Celtic Contructors. Inc. v. Van Pelt, Jack E. & Mary C.

CourtCourt of Appeals of Texas
DecidedDecember 12, 2002
Docket01-02-00012-CV
StatusPublished

This text of Celtic Contructors. Inc. v. Van Pelt, Jack E. & Mary C. (Celtic Contructors. Inc. v. Van Pelt, Jack E. & Mary C.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Celtic Contructors. Inc. v. Van Pelt, Jack E. & Mary C., (Tex. Ct. App. 2002).

Opinion



In The

Court of Appeals

For The

First District of Texas

____________

NO. 01-02-00012-CV



CELTIC CONSTRUCTORS, INC., Appellant



v.



JACK E. VAN PELT AND MARY C. VAN PELT, Appellees



On Appeal from the 280th District Court

Harris County, Texas

Trial Court Cause No. 2000-15620



O P I N I O N

This is an appeal of a take-nothing judgment rendered by the trial court after a jury trial. We affirm.



BACKGROUND

Jack E. Van Pelt and Mary C. Van Pelt, appellees and defendants below, entered into a contract with Celtic Constructors, Inc. (Celtic), appellant and plaintiff below, to remodel the Van Pelt's home for a contract price of $67,403.44. Celtic stopped work on the remodeling before the job was completed because, according to Celtic, the Van Pelts had stopped paying as agreed. Celtic sued the Van Pelts for breach of contract and quantum meruit. The Van Pelts counterclaimed, alleging that Celtic had not performed the work in a good and workmanlike manner and had not completed the work as agreed under the contract. The trial court granted Celtic's motion for summary judgment on the Van Pelt's counterclaims, and Celtic's claims were tried to a jury.

During the Van Pelts' presentation of evidence, the trial court granted the Van Pelts' motion for directed verdict on Celtic's claim for damages for breach of contract on the basis that Celtic had acknowledged that the cost of completion would be more than the amount remaining on the contract. The case proceeded on Celtic's quantum meriut claim. The parties stipulated that the Van Pelts had paid $61,618.38 to Celtic for the work performed. Celtic contended that, of this amount, part had been paid on the contract and part on extra work performed by Celtic.

The case was submitted to the jury. During deliberations, the jury sent out the following question: "Does the value of compensible [sic] work mean (1) the total value of the work performed or (2) the value owed to the plaintiff over/under the amount paid." The court proposed the answer: "#1--the total value of the work performed." Celtic stated that it had no objection to that answer, and the trial court provided that answer to the jury over the Van Pelts' objection.

In response to the questions in the court's charge, the jury found that (1) the Van Pelts failed to comply with their agreement with Celtic, (2) the Van Pelts' failure to comply was not excused, (3) the actions of the Van Pelts did not prevent Celtic from completing the renovation project, (4) Celtic performed compensable work for the Van Pelts, (5) the reasonable value of the compensable work was $56,570, and (6) a reasonable fee for the services of Celtic's attorney was $24,350. The judgment signed by the trial court recited the questions submitted to the jury and the jury's answers and then stated,

Based on the answers to the questions and the evidence produced at trial, it appears that the verdict is in favor of the Defendants, as the amount already paid to Celtic by Defendants is more than the value of the compensable work performed by Celtic for Defendants, as determined by the jury."



The trial court rendered a take-nothing judgment against Celtic, and Celtic appealed.

DISCUSSION

Effect of the Stipulation

In its first issue, Celtic contends that the trial court erred in disregarding the jury's finding regarding damages and attorney's fees and entering a take-nothing judgment when the Van Pelts did not file a motion for judgment notwithstanding the verdict.

The trial court did not render a judgment notwithstanding the verdict. The trial court rendered a judgment on the verdict after taking into account the amount that the Van Pelts had already paid Celtic for work performed. During the trial, out of the presence of the jury, the following occurred:

THE COURT: And before we went on the record, the Court and counsel were discussing how we account for the fact that the plaintiffs have already been paid a certain amount of money and how we would evidentially make that fit with an answer if the jury gave one on Quantum Meruit value of the work.

And the Court has suggested that the parties stipulate to the amount that the plaintiffs have already been paid, since there is no dispute on that amount.

Ms. Clark, would you state what that amount is.



MS. CLARK (counsel for Celtic): Yes, that amount is $61,618.38.



THE COURT: $61,618.38?



MS. CLARK: Yes, but with the reservation that this has not all been paid on the contract, part of it has been paid on the extras.



THE COURT: But this is the amount you've been paid -



MS. CLARK: In total, yes.



THE COURT: Mr. Pearce, do you agree that's the amount that's been paid in total?



MR. PEARCE (counsel for the Van Pelts): Yes, Your Honor, defendants do agree . . . .



An uncontroverted fact issue upon which reasonable minds cannot differ is established as a matter of law. Lehmann v. Wieghat, 917 S.W.2d 379, 382 (Tex. App.--Houston [14th Dist] 1996, writ denied). In this case, the parties agreed on the total amount that the Van Pelts had paid Celtic, and the trial court indicated to the parties that it intended to use the stipulated amount to "make that fit" with any answer that the jury gave on quantum meruit. The trial court's answer to the jury's question regarding the meaning of "the value of compensible [sic] work" was consistent with that intent. The trial court simply applied the stipulated fact to the findings of the jury to render a judgment on the jury verdict. See T.O. Stanley Boot Co. v. Bank of El Paso, 847 S.W.2d 218, 222-24 (Tex. 1992) (applying undisputed amounts of notes and balances to modify court of appeals' judgment); Beller v. DeLara, 565 S.W.2d 319, 319-20 (Tex. Civ. App.--San Antonio 1978, no writ) (on quantum meruit claim, trial court awarded sum found by jury less sum already paid by defendant).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lehmann v. Wieghat
917 S.W.2d 379 (Court of Appeals of Texas, 1996)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
Prather v. Brandt
981 S.W.2d 801 (Court of Appeals of Texas, 1998)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Southeastern Pipe Line Co., Inc. v. Tichacek
997 S.W.2d 166 (Texas Supreme Court, 1999)
Beller v. De Lara
565 S.W.2d 319 (Court of Appeals of Texas, 1978)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Celtic Contructors. Inc. v. Van Pelt, Jack E. & Mary C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/celtic-contructors-inc-v-van-pelt-jack-e-mary-c-texapp-2002.