Spitcaufsky v. State Highway Commission

159 S.W.2d 647, 349 Mo. 117, 1941 Mo. LEXIS 495
CourtSupreme Court of Missouri
DecidedDecember 16, 1941
StatusPublished
Cited by17 cases

This text of 159 S.W.2d 647 (Spitcaufsky v. State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spitcaufsky v. State Highway Commission, 159 S.W.2d 647, 349 Mo. 117, 1941 Mo. LEXIS 495 (Mo. 1941).

Opinion

*120 ELLISON, J.

This case has been reassigned to the writer. The plaintiff-respondent was the successful bidder for the construction of a State road project designated as Route SE., Sec. 2, in Platte County, tó be completed on December 1, 1936. After the work had started the defendant-appellant State Highway Commission (hereinafter called the Commission) changed the design for a large culvert. The Commission claimed the change was necessitated by soil conditions revealed by excavation and by respondent’s faulty method of excavating for the culvert as originally designed. The respondent contended his method of excavating was correct; that it conformed to the directions of the Commission’s supervisors; that the Commission’s action was arbitrary and capricious, constituting a breach of the contract; and that the change was material, having increased the cost and delayed the progress of the work to an extent which he could not have anticipated when he bid on it. It was not finished until the following spring, on May 28, 1937. The Commission allowed respondent an extension of time to January 28, 1937; but refused to sanction the whole delay, and withheld $1500 from respondent’s compensation as liquidated damages because of the remaining time arrearage, under a clause of the construction contract.

Respondent thereupon brought this suit. In the first count of his petition he sued for the aforesaid $1500 balance of the contract price, alleged to be due because of the Commission’s breach of the contract, and recovered a verdict for the full amount. The second count was for $6145 damages claimed for increased cost of supervision and *121 rental value of equipment, due to the delay and unfavorable weather. On that count the verdict was for $700. The third count, added by amendment a year after the institution of the suit, was for the cost of materials furnished as agreed upon and used in heating concrete aggregates to prevent freezing, in the amount of $100. The verdict on that count was for $119.72. The judgment was for the sum of these several verdicts, $2319.72, with about nineteen months’ interest on the first and third items.

The testimony for respondent and his superintendent concerning the delay is very indefinite. As we understand it, excavation work for the culvert started about the middle of September. At the depth called for by the plans no sufficient rock footings were found and the Commission’s engineer required two feet further excavation. Instead of merely digging a separate trench for each of the three bridge supports as the engineer advised but did not demand, respondent blasted and excavated the whole area necessary to include all- three supports. All this took about two weeks. Then work was suspended on order of the Commission for about two weeks, and new plans were substituted calling for backfilling the whole excavated area 4 or 5 feet and constructing a concrete floor thereon as a base for the bridge supports. This backfilling took about two weeks, and altogether there were about four weeks delay in a total elapsed time of six weeks extending to about November 1.

There is not much controversy on these dates. The Commission’s supervising engineer testified from his diary that respondent was notified of the redesigning of the culvert on October 17; and that backfilling was commenced on October 21 and finished on November 1. However, this witness stated respondent was engaged in excavating during the whole month .from September 14 to October 14, thus in effect denying- that it was completed in two weeks and suspended for two weeks before backfilling began. The new plans required different steel for the culvert and construction work thereon did not begin until December 1. The weather turned cold unusually early that winter with sleet on the ground for six weeks. Respondent had expected to finish all the work late in October. But the Commission^ supervisor, just mentioned, declared there were shutdowns from time to time because of breakdowns in respondent’s excavating machinery.

