Sager v. State Highway Commission

160 S.W.2d 757, 349 Mo. 341, 1942 Mo. LEXIS 364
CourtSupreme Court of Missouri
DecidedApril 16, 1942
StatusPublished
Cited by12 cases

This text of 160 S.W.2d 757 (Sager v. State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sager v. State Highway Commission, 160 S.W.2d 757, 349 Mo. 341, 1942 Mo. LEXIS 364 (Mo. 1942).

Opinions

This is an action (by the last Board of Directors of the Inland Construction Company, a defunct Missouri corporation, hereinafter called plaintiff) for additional compensation claimed for extra work, due to change of plans made and additional difficulties encountered, during the construction of a state highway between Morehouse and Lilbourn in New Madrid County. The suit was in 14 counts and the jury found for plaintiff in some amount (on several for less than claimed) on each count, except the sixth. Judgment *Page 345 thereon for the total amount of $4481.94 was entered, and defendant has appealed.

Defendant raised questions (in its answer) involving the construction of Section 48, Art. IV of the Constitution. [See Spitcaufsky v. State Highway Commission, No. 36838, 349 Mo. 117,159 S.W.2d 647, recently decided in Division 2.] This highway was built in 1934 and 1935. It covered about seven miles, let in two projects. The 13 counts upon which plaintiff had a verdict (there was no appeal as to the sixth) involved several types of claims which may be classified, as follows:

Counts 1-4-5. That land furnished for borrow pits or for obtaining material for building the highway was not suitable because full of stumps, and that this delayed the work, damaged machinery and required use of teams and scrapers instead of excavating [759] machinery, which increased expense of plaintiff.

Counts 2-3-7. That plans were materially altered by raising the grade or increasing the width of the highway at certain places without furnishing a sufficient borrow pit requiring plaintiff to widen side ditches (2), or to deepen existing borrow pit (3), and move wet material (3 and 7), which could not be done with excavating machinery, so that plaintiff had to use teams and scrapers at increased expense and delay.

Count 8. That plans as furnished were not correct as to working conditions because excavation, over the specified 200 feet, could not be done with excavating machinery at this place but required excavation at a considerable distance and removal to the highway which caused increased expense and delay.

Counts 9-10-11-12-13-14. That plans were materially altered by changing the grade and width at approaches to the highway, or over drainage pipes which were raised, requiring moving men and machinery, back from other places, delaying the work and increasing expense.

Defendant's answer, in addition to general denial, set up Section 48, Art. IV of the Constitution as prohibiting payment of plaintiff's claims because the work authorized was fully covered by a written contract, let after notice and competitive bidding as required by Sections 3349 and 8764, R.S. 1939. (Sections 2962 and 8116, Mo. Stat. Ann. 1827 and 6900.) It stated that no payment could be made to plaintiff out of state funds for changes or extra work except in accordance with the contract which provided there should be no payment therefor unless there was a change order signed by the engineer or the parties before such work was done. Defendant also set up other contract provisions hereinafter stated. Plaintiff's reply claimed estoppel on the ground that defendant's engineer in charge of the work ordered the changes and promised to furnish the necessary change orders. Plaintiff alleged that it did the work relying on such representations. *Page 346

[1] Section 48, Article IV, provides: "The General Assembly shall have no power (to grant, or to authorize any county or municipal authority to grant any extra compensation, fee or allowance to a public officer, agent, servant or contractor, after service has been rendered or a contract has been entered into and performed in whole or in part), (nor pay nor authorize the payment of any claim hereafter created against the State, or any county or municipality of the State, under any agreement or contract made without express authority of law); and all such unauthorized agreements or contracts shall be null and void." (Parentheses ours.)

