Antonellis v. Northgate Construction Corp.

291 N.E.2d 626, 362 Mass. 847, 1973 Mass. LEXIS 370
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 19, 1973
StatusPublished
Cited by52 cases

This text of 291 N.E.2d 626 (Antonellis v. Northgate Construction Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Antonellis v. Northgate Construction Corp., 291 N.E.2d 626, 362 Mass. 847, 1973 Mass. LEXIS 370 (Mass. 1973).

Opinion

Kaplan, J.

The plaintiffs’ declaration (the claim) sought damages for the defendant’s alleged breach of contract in failing to remové fill from the plaintiffs’ gravel *848 pit and to pay for it as agreed. The defendant answered, alleging that the execution of the contract sued on was based upon an agreement that the contract was to terminate if the fill did not meet the quality requirements of the city of Brockton, that the fill was rejected by the city, and that accordingly the defendant did not stand in breach. 1 Filed with the answer was the defendant’s declaration “in counterclaim and set-off” for the return of the amount of its deposit under the contract (the counterclaim) ; to this the plaintiffs responded with denials. Upon trial without a jury, the judge found for the defendant on both the claim and the counterclaim. The plaintiffs excepted to the judge’s allowing a certain question during the cross-examination of one of their witnesses, and also to the judge’s denial of their motion for a new trial on the claim and the counterclaim, and these rulings are made the basis of the plaintiffs’ bill of exceptions.

On August 15, 1966, the plaintiffs, as sellers, and the defendant, as buyer, executed a one-page agreement, entitled “Contract Terms,” prepared by and on the letterhead of a broker, for the purchase and sale of 150,000 yards of fill at twenty cents a yard, the fill to be removed by the buyer from the plaintiffs’ pit at Easton, Massachusetts. There was provision that the buyer was in certain events to pay the wages of a checker; that the removal was under the sellers’ permit and removal by other contractors was not to be allowed for a period of four months after operations under the agreement had begun; that the buyer was to deposit $5,000, from which the sellers were to pay $1,500 to the named broker (with a pro rata refund by the broker if less than 125,000 yards of fill was purchased by the buyer); that the buyer was to pay the broker $2,000 within sixty days after removal began; and that, after the sellers had used up the balance of the deposit by reimbursing themselves for the first fill taken, they were to bill the buyer bi-weekly for further *849 fill. The concluding paragraph 6 of the agreement read: “This contract is contingent upon the . . . [buyer] obtaining the Contract from the City of Brockton or their agents for this job.”

It appears that the defendant took about 21,000 yards of fill from September 16 to October 21, 1966. The city of Brockton rejected the fill as unsuited to the particular job of preparing a site for a high school, the rejection being shown by a letter of September 30 from the Brockton clerk of works to the defendant. Thereafter the defendant declined to take any additional fill from the plaintiffs, and pointed to the agreement for termination above mentioned.

The plaintiffs contended that there was no such agreement; they also intimated that such an agreement could not in any event be given effect in the face of the written contract of August 15, that is to say, the contingency paragraph of the contract of August 15 so far “integrated” its subject matter as to exclude by reference to the paroi evidence rule the recognition of an agreement regarding acceptability of the fill to the Brockton authorities.

The parties have addressed themselves to these issues on the merits, and we do also, although, as will be seen below, there is much doubt whether they are properly presented for review.

1. Whether there was an integration as the plaintiffs contended was a question of the intention of the parties on which proof could be received ranging beyond the writing proper. Carlo Bianchi & Co. Inc. v. Builders’ Equip. & Supplies Co. 347 Mass. 636, 643. Corbin, Contracts, §§ 573, 582, 588. The plaintiffs themselves called witnesses who testified about discussions between the parties before the writing was executed. One of the plaintiffs, Antonellis, testified that it was only after the defendant stopped digging that the defendant’s president informed him that the fill had to be approved by the Brockton city engineer. The plaintiffs, however, then went on to call the defendant’s president, Faino; he *850 testified that he had asked one Cicione, a representative of the broker, to find gravel for the defendant for the job in Brockton; that he met with Antonellis and Cicione and said'that the fill would be for a specific municipal job in Brockton and had to meet certain specifications of the city, and if the fill met those specifications and the defendant obtained the particular Brockton job, the defendant would be willing to buy the fill. 2 Cicione, also called by the plaintiffs, corroborated Paino’s testimony in substance, adding that Antonellis had said, “there would be no trouble at all if they [Brockton] couldn’t accept it.”

