Caputo v. Continental Construction Corp.

162 N.E.2d 813, 340 Mass. 15, 1959 Mass. LEXIS 720
CourtMassachusetts Supreme Judicial Court
DecidedDecember 7, 1959
StatusPublished
Cited by14 cases

This text of 162 N.E.2d 813 (Caputo v. Continental Construction Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caputo v. Continental Construction Corp., 162 N.E.2d 813, 340 Mass. 15, 1959 Mass. LEXIS 720 (Mass. 1959).

Opinion

Spalding, J.

The defendant, as general contractor, entered into a contract with the Commonwealth for the repair and construction of the French King Bridge. Thereafter subcontracts for certain work and materials for the bridge were made by the plaintiff and the defendant. The plaintiff seeks in this action to recover for labor and materials furnished to the defendant under three contracts. This action was tried with a cross action brought by the defendant to recover damages for alleged breaches of contracts by the plaintiff. The judge found for the plaintiff in the original action and the case is here on the defendant’s exceptions.

The question for decision arises out of a ruling on evidence which occurred in these circumstances. The contracts which are the basis of counts 1, 2, and 3 are three letters which are set forth below. 1 The defendant sought to show through *17 Ragone, its president, conversations with the plaintiff prior to March 28, 1955, the date of the first of the three letters. This evidence was objected to by the plaintiff but the judge *18 admitted it de bene. Ragone testified that on or about March 25, 1955, he had a telephone conversation with the plaintiff during which Ragone had “stressed to . . . [the plaintiff] the importance of getting the work quickly started and of speedily completing the project . . . so as to enable the defendant to take advantage of the bonus clause in its master contract with the Commonwealth.” Ragone further testified that the parties had “also agreed that the plaintiff would be paid by the defendant in the same manner as the defendant was paid by the Commonwealth . . . and that the plaintiff would carry the insurance required by the specifications” for the job. Evidence was also admitted de bene that the plaintiff had neither supplied the materials nor performed the work “as called on by the defendant” and by failing to do so had delayed the completion of the job with the result that the defendant lost the bonus it might have received had the plaintiff performed seasonably.

Thereafter, subject to the defendant’s exception, the judge ordered struck from the record all the evidence admitted de bene “pertaining to the alleged terms and performance of the . . . oral agreement.”

The governing principles of law are very familiar and need not be restated. Unless the letters can be said to state the entire agreements of the parties, the excluded evidence should have been admitted. Glackin v. Bennett, 226 Mass. 316, 319. Kerwin v. Donaghy, 317 Mass. 559, 567-568, and cases cited. We are of opinion that the letters did not state the entire agreements and that the excluded evidence was admissible. Matters of importance which normally would be included in contracts of the sort under consideration would be the time when the plaintiff was to complete performance, the method of payment, provisions as to insurance, and the specifications and standards to be complied with. None of the letters sheds any light on these matters. This indicates, we think, that the parties never intended that the letters were to constitute their entire agreements. In these circumstances extrinsic evidence was admissible. Peerless Petticoat Co. v. Colpak-Van Costume Co. 273 Mass. *19 289, 292. Kesslen Shoe Co. Inc. v. Philadelphia Fire & Marine Ins. Co. 295 Mass. 123, 131. International Business Mach. Corp. v. Quinn Bros. Elec. Co. 321 Mass. 16, 19. Cotty v. Meister, 339 Mass. 202, 204-205.

Exceptions sustained.

1

“March 28, 1955

Continental Const. Co.

437 Main St.

Lynnfield, Mass.

Re: French King Bridge Erving • — ■ Gill

Gentlemen:

Confirming our verbal agreement, we will furnish and deliver in accordance with plans, f.o.b. above job for the sum of twenty seven thousand five hundred ($27,500.00) dollars the following items:

16 Scuppers Curb plates

anchor bolts & lead sheets for fence New expansion joints

1 steel ladder catwalk & gratings We will erect:

Angles only, adjacent to scuppers.

Curb plates in one operation, after the reinforcing for curb is installed by you, to which we will attach the curb plates.

Removing & re-erecting fence and we expect to lash this fence to fence on opposite side.

One steel ladder.

Catwalk complete in one operation after concrete deck has been removed by you.

We do not install:

Scuppers

Anchor bolts for fence

*17 Approach half of expansion joints

No field painting.

Very truly yours, Builders Iron Works