This court held, in the Spitcaufsky case, that the first clause of Section 48 prohibits the Highway Commission from paying extra compensation to a contractor outside the terms of a legal contract; that is, compensation for doing work, for which the legal contract does not provide, or for any claims different from those any other bidder at the letting could have legally asserted in the same circumstances if the contract had been awarded to him. The second clause forbids payment of a claim under an illegal contract, meaning in this case any contract not made as prescribed by Section 8764, supra; that is, the agreement to pay, relied upon, must be a part of the contract offered to the lowest responsible bidder by the notice and cannot be based upon substantially different oral understandings which are more beneficial to the contractor than the provisions included in and contemplated by the plans and specifications upon which bids were invited. [See also United Construction Co. v. St. Louis,334 Mo. 1006, 69 S.W.2d 639.] We think this construction is sound and reaffirm it.

[2] As pointed out in plaintiff's statement, the plans provided for what is commonly known as "typical section" construction over much of the project; that is, a typical cross section of the road, showing the contour of the surface of the road, the shoulders, ditches and back slopes, and the relative elevation of each to the others. There are two ways to build a highway; one is by an established grade designated on the plans; the other is by a typical section without any elevated grade. In typical section construction, the height of the roadbed is determined by the depth and width of the ditches as shown on the plans. This method of constructing a highway is by removing the dirt from the ditches and placing it on the roadbed, and is commonly known as "machine grading." This machine grading is ordinarily done with a 12-foot grader and a fifty or sixty-horsepower tractor, and with that equipment the contractor ordinarily employs [760] three 3-horse teams to drift the dirt back and forth across the road as it comes off of the machine grader. The elevating machine graders, used on this job, were equipped to roll on four wheels, had a disk plow of approximately thirty inches in diameter, and were equipped with a carrier to carry the dirt from underneath the machine out to *Page 347 the side about eight or ten feet on a belt, depositing the dirt about twenty feet from the plow in dump trucks or wagons.

As to counts 1-4-5, there is no claim of change of plans by alteration of grade or width. Instead, it is claimed that there were hidden stumps, roots and logs in the material to be moved to build the highway. Removal of these things is claimed to be extra work, not covered by the contract, because the plans and specifications did not disclose the presence of such things in the material. It is claimed that this extra work constituted a material change therein, which resulted in altering the nature of the work so as to increase cost, and that additional compensation was promised by the project engineer. The contract provided (B-5) that "bidders are required to examine the site of the proposed work, the proposal, plans, etc. . . . for the work contemplated." Plaintiff's proposal stated that he had done so and plaintiff's president testified that they did go over the site of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Lamar Company, LLC v. City of Columbia, Missouri
512 S.W.3d 774 (Missouri Court of Appeals, 2016)
Miller v. Missouri Department of Transportation
32 S.W.3d 170 (Missouri Court of Appeals, 2000)
Bernard McMenamy Contractors, Inc. v. Missouri State Highway Commission
582 S.W.2d 305 (Missouri Court of Appeals, 1979)
Denton Construction Co. v. Missouri State Highway Commission
454 S.W.2d 44 (Supreme Court of Missouri, 1970)
Rock Hill Asphalt & Construction Co. v. State Highway Commission
452 S.W.2d 810 (Supreme Court of Missouri, 1970)
State ex rel. State Highway Commission v. County of Camden
394 S.W.2d 71 (Missouri Court of Appeals, 1965)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
Kizior v. City of St. Joseph
329 S.W.2d 605 (Supreme Court of Missouri, 1959)
Samuel Kraus Co. v. Kansas City
315 S.W.2d 758 (Supreme Court of Missouri, 1958)
State Ex Rel. Armontrout v. Smith
182 S.W.2d 571 (Supreme Court of Missouri, 1944)
White v. Jones
177 S.W.2d 603 (Supreme Court of Missouri, 1944)
Webb-Boone Paving Co. v. State Highway Commission
173 S.W.2d 580 (Supreme Court of Missouri, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
160 S.W.2d 757, 349 Mo. 341, 1942 Mo. LEXIS 364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sager-v-state-highway-commission-mo-1942.