The Commission’s most elaborately briefed contention is that the trial court erred in receiving the three verdicts and entering judgment thereon because all were for extra compensation outside of the written construction contract, and to be paid out of the State Treasury from funds appropriated by the Legislature. It is asserted this would violate Sec. 48, Art. IV of the State Constitution and Sec. 8764, R. S. 1939, Sec. 8116, Mo. Stat. Ann., p. 6900. The constitutional provision contains two clauses. In quoting it we emphasize certain words and mark the second clause with an asterisk for convenience in reference:

*122 ‘ ‘ The General Assembly shall have no power to grant, or to authorize any county or municipal authority to grant any extra compensation, fee or allowance to a public officer, agent, servant or contractor, after service has been rendered or a contract has been entered into and performed in whole or in part, *nor pay nor authorize the payment of any claim hereafter created against the State, or any county or municipality of the State,.under any agreement or contract made without express authority of law; and all such unauthorized agreements or contracts shall be null and void.” Under the Statute, Sec. 8764, supra, contracts for the construction of parts of the state highway system must be furnished and prescribed by the State Highway Commission, and let to the lowest responsible bidder after published advertisement. Otherwise they are not authorized by law.

The Commission construes the first clause of the constitutional provision as prohibiting payment of extra compensation to a contractor in the sense of compensation outside the terms of a legal contract; and the second as forbidding payment of a claim under an illegal contract, meaning any contract not made as prescribed by Sec. 8764, supra. Both parties concede the written construction contract actually entered into was legally made. But the Commission asserts it exclusively provided for payment at unit prices on the quantities of work actually done; and does not authorize the payment of compensatory damages en gros, certainly not in an amount above the stipulated contract price. Hence the contention is made that if respondent is entitled to the amounts sued for and recovered it must be under some other and different contract which was not advertised and let to the lowest bidder, as required by the second clause of the constitutional provision and Sec. 8764, supra. And the Commission further says that even if it be conceded respondent might otherwise recover on the claims asserted in counts 2 and 3 of the petition, still he cannot do so in this instance because he failed to give 60 days detailed notice of said claims, and to prove the Commission’s Chief Engineer had certified the amounts sued for and recovered were due and that the work had been satisfactorily completed — all as required by the contract and specifications. There are other assignments of error in the Commission’s brief, on the admission and exclusion of evidence.

The authorities are uniform on the second proposition advanced by the Commission, as stated at the beginning of the last paragraph— that it cannot pay a claim under a contract which is not authorized by law, in this instance Sec. 8764, supra. Two cases in point cited from other jurisdictions are Diamond v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Home Shopping Club, Inc. v. Roberts Broadcasting Co.
989 S.W.2d 174 (Missouri Court of Appeals, 1998)
J.A. Tobin Construction Co. v. State Highway Commission of Missouri
697 S.W.2d 183 (Missouri Court of Appeals, 1985)
Thomas O'Connor & Co. v. City of Medford
448 N.E.2d 1276 (Massachusetts Appeals Court, 1983)
Denton Construction Co. v. Missouri State Highway Commission
454 S.W.2d 44 (Supreme Court of Missouri, 1970)
Rock Hill Asphalt & Construction Co. v. State Highway Commission
452 S.W.2d 810 (Supreme Court of Missouri, 1970)
Parsons Construction Co. v. Missouri Public Service Co.
425 S.W.2d 166 (Supreme Court of Missouri, 1968)
Maryland Casualty Co. v. State Highway Commission
256 F. Supp. 666 (W.D. Missouri, 1966)
State ex rel. State Highway Commission v. County of Camden
394 S.W.2d 71 (Missouri Court of Appeals, 1965)
Kizior v. City of St. Joseph
329 S.W.2d 605 (Supreme Court of Missouri, 1959)
Samuel Kraus Co. v. Kansas City
315 S.W.2d 758 (Supreme Court of Missouri, 1958)
Spencer v. General Electric Company
243 F.2d 934 (Eighth Circuit, 1957)
Spencer v. General Electric Co.
243 F.2d 934 (Eighth Circuit, 1957)
State Ex Rel. Armontrout v. Smith
182 S.W.2d 571 (Supreme Court of Missouri, 1944)
Webb-Boone Paving Co. v. State Highway Commission
173 S.W.2d 580 (Supreme Court of Missouri, 1943)
Sager v. State Highway Commission
160 S.W.2d 757 (Supreme Court of Missouri, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
159 S.W.2d 647, 349 Mo. 117, 1941 Mo. LEXIS 495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spitcaufsky-v-state-highway-commission-mo-1941.