Dreben, J.
In Thomas O’Connor & Co. v. Medford, 16 Mass. App. Ct. 10 (1983), we considered the appeal of the [762]*762city from a judgment entered on October 23, 1981, awarding the general contractor $1,658,317.36 in damages for breach of a construction contract. We affirmed the trial court’s judgment in all respects except for two percentage additions to direct costs covering overhead, superintendence and profits. We suggested that the trial judge, in his discretion, might enter a partial judgment covering all items except for the two percentage additions. The latter items were discussed in section 5(b) of our previous opinion (the 5[b] items). Id. at 18, 19.1
The questions on this second appeal by the city are (1) whether the judgment entered on January 10,1984, after further hearing in the trial court, was consistent with our remand order, and (2) whether the 1984 judgment applied the proper interest rate. We answer no to both questions.
1. Treatment of 5(b) items after our 1983 remand. In our decision at page 18, we concluded that to the extent the percentage additions to direct costs covered overhead and superintendence costs, they were not unjustified. We held, however, that an addition attributable to a loss of profits would be improper unless the contractor could show that there were, in fact, lost profits. The matter was remanded “for a determination ... of the lost profits, if any, which were occasioned by the city’s breach.” Ibid. On remand, the trial judge found that the “plaintiff has failed to prove any lost profit because no evidence was offered in support of any lost profit.” Instead of reducing the damages, the judge permitted the contractor to submit additional evidence on the items of overhead and superintendence. He found that the damages for those two items were $437,249, thus exceeding the amount attributable to the 5(b) items in the 1981 judgment. See note 1, supra. The final judgment entered on January 10, 1984, reflected this increase.
We intended by our remand that a finding of no lost profits would result in a reduction in the percentage additions so as [763]*763to eliminate the share attributable to profits.2 Our remand was not intended to authorize the taking of evidence to increase the previous award on account of superintendence and overhead. Accordingly, the judgment, insofar as it pertains to the items covered in 5(b) of our previous opinion, is vacated, and the matter is remanded to eliminate the profit element from the percentage additions.3
2. Interest on partial judgment. In accordance with our suggestion, a partial judgment entered on October 12, 1983, covering all items except the percentage additions. Interest was awarded as follows: “six per cent (6%) per annum from December 29, 1972 to August 14, 1974, and eight per cent (8%) per annum thereafter . . . .” The judgment contained the following explanation: “Damages were assessed in this action before July 1, 1982.”4
Subsequent to the entry of the partial judgment, the judge increased the damages for the 5(b) items as recounted in part 1 of this opinion. He ordered that “final judgment enter to incorporate the partial judgment . . . previously . . . entered .... with interest thereon at the current rates, because . . . [764]*764assessment occurred today [January 5, 1984] as opposed to in the past.” A judgment entered on January 10, 1984, with interest at the rate of twelve percent from the date of the commencement of the action on December 29, 1972, to January 5, 1984.5
The interest award was erroneous. Had the October 23, 1981, judgment been affirmed in whole, there is no question that the twelve percent rate would not have applied. That rate is applicable only to actions where damages are assessed on or after July 1, 1982. See note 4, supra. In Patry v. Liberty Mobilehome Sales, Inc., 394 Mass. 270, 273 (1985), the court upheld a computation of interest at eight percent despite the plaintiff’s contention that damages were not assessed until 1983, when the trial court’s judgment was affirmed. The Supreme Judicial Court rejected the plaintiff’s claim, saying: “The damages were assessed by the trial court in 1981. The appellate process did not alter the judgment based on that assessment. Affirmation of a judgment does not involve the assessment of damages.” Ibid.
On the other hand, had the October 23, 1981, judgment been reversed, and a new trial ordered, the new judgment, if entered after July 1, 1982, would have included interest at the rate of twelve percent from the date of the commencement of the action. See Tosti v. Ayik, 394 Mass. 482, 484, 499-500 (1985).
