PMC Chase, LLP and Steve Turnbow v. Branch Structural Solutions, Inc.

CourtCourt of Appeals of Texas
DecidedJanuary 28, 2020
Docket05-18-01383-CV
StatusPublished

This text of PMC Chase, LLP and Steve Turnbow v. Branch Structural Solutions, Inc. (PMC Chase, LLP and Steve Turnbow v. Branch Structural Solutions, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PMC Chase, LLP and Steve Turnbow v. Branch Structural Solutions, Inc., (Tex. Ct. App. 2020).

Opinion

AFFIRM; Opinion Filed January 28, 2020

In The Court of Appeals Fifth District of Texas at Dallas No. 05-18-01383-CV

PMC CHASE, LLP AND STEVE TURNBOW, Appellants V. BRANCH STRUCTURAL SOLUTIONS, INC., Appellee

On Appeal from the County Court at Law No. 5 Dallas County, Texas Trial Court Cause No. CC-16-01773-E

MEMORANDUM OPINION Before Justices Myers, Schenck, and Carlyle Opinion by Justice Carlyle

Construction contractor Branch Structural Solutions, Inc. (BSS) sued PMC Chase, LLP

and its manager, Steve Turnbow (collectively, appellants), seeking payment for work performed.

After a bench trial, the trial court found Mr. Turnbow personally liable for breach of contract and

PMC Chase liable in quantum meruit. The trial court signed a judgment awarding BSS $32,627.10

in damages and $23,860.00 in attorney’s fees against Mr. Turnbow and PMC Chase, jointly and

severally.

In six issues on appeal, appellants challenge the sufficiency of the evidence regarding

damages and contend the trial court erred by (1) finding that Mr. Turnbow contracted for the work

in his personal capacity, (2) not limiting BSS to a quantum meruit recovery, and (3)“awarding judgment for the same damages on both breach of contract and quantum meruit.” We affirm in this

memorandum opinion. See TEX. R. APP. P. 47.4.

Background

BSS is a “structural steel fabricator and erector.” Its president is Kerry Branch. In October

2015, a mutual friend introduced Mr. Branch to Mr. Turnbow, who asked Mr. Branch to submit a

proposal regarding a commercial construction project. On December 9, 2015, Mr. Turnbow signed

a one-page document prepared by BSS (the contract). The contract stated “Attention: Steve

Turnbow” and listed four items to be installed by BSS for a total price of $32,450.00: (1) “Columns

and beams,” (2) “1 set of dumpster gates with hardware,” (3) “1 roof access ladder (No Safety

Cage),” and (4) “RTU Frame.” Mr. Turnbow also accepted a subsequent change order that

included $677.10 in additional charges.

On December 21, 2015, BSS sent appellants an invoice for $33,127.10, with a January 20,

2016 “due date.”1 No payment was made. In April 2016, BSS filed this lawsuit against PMC Chase

and Mr. Turnbow. BSS’s petition asserted claims for breach of contract and quantum meruit, in

the alternative, against both defendants based on work BSS performed. PMC Chase and Mr.

Turnbow filed a joint breach of contract counterclaim, contending BSS failed to complete the work

as agreed.

At trial, BSS abandoned its breach of contract claim against PMC Chase, stating “the

contract was with just Mr. Turnbow individually.” Appellants argued at trial that Mr. Turnbow

was “just an agent” for PMC Chase and therefore was not personally liable on the contract. Mr.

Turnbow testified:

Q. So you agree that this is a legally binding contract? A. Yes. 1 BSS sent the invoice to: Steve Turnbow PMC Chase LLP 2800 Park Dr., Suite #100 Arlington, TX 76015 –2– Q. And that contract would have been signed by you individually; is that correct? A. I was signing for my company. Q. . . . Where on this document does it say that you’re signing for your company? A. It doesn’t. .... Q. And is this document addressed to you and signed by you individually? Is that correct? A. Yes. Q. And nowhere on the document does it say that you’re signing on behalf of PMC Chase? A. No.

Mr. Branch testified,

Q. . . . When you contracted with—when this document was signed, did you know that Mr. Turnbow represented PMC Chase at that time? A. Yes, sir. Q. Okay. When he signed this document, did you believe he was signing—what was your understanding of how he was signing it? A. He was an officer of the company and he was entering into an agreement. .... Q. . . . You—your understanding was that when he signed this he was personally guaranteeing that he was going to pay; is that correct? A. Yes, sir. Q. That was your understanding? A. Yes.

As to damages, BSS acknowledged at trial that two contract items, the dumpster gates and

roof access ladder, were never installed. Mr. Branch testified the installation of those two items

accounted for about $500.00 of the contract price and was not completed because appellants did

not supply the gates and ladder as required. According to Mr. Branch, BSS completed all other

work under the contract, including installation of “[t]he columns and beams,” “the RTU frame,”

and the additional items described in the change order. He stated that after the invoice was sent,

he and Mr. Turnbow had “discussions” regarding “items needed to complete his roof structure,”

but that work was “different than what the original contract was for.” Mr. Branch provided a price

for that additional work, but no agreement was reached and BSS did not perform that work.

Mr. Branch testified BSS began working on the project “probably end of November,

maybe” and his crew was on the job site “for several weeks.” The size of his crew varied from –3– three to six workers, depending on that day’s work. On cross-examination by appellants’ counsel,

Mr. Branch testified his “cost per worker” is “typically around $85 an hour per man” and his crew

worked on the project “probably 10 hours a day” for “probably three weeks.”

According to Mr. Turnbow, BSS began work several days after the contract was signed

and worked a total of about five days. Mr. Turnbow testified the “RTU frame” was “partially

completed,” but BSS failed to complete rooftop “decking” he believed was required as part of that

contract item. He “thought that the amount that [BSS] was asking for was not correct with what

was done” and paid BSS nothing. He stated he (1) subsequently paid other contractors $11,500.00

to complete the contract work and (2) believes the value of the work BSS completed is “around

$15,000,” “based on what it took to complete it.”

The trial court’s judgment stated (1) “[o]n the claim of Breach of Contract, the Court finds

in favor of [BSS] and against Defendant Steve Turnbow, in the amount of $32,627.10”; (2) “[o]n

the claim of Quantum Meruit, the Court finds in favor of [BSS] and against Defendant, PMC

Chase, LLP, in the amount of $32,627.10”; and (3) “Steve Turnbow and PMC Chase, LLP are

joint and severally liable for the judgment of $32,627.10 plus interest and for the attorney’s fees

in the amount of $23,860.00 plus interest.” On appellants’ request, the trial court also filed findings

of fact and conclusions of law.2

2 The trial court’s findings of fact and conclusions of law stated:

Findings of Fact A. Plaintiff entered into a signed contract with Steve Turnbow on December 9, 2015. B. The Contract was to supply labor and equipment . . . for a building being built for PMC Chase LLP. C. Plaintiff completed the work with the exception of installing 1 set of dumpster gates with hardware and 1 roof access ladder. D. PMC Chase LLP is owned by Steve Turnbow and the work done by Plaintiff directly benefited PMC Chase LLP as PMC Chase LLP owns the building that was being constructed. E. Plaintiff was never paid for any of the work done by either Steve Turnbow or PMC Chase LLP. .... Conclusions of Law A. Plaintiff complied with the terms of the contract with the exception of installing 1 set of dumpster doors and one roof access ladder. B. Defendant, Steve Turnbow, breached the terms of the contract by failing to pay Plaintiff the money owed in the amount of $32,627.10. C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lamajak, Inc. v. Frazin
230 S.W.3d 786 (Court of Appeals of Texas, 2007)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Seale v. Nichols
505 S.W.2d 251 (Texas Supreme Court, 1974)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
Friendswood Development Co. v. McDade + Co.
926 S.W.2d 280 (Texas Supreme Court, 1996)
Waite Hill Services, Inc. v. World Class Metal Works, Inc.
959 S.W.2d 182 (Texas Supreme Court, 1998)
Randy v. Squires Construction, Inc.
188 S.W.3d 396 (Court of Appeals of Texas, 2006)
Landerman v. State Bar of Texas
247 S.W.3d 426 (Court of Appeals of Texas, 2008)
Dal-Chrome Co. v. Brenntag Southwest, Inc.
183 S.W.3d 133 (Court of Appeals of Texas, 2006)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Montclair Corporation v. Earl N. Lightfoot Paving Co.
417 S.W.2d 820 (Court of Appeals of Texas, 1967)
Lassiter v. Rotogravure Committee, Inc.
727 S.W.2d 8 (Court of Appeals of Texas, 1987)
Lyons v. Montgomery
701 S.W.2d 641 (Texas Supreme Court, 1985)
Boyce Iron Works, Inc. v. Southwestern Bell Telephone Co.
747 S.W.2d 785 (Texas Supreme Court, 1988)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Green Oaks, Ltd. v. Cannan
749 S.W.2d 128 (Court of Appeals of Texas, 1987)
Wright Group Architects-Planners, P.L.L.C. v. Pierce
343 S.W.3d 196 (Court of Appeals of Texas, 2011)
Kachina Pipeline Company, Inc. v. Michael D. Lillis
471 S.W.3d 445 (Texas Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
PMC Chase, LLP and Steve Turnbow v. Branch Structural Solutions, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pmc-chase-llp-and-steve-turnbow-v-branch-structural-solutions-inc-texapp-2020.