J.H. Berra Construction Co. v. Missouri Highway & Transportation Commission

14 S.W.3d 276, 2000 Mo. App. LEXIS 382, 2000 WL 291417
CourtMissouri Court of Appeals
DecidedMarch 21, 2000
DocketWD 56853
StatusPublished
Cited by5 cases

This text of 14 S.W.3d 276 (J.H. Berra Construction Co. v. Missouri Highway & Transportation Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.H. Berra Construction Co. v. Missouri Highway & Transportation Commission, 14 S.W.3d 276, 2000 Mo. App. LEXIS 382, 2000 WL 291417 (Mo. Ct. App. 2000).

Opinion

HAROLD L. LOWENSTEIN, Judge.

FACTS

This is an appeal from a summary judgment in favor of the Missouri Highway and Transportation Commission (hereafter the “Commission”) on an issue of contract interpretation. The contract in question was between the plaintiff-appellant, who was the successful bidder on a contract to do roadwork for the State of Missouri, and *278 the State of Missouri. In this suit, J.H. Berra Construction Co., Inc. (“Berra”) sought damages for breach pursuant to the contract in the amount of $1,164,234 for work it did which was necessary to fulfill its contractual obligation, but which the Commission declined to pay.

Appellant, Berra submitted a bid to the Commission in response to the Commission’s Request for Proposal soliciting bids to construct part of Route M in Jefferson City, Missouri (the “Project”). The proposal showed the location, character and details of the work, as well as an “Itemized Proposal” purporting to list a description of all the work necessary to complete the Project and the quantity of that work called for in the plans.

As required, Berra bid on the project by placing a “unit price” next to each separately described item of work listed in the Itemized Proposal. The Commission thereafter awarded the contract to Berra, who in turn began construction and completed the Project.

A portion of the work on the Project involved hauling dirt. The Missouri Standard Specifications for Highway Construction 1993 Edition (“Standard Specifications”) is the controlling authority of the issue in this case and was incorporated into the contract. The Standard Specifications state that all hauling within 2,000 feet is known as “free-haul” and not included as a “pay item,” while hauling that exceeds 2,000 feet is known as “overhaul.” The Standard Specifications define “pay item” as “[an] item of work specifically described and for which a price, either unit or lump sum, is provided.” The Commission is to include overhaul as a pay item and quantify overhaul in the plans if it intends to invite a bid for that work also, according to the Standard Specifications.

As a design decision, the Missouri Department of Transportation chose not to include overhaul as a separate pay item on the Project. The quantities prepared by the Commission and included within the Itemized Proposal did not contain quantities for overhaul. Nowhere in the bidding documents was hauling beyond the free-haul distance quantified.

However, the Project as designed did require overhaul that had not been calculated by the Commission. The costs associated with this overhaul is Berra’s claim on appeal.

Berra claims that overhaul distances allowed “determination” of a quantity, although it admits the quantity was stated nowhere in the contract. Berra further claims that absent a note stating otherwise, there should be separate payment of overhaul as a contract obligation pursuant to the Standard Specifications.

After making a claim in the amount of $494,040 for the overhaul that Berra performed in the course of the project, the Missouri Department of Transportation’s Claims Committee determined that Berra’s claim should be denied. Berra subsequently brought this suit in Circuit Court seeking compensation in the amount of $1,164,234: the amount of the previous claim plus additional overhaul it had performed. Both the Claims Committee and the Circuit Court held that Berra’s interpretation of the contract was incorrect and denied Berra any relief.

Although there was no way for Berra to quantify the overhaul or even prove there would be any at the time of the bid, Berra claims it ultimately provided 16,468,000 station yards of overhaul in completing the Project. Berra hired personnel capable of making the overhaul calculations, and after doing so, requested payment for the overhaul it had already performed. The Commission’s response to Berra was that Berra had no basis to be paid for the overhaul since it was not quantified in the plans.

STANDARD OF REVIEW

Appellant’s claim was decided on summary judgment. Accordingly, the applicable standard of review is as follows:

*279 Our review is essentially de novo. The criteria on appeal for testing the propriety of summary judgment are no different from those which should be employed by the trial court to determine the propriety of sustaining the motion initially. The propriety of summary judgment is purely an issue of law. As the trial court’s judgment is founded on the record submitted and the law, an appellate court need not defer to the trial court’s order granting summary judgment.

Rodgers v. Threlkeld, WD 56759, 1999 WL 807627 (Mo.App.W.D. 1999) citing ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993) (citations omitted).

Summary judgment will be upheld on appeal if: (1) there is no genuine dispute of material fact, and (2) the movant is entitled to judgment as a matter of law. Id. at 377.

When considering appeals from summary judgments, the [cjourt will review the record in the light most favorable to the party against whom judgment was entered. Id. at 376. Facts set forth by affidavit or otherwise in support of a party’s motion are taken as true unless contradicted by the non-moving party’s response to the summary judgment motion. Id. We accord the non-movant the benefit of all reasonable inferences. Id.

POINT RELIED ON

Appellant contends that the trial court erred in entering summary judgment in favor of the Commission because it was not entitled to judgment as a matter of law as the contract obligates the Commission to compensate Berra for authorized hauling in excess of the free-haul distance.

This case is fundamentally governed by the primary purpose of contract interpretation; to ascertain the intent of the parties and to give effect to that intent. CB Commercial Real Estate Group, Inc. v. Equity Partnerships Corp., 917 S.W.2d 641, 646 (Mo.App.1996). “The terms of a contract are read as a whole to come to the intention of the parties.” Village of Cairo v. Bodine Contracting Co., 685 S.W.2d 253, 264 (Mo.App.1985). “[E]ach term is construed to avoid an effect which renders other terms meaningless: a construction which attributes a reasonable meaning to all the provisions of the agreement is preferred to one which leaves' some of them without function or sense.” Id. When several documents make up the agreement between the parties, “the parties’ intent and the meaning of those documents must be determined from the entire transaction and not simply from isolated portions of particular documents.” Norcomo Corp. v. Franchi Constr. Co., 587 S.W.2d 311, 317 (Mo.App.1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schwarz v. Gierke
2010 ND 166 (North Dakota Supreme Court, 2010)
Spirtas Co. v. Division of Design & Construction
131 S.W.3d 411 (Missouri Court of Appeals, 2004)
East Attucks Community Housing, Inc. v. Old Republic Surety Co.
114 S.W.3d 311 (Missouri Court of Appeals, 2003)
Anderson v. Curators of the University of Missouri
103 S.W.3d 394 (Missouri Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
14 S.W.3d 276, 2000 Mo. App. LEXIS 382, 2000 WL 291417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jh-berra-construction-co-v-missouri-highway-transportation-commission-moctapp-2000.