Here, the October 23, 1981, judgment was affirmed except for the 5(b) items. A somewhat similar situation occurred in Kneeland v. American Loan & Trust Co., 138 U.S. 509, 511 [765]*765(1891), decided before the adoption of the Federal Rules of Appellate Procedure.6 On a prior appeal in Kneeland, the Supreme Court had “reversed” and “remanded” with “instructions to strike out allowances for rentals prior to December 1, 1883” but to allow subsequent rentals as determined by the lower court to stand. On remand, the lower court interpreted the Supreme Court’s mandate as affirming so much of the decrees as provided for the rental allowances subsequent to December 1, 1883. In its new decrees, the lower court awarded postjudg[766]*766ment interest on those subsequent allowances from the date of its former decrees. The Supreme Court affirmed, stating at 511-512,
“While the former decrees were in terms reversed, and the cases remanded for the entering of new decrees, yet, the terms of those new decrees were specifically stated, and in so far as the separate and distinct matters embraced in the former decrees were ordered to be incorporated into the new, it is so to be regarded as pro tanto an affirmance. . . . The rights of parties are not to be sacrificed to the mere letter, and whether the language used was reversed, modified, or affirmed in part and reversed in part, is immaterial. Equity looks beyond these words of description to see what was in fact ordered to be done.”
The analogy of Kneeland is helpful even though in the present case additional evidence had to be taken as to the portion of the judgment which was not affirmed (the 5[b] items). Where, as here, 1) the portion of the judgment which was affirmed was clearly separated from the part which was vacated for additional proceedings; 2) the amount of the portion which was affirmed was ascertained or ascertainable in dollar amount; and 3) where the appellate court itself suggested the entry of a partial judgment in the amount which was affirmed, the principles of Patry v. Liberty Mobilehome Sales, Inc., 394 Mass. at 273, should be applied to the portion of the judgment which was affirmed. Those damages should, therefore, be considered “assessed” at the time of the original judgment. See also Frank D. Wayne Associates v. Lussier, 394 Mass. 619, 621-622 & n.2 (1985).
Free access — add to your briefcase to read the full text and ask questions with AI
Dreben, J.
In Thomas O’Connor & Co. v. Medford, 16 Mass. App. Ct. 10 (1983), we considered the appeal of the [762]*762city from a judgment entered on October 23, 1981, awarding the general contractor $1,658,317.36 in damages for breach of a construction contract. We affirmed the trial court’s judgment in all respects except for two percentage additions to direct costs covering overhead, superintendence and profits. We suggested that the trial judge, in his discretion, might enter a partial judgment covering all items except for the two percentage additions. The latter items were discussed in section 5(b) of our previous opinion (the 5[b] items). Id. at 18, 19.1
The questions on this second appeal by the city are (1) whether the judgment entered on January 10,1984, after further hearing in the trial court, was consistent with our remand order, and (2) whether the 1984 judgment applied the proper interest rate. We answer no to both questions.
1. Treatment of 5(b) items after our 1983 remand. In our decision at page 18, we concluded that to the extent the percentage additions to direct costs covered overhead and superintendence costs, they were not unjustified. We held, however, that an addition attributable to a loss of profits would be improper unless the contractor could show that there were, in fact, lost profits. The matter was remanded “for a determination ... of the lost profits, if any, which were occasioned by the city’s breach.” Ibid. On remand, the trial judge found that the “plaintiff has failed to prove any lost profit because no evidence was offered in support of any lost profit.” Instead of reducing the damages, the judge permitted the contractor to submit additional evidence on the items of overhead and superintendence. He found that the damages for those two items were $437,249, thus exceeding the amount attributable to the 5(b) items in the 1981 judgment. See note 1, supra. The final judgment entered on January 10, 1984, reflected this increase.
We intended by our remand that a finding of no lost profits would result in a reduction in the percentage additions so as [763]*763to eliminate the share attributable to profits.2 Our remand was not intended to authorize the taking of evidence to increase the previous award on account of superintendence and overhead. Accordingly, the judgment, insofar as it pertains to the items covered in 5(b) of our previous opinion, is vacated, and the matter is remanded to eliminate the profit element from the percentage additions.3
2. Interest on partial judgment. In accordance with our suggestion, a partial judgment entered on October 12, 1983, covering all items except the percentage additions. Interest was awarded as follows: “six per cent (6%) per annum from December 29, 1972 to August 14, 1974, and eight per cent (8%) per annum thereafter . . . .” The judgment contained the following explanation: “Damages were assessed in this action before July 1, 1982.”4
Subsequent to the entry of the partial judgment, the judge increased the damages for the 5(b) items as recounted in part 1 of this opinion. He ordered that “final judgment enter to incorporate the partial judgment . . . previously . . . entered .... with interest thereon at the current rates, because . . . [764]*764assessment occurred today [January 5, 1984] as opposed to in the past.” A judgment entered on January 10, 1984, with interest at the rate of twelve percent from the date of the commencement of the action on December 29, 1972, to January 5, 1984.5
The interest award was erroneous. Had the October 23, 1981, judgment been affirmed in whole, there is no question that the twelve percent rate would not have applied. That rate is applicable only to actions where damages are assessed on or after July 1, 1982. See note 4, supra. In Patry v. Liberty Mobilehome Sales, Inc., 394 Mass. 270, 273 (1985), the court upheld a computation of interest at eight percent despite the plaintiff’s contention that damages were not assessed until 1983, when the trial court’s judgment was affirmed. The Supreme Judicial Court rejected the plaintiff’s claim, saying: “The damages were assessed by the trial court in 1981. The appellate process did not alter the judgment based on that assessment. Affirmation of a judgment does not involve the assessment of damages.” Ibid.