The record does not contain any specific evaluation of this evidence by the judge, but we think that, considered on the preliminary issue of integration, see Caputo v. Continental Constr. Corp. 340 Mass. 15,17-18; Restatement 2d: Contacts (Tent, draft No. 5, March 31, 1970) § 235 (2) and comment c, § 236 (3) and comments b and c, the evidence could justify a negative conclusion favoring the defendant; especially so, in view of the brevity of the writing and the evident design to mesh this agreement with the Brockton job. The same evidence could then readily support a further conclusion that the parties had in fact agreed that the buyer’s obligation to take fill from the plaintiffs would end if Brock-ton rejected it as unsuitable. Cf. Restatement 2d: Contracts, supra, § 235, comment c. The conclusion of nonintegration is quite plausible even if acceptance of the fill by Brockton is viewed as a contingency or condition added to (and consistent with) that of “obtaining” the Brockton contract as expressed in paragraph 6. See Hicks v. Bush, 10 N. Y. 2d 488, 492-493. 3 Considered *851 from a different angle, the agreement about the suitability of the fill for the Brockton job may be thought of as a specification of the quality of the fill that the defendant was contracting to take from the plaintiffs, rather than as a contingency or condition. The writing omitted mention of specifications despite the fact that the fill was destined for a construction project, and the judge could well find that the parties did not intend to exclude an oral agreement upon that subject. See Caputo v. Continental Constr. Corp., supra, at 18; Wigmore, Evidence (3d ed.) § 2430, at pp. 98-99.

But if it were held that there was an integration excluding an effective agreement outside the writing, the judge’s decision on the claim could still be supported. Paragraph 6 is not self-interpreting — no form of words is — and the evidence could be received and used to elucidate its meaning in context. Robert Indus. Inc. v. Spence, ante 751, 753. Imper Realty Corp. v. Riss, 358 Mass. 529, 535. Bridgewater Washed Sand & Stone Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rangeway Owner, LLC v. Billerica Developers, LLC.
Massachusetts Appeals Court, 2025
Guldseth v. Family Medicine Associates LLC
45 F.4th 526 (First Circuit, 2022)
Realty Finance Holdings, LLC v. KS Shiraz Manager, LLC
18 N.E.3d 350 (Massachusetts Appeals Court, 2014)
Chambers v. Gold Medal Bakery, Inc.
982 N.E.2d 1190 (Massachusetts Appeals Court, 2013)
Commonwealth v. Garcia
972 N.E.2d 40 (Massachusetts Appeals Court, 2012)
Latham v. Homecomings Financial LLC
27 Mass. L. Rptr. 3 (Massachusetts Superior Court, 2010)
Marcoux v. Shell Oil Products Co. LLC
524 F.3d 33 (First Circuit, 2008)
Lederer v. JOHN SNOW, INC.
411 F. Supp. 2d 25 (D. Massachusetts, 2006)
Empire Business Brokers of Massachusetts, LLC v. ASC Family, Inc.
19 Mass. L. Rptr. 637 (Massachusetts Superior Court, 2005)
Quaboag Transfer, Inc. v. Halpin
19 Mass. L. Rptr. 257 (Massachusetts Superior Court, 2005)
RGJ Associates, Inc. v. Stainsafe, Inc.
338 F. Supp. 2d 215 (D. Massachusetts, 2004)
Corcoran Management Co. v. Town of Framingham
16 Mass. L. Rptr. 519 (Massachusetts Superior Court, 2003)
Cabot v. Cabot
774 N.E.2d 1113 (Massachusetts Appeals Court, 2002)
Trent Partners & Associates, Inc. v. Digital Equipment Corp.
120 F. Supp. 2d 84 (D. Massachusetts, 1999)
City of Haverhill v. George Brox, Inc.
716 N.E.2d 138 (Massachusetts Appeals Court, 1999)
Marrotto v. Naumann
1999 Mass. App. Div. 35 (Mass. Dist. Ct., App. Div., 1999)
Wagley v. Danforth
46 Mass. App. Ct. 15 (Massachusetts Appeals Court, 1998)
Davis v. Dawson, Inc.
15 F. Supp. 2d 64 (D. Massachusetts, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
291 N.E.2d 626, 362 Mass. 847, 1973 Mass. LEXIS 370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/antonellis-v-northgate-construction-corp-mass-1973.