Parkview General Hospital, Inc. v. Eppes

447 S.W.2d 487
CourtCourt of Appeals of Texas
DecidedOctober 30, 1969
Docket461
StatusPublished
Cited by34 cases

This text of 447 S.W.2d 487 (Parkview General Hospital, Inc. v. Eppes) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parkview General Hospital, Inc. v. Eppes, 447 S.W.2d 487 (Tex. Ct. App. 1969).

Opinions

OPINION

NYE, Justice.

This is a suit for architectural fees alleged to be due and owing for work performed in the drawing and preparation of plans and specifications for the construction of certain additions to Parkview General Hospital located in the City of Corpus Christi, Texas. The agreement between the parties was covered by a written contract. The project was never constructed and a dispute arose between the parties as to the amount due and owing under the contract for the work performed by the architect. The written contract sued upon was accompanied by a letter agreement written by the architect making the contract conditional upon getting a satisfactory loan commitment and permission from the City of Corpus Christi to build the project.

The trial of the case was had before a jury which answered numerous special issues and found in effect that the total compensation that would be due the architect based upon the project construction costs would have been the sum of $27,062.-00. This amount would be subject to an offset of $10,980.00 which appellant had previously paid. The jury also found that at least one of the conditions set forth in the letter agreement, had not been met and that such condition had not been waived. The trial court, upon motion of the architect, disregarded these and other certain jury findings and rendered judgment for [489]*489the architect for the amount of $18,522.00 which included $2500.00 as reasonable attorney fees.

The appellant built the existing Parkview General Hospital in 1961-1962. The architect did the architectural work on the original hospital and upon a 25-room addition in 1963. In 1965 appellant decided to put on a second addition to the hospital and negotiated with and executed a contract with the architect to do the architectural work for the new addition. The contract was executed by the appellant’s administrator only after the architect had delivered a letter setting forth certain conditions. The letter from the architect reads as follows:

“April 15, 1965
Mr. Harold Hartgraves, Administrator
Parkview General Hospital
4626 Weber
Corpus Christi, Texas
Dear Harold:
I will bring an ‘Agreement between Owner and Architect’ to you tomorrow. This is for two purposes: first and foremost, so that I can borrow some cash on a contract, the second being to officially recognize that I have the job.
I realize there are several hurdles to cross. First, you must obtain the City’s permission to build, as usual. Second, you must obtain a committment from Aetna Life, which I understand to be substantially more than we will need for the second addition. Neither of these is a real obstacle, of course, but to protect your interests: I hereby recognize that if either the city does not grant permission to build, or if you fail to obtain a satisfactory committment, that our ‘Agreement between Owner and Architect’ shall be null and void.
Sincerely,
Paul G. Eppes” (Emphasis supplied)

The project was slow in getting started. Even though the contract for architectural services was executed on April 16, 1965, thirteen months later the architect had only billed the appellant for 15% of the entire fee for work he had completed to that time. In September 1966 a loan commitment was obtained. About this same time application was made to the City Zoning and Planning Commission for a change of zoning. Since the hospital was in a residential area it was necessary for the appellant to seek a change of zoning from residential to AB zoning classification. The Zoning and Planning Commission approved appellant’s application as submitted. When the application for zoning came before the City Council upon recommendation of the Zoning and Planning Commission, the application was tabled for further study.

The evidence shows that quite a controversy existed between the City Council and the applicants for the zoning change and building permit. There were a number of objections filed by the general public. After considerable study, the Council decided to grant a special council zoning permit in the form of a special ordinance. This ordinance stated that the applicants would be granted a special permit for the construction of the project, but the permit would be subject to accepting and executing an indemnification agreement between the City of Corpus Christi and the Park-view General Hospital, Inc., which was attached and made a part of the ordinance. The indemnification agreement was designed to protect the City from any and all liability arising out of the building of the project on a sanitary fill which was the location site of the hospital addition- The indemnification agreement was never signed or accepted by the appellant. The evidence shows that sometime between the latter part of October, when the appellant received the indemnification agreement, and the first part of December, notice was given to the architect to discontinue work on the plans. At least from December 2 and thereafter, no additional work was performed by the architect nor were any sums other than $10,980.00 previously paid, remitted to him.

[490]*490Plaintiff’s case was tried on the theory that the architect was entitled to 100% of the total architectural fee. This was based upon 6% of the project construction cost. The architect had billed the owners up and until the dispute arose on the basis of work completed at the rate of 6% of an estimated project cost. This was considerably less than actual project cost permitted under the agreement between the owner and architect. Although it was undisputed that the architect had completed only 69% of the total work, judgment was entered for 100% of the project construction cost, less the amount previously paid, plus attorney fees.

The jury in response to special issues found that the hospital administrator who had executed the various contracts was operating within the scope of his authority as agent of the hospital and did in fact enter into the contract of employment with the architect to draw the plans. The jury further found the amount of the project construction cost, the percentage of architectural work completed, the rate of compensation based on the construction cost. Additionally the jury refused to find (Special Issue #18) that the defendant hospital owners waived the conditions precedent stated by the architect in his letter to the hospital owners. The jury found that the hospital had obtained a satisfactory loan commitment. (One of the stated conditions precedent). However, in Special Issue 22 the jury found that the Parkview General Hospital did not obtain a satisfactory permit from the City of Corpus Christi for the construction of the second addition to Park-view General Hospital (the other condition precedent). The final issue was No. 23: “Do you find from a preponderance of the evidence that there was a waiver by the defendant Parkview General Hospital of the failure to obtain a satisfactory permit from the City of Corpus Christi to erect a second addition to Parkview General Hospital?” The jury answered “No.”

The defendants had plead various defenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re CS Estate Inc.
558 B.R. 292 (W.D. Wisconsin, 2016)
Mark Pereida v. State
Court of Appeals of Texas, 2010
Town Bank v. City Real Estate Development, LLC
2009 WI App 160 (Court of Appeals of Wisconsin, 2009)
Beard Family Partnership v. Commercial Indemnity Insurance Co.
116 S.W.3d 839 (Court of Appeals of Texas, 2003)
Fox Ex Rel. Fricker v. Catholic Knights Insurance Society
2003 WI 87 (Wisconsin Supreme Court, 2003)
Insurance Corp. of America v. Webster
906 S.W.2d 77 (Court of Appeals of Texas, 1995)
Weng Enterprises, Inc. v. Embassy World Travel, Inc.
837 S.W.2d 217 (Court of Appeals of Texas, 1992)
Life Insurance Co. of the Southwest v. Verex Assurance, Inc.
810 S.W.2d 416 (Court of Appeals of Texas, 1991)
Kocinski v. Home Insurance Co.
433 N.W.2d 654 (Court of Appeals of Wisconsin, 1988)
Malone v. Carl Kisabeth Co., Inc.
726 S.W.2d 188 (Court of Appeals of Texas, 1987)
Farmer Foundation Co. v. Leach
680 S.W.2d 828 (Court of Appeals of Texas, 1984)
Gordin v. Shuler
635 S.W.2d 559 (Court of Appeals of Texas, 1982)
Baker v. Lockheed Aircraft Service Co.
584 S.W.2d 369 (Court of Appeals of Texas, 1979)
Hohenberg Bros. Co. v. George E. Gibbons & Co.
526 S.W.2d 570 (Court of Appeals of Texas, 1975)
Hurst v. Rush
514 S.W.2d 472 (Court of Appeals of Texas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
447 S.W.2d 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parkview-general-hospital-inc-v-eppes-texapp-1969.