On the other hand, had the October 23, 1981, judgment been reversed, and a new trial ordered, the new judgment, if entered after July 1, 1982, would have included interest at the rate of twelve percent from the date of the commencement of the action. See Tosti v. Ayik, 394 Mass. 482, 484, 499-500 (1985).
Here, the October 23, 1981, judgment was affirmed except for the 5(b) items. A somewhat similar situation occurred in Kneeland v. American Loan & Trust Co., 138 U.S. 509, 511 [765]*765(1891), decided before the adoption of the Federal Rules of Appellate Procedure.6 On a prior appeal in Kneeland, the Supreme Court had “reversed” and “remanded” with “instructions to strike out allowances for rentals prior to December 1, 1883” but to allow subsequent rentals as determined by the lower court to stand. On remand, the lower court interpreted the Supreme Court’s mandate as affirming so much of the decrees as provided for the rental allowances subsequent to December 1, 1883. In its new decrees, the lower court awarded postjudg[766]*766ment interest on those subsequent allowances from the date of its former decrees. The Supreme Court affirmed, stating at 511-512,
“While the former decrees were in terms reversed, and the cases remanded for the entering of new decrees, yet, the terms of those new decrees were specifically stated, and in so far as the separate and distinct matters embraced in the former decrees were ordered to be incorporated into the new, it is so to be regarded as pro tanto an affirmance. . . . The rights of parties are not to be sacrificed to the mere letter, and whether the language used was reversed, modified, or affirmed in part and reversed in part, is immaterial. Equity looks beyond these words of description to see what was in fact ordered to be done.”
The analogy of Kneeland is helpful even though in the present case additional evidence had to be taken as to the portion of the judgment which was not affirmed (the 5[b] items). Where, as here, 1) the portion of the judgment which was affirmed was clearly separated from the part which was vacated for additional proceedings; 2) the amount of the portion which was affirmed was ascertained or ascertainable in dollar amount; and 3) where the appellate court itself suggested the entry of a partial judgment in the amount which was affirmed, the principles of Patry v. Liberty Mobilehome Sales, Inc., 394 Mass. at 273, should be applied to the portion of the judgment which was affirmed. Those damages should, therefore, be considered “assessed” at the time of the original judgment. See also Frank D. Wayne Associates v. Lussier, 394 Mass. 619, 621-622 & n.2 (1985).
With the October 23, 1981, date as the date of assessment, the plaintiff is now entitled to a partial judgment as follows:
(1) The principal amount, as set forth in subparagraph
(a) of note 5, supra.
(2) Interest at six percent of the principal amount from December 29, 1972, to August 14, 1974, as set forth in [767]*767subparagraph (b) of note 5, supra. (Rate determined by St. 1968, c. 763.)
(3) Interest at eight percent on the principal amount from August 14, 1974, to October 23, 1981, the date of entry of the initial judgment in the trial court. (Rate determined by St. 1974, c. 224, § 2, effective August 14, 1974.)7
(4) Postjudgment interest on the sum of the amounts listed in subparagraphs 1-3 above from October 23, 1981, to the date of payment, February 6, 1984. The postjudgment interest should be computed at the rate of six percent for the reasons explained in Peak v. Massachusetts Bay Transp. Authy., ante 726, 728-729 (1985).
3. Further proceedings. The judgment entered on January 10, 1984, is vacated, and a partial judgment is to enter in accordance with the four numbered items of the last paragraph of part 2 of this opinion. Since the judge who originally heard this case is no longer on the bench, another judge is to take evidence on the 5(b) items and is to reduce the percentage additions consistent with the discussion contained in part 1 of this opinion.
So ordered.