof design and repairs was $43,141.88, the value of the completed project to CPC exceeded the costs paid to Gaiser, and an award to Gaiser was necessary to avoid CPC’s unjust enrichment. After determining that CPC’s defensive theory of unclean hands was not sufficiently shown, Judge Diaz *822 awarded to Gaiser quantum meruit damages in the amount of $89,794.68, attorneys’ fees in the amount of $89,945, court costs of $2,699.95, and arbitration and reasoned-opinion fees of $6,150.

Although Judge Diaz believed Gaiser, as the prevailing party, would be entitled to pre-judgment interest as required by law, Judge Diaz stated that he did not have sufficient data with which to calculate the proper amount of interest and sought additional information from the parties by which he could render a supplemental award at no charge. Judge Diaz also found that Gaiser’s lien on CPC’s property was never properly perfected and again requested additional briefing of authorities by the parties upon which he could provide a supplemental ruling. The record contains no evidence that any party alleged or objected on the basis that Judge Diaz had failed to comply with AAA rules between June 29, 2009, the date on which Judge Diaz stated he would “complete his work,” and July 29, 2009, the date on which Judge Diaz issued his “Arbitrator’s Award with Reasoned Opinion.” In fact, CPC’s counsel affirmatively represented to the trial court at the August 5, 2010, hearing to confirm or vacate the award that it had not objected to Judge Diaz’s delay in issuing an award within the 80-day time frame as prescribed under AAA Rule 42 until after Judge Diaz had rendered the initial award on July 29, 2009, and before his supplemental award on July 12, 2010.

CPC moved to vacate the July 29, 2009, arbitration award and remove Judge Diaz as arbitrator. On October 15, 2009, CPC filed its motion to vacate the arbitration award and remove Judge Diaz as arb award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
394 S.W.3d 818, 2013 WL 351077, 2013 Tex. App. LEXIS 850, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corrections-products-company-ltd-v-gaiser-precast-construction-texapp-2013.