KIVA, Inc. v. Central Texas Barricades

CourtCourt of Appeals of Texas
DecidedJanuary 8, 2010
Docket03-07-00684-CV
StatusPublished

This text of KIVA, Inc. v. Central Texas Barricades (KIVA, Inc. v. Central Texas Barricades) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KIVA, Inc. v. Central Texas Barricades, (Tex. Ct. App. 2010).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN




NO. 03-07-00684-CV

Kiva, Inc., Appellant



v.



Central Texas Barricades, Appellee



FROM THE COUNTY COURT AT LAW NO. 1 OF TRAVIS COUNTY

NO. C-1-CV-04-281824, HONORABLE ERIC SHEPPERD, JUDGE PRESIDING

M E M O R A N D U M O P I N I O N



Kiva, Inc. appeals from a judgment rendered in favor of Central Texas Barricades ("CTB"). CTB filed a suit on a sworn account seeking payment of invoices CTB submitted to Kiva in connection with its work as Kiva's subcontractor on a municipal construction project. In the alternative, CTB sought damages for breach of contract or to recover under quantum meruit. After a bench trial, the district court rendered judgment in CTB's favor on its suit on a sworn account. The district court denied Kiva's counterclaim seeking damages caused by CTB's alleged non-performance. In four issues, Kiva contends the trial court erred by rendering judgment in CTB's favor and in failing to render judgment in its favor on its counterclaim for "lost production" damages. We will affirm in part and reverse and render in part.





FACTUAL AND PROCEDURAL BACKGROUND

Kiva is a construction company primarily engaged in municipal utility and excavation work. In early 2003, Kiva bid on the City of Austin's Windsor area wastewater improvement project ("the Windsor Project"). In connection with the bid process, Kiva solicited bids from various subcontractors for services related to the project including the provision of traffic control signals and barricades. CTB submitted a quote in which it set forth the rates for providing the various detours and signs required for the project. Kiva accepted CTB's quote, and the parties executed a "Letter of Intent" which incorporated the rates included in CTB's original quote.

The City of Austin awarded Kiva the Windsor Project in March 2003, and Kiva began work in May 2003. CTB provided barricades and other traffic diversion services for the project, but by August 2003, disputes arose between Kiva and CTB regarding the scope of services included in CTB's original quote and the manner in which CTB billed for its services. Finally, in late August 2003, CTB informed Kiva that it would not perform requested maintenance of the barricades located on site at the Windsor Project. CTB contends that it refused to perform the maintenance services because the parties could not agree on whether such maintenance was included in the original quote for services, and because Kiva refused to agree to pay CTB for maintaining and/or moving the barricades. Ultimately, Kiva hired another company to perform traffic control services and asked CTB to remove its equipment from the site. In September 2003, Kiva sent CTB a check bearing the notation "Full Payment (Acct Paid in Full)" which CTB cashed. CTB also notified Kiva that it was suspending further performance under the Letter of Intent. CTB did not remove its traffic diversion equipment from the site, so the replacement subcontractor moved the equipment off the street and stored it.

In October 2003, Kiva and CTB began negotiating CTB's return to the Windsor Project. These negotiations were motivated by the City of Austin's requirement that a certain percentage of work on municipal projects be performed by qualifying minority-owned subcontractors. On October 8th, during the course of these negotiations, Kiva forwarded a new proposed contract to CTB. CTB made changes to the contract including deleting the liquidated damages provision and adding a provision requiring that Kiva pay CTB $375 for each time CTB visited the site to maintain its equipment. Kiva did not sign the modified contract.

At Kiva's request, CTB did return to work on the Windsor Project on December 2, 2003. CTB performed services for Kiva until December 18th, when CTB removed its personnel from the jobsite and filed a claim for $13,071.21 against Kiva's payment bond. CTB finally removed its equipment from the jobsite in January 2004. In November 2004, CTB filed a suit on a sworn account for $13,071.21. In the alternative, CTB alleged a cause of action for breach of a contract the parties allegedly entered into in October 2003, or for recovery under quantum meruit. Kiva filed a sworn denial of the account and filed a counterclaim for damages arising out of CTB's alleged failure to perform its obligations in August 2003 and in December 2003.

After a bench trial, the district court rendered judgment in favor of CTB for $12,454.18 "on the claim based on a Sworn Account," plus attorneys' fees, pre- and post-judgment interest and costs, and denied Kiva's counterclaim. In its findings of fact, the district court found that Kiva had paid CTB in full for all work conducted prior to September 15, 2003, that CTB presented an accurate systematic statement of account for goods and services provided thereafter, and that Kiva had failed to pay the account. The district court also found that Kiva and CTB entered into a contract dated on or about October 8, 2003, that CTB had performed services pursuant to that contract, and that Kiva breached the contract. The district court further found that CTB satisfied the requirements of a claim under quantum meruit.

In this appeal, Kiva challenges the legal sufficiency of the evidence supporting an award of damages on CTB's sworn account, for breach of contract, or under quantum meruit. Kiva also contends that it conclusively proved its right to recover on its counterclaim for damages caused by CTB's failure to provide traffic control services in December 2003.



STANDARD OF REVIEW

Findings of fact entered in a case tried to the court have the same force and dignity as a jury verdict. Anderson v. City of Seven Points, 806 S.W.2d 791, 794 (Tex. 1991). When, as here, the record contains a complete statement of facts, we are not bound by the trial court's findings, and we review them by the same standards used in reviewing the evidence supporting a jury's verdict. Middleton v. Kawasaki Steel Corp., 687 S.W.2d 42, 44 (Tex. App.--Houston [14th Dist.] 1985), writ ref'd n.r.e. per curiam, 699 S.W.2d 199 (Tex. 1985). In a legal sufficiency review, we credit evidence favorable to the finding if a reasonable fact-finder could, disregard contrary evidence unless a reasonable fact-finder could not, and reverse the fact-finder's determination only if the evidence presented would not enable a reasonable and fair-minded person to reach the judgment under review. City of Keller v. Wilson, 168 S.W.3d 802, 827 (Tex. 2005). We will sustain the legal-sufficiency challenge if the record reveals: (1) the complete absence of evidence supporting the finding; (2) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to support the finding; (3) the evidence offered to prove the finding is no more than a mere scintilla; or (4) the evidence conclusively establishes the opposite of the finding. Id. at 810-11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Material Partnerships, Inc. v. Ventura
102 S.W.3d 252 (Court of Appeals of Texas, 2003)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
City of Ingleside v. Stewart
554 S.W.2d 939 (Court of Appeals of Texas, 1977)
Northwest Park Homeowners Ass'n, Inc. v. Brundrett
970 S.W.2d 700 (Court of Appeals of Texas, 1998)
Glass v. Anderson
596 S.W.2d 507 (Texas Supreme Court, 1980)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Middleton v. Kawasaki Steel Corp.
687 S.W.2d 42 (Court of Appeals of Texas, 1985)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Mays v. Pierce
203 S.W.3d 564 (Court of Appeals of Texas, 2006)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
Double Diamond, Inc. v. Hilco Electric Cooperative, Inc.
127 S.W.3d 260 (Court of Appeals of Texas, 2003)
Boland v. Mundaca Investment Corp.
978 S.W.2d 146 (Court of Appeals of Texas, 1998)
Gilbert v. Pettiette
838 S.W.2d 890 (Court of Appeals of Texas, 1992)
City of Harker Heights v. Sun Meadows Land, Ltd.
830 S.W.2d 313 (Court of Appeals of Texas, 1992)
MTrust Corp. NA v. LJH CORP.
837 S.W.2d 250 (Court of Appeals of Texas, 1992)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Mantis v. Resz
5 S.W.3d 388 (Court of Appeals of Texas, 1999)
Woodard v. Southwest States, Inc.
384 S.W.2d 674 (Texas Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
KIVA, Inc. v. Central Texas Barricades, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiva-inc-v-central-texas-barricades-texapp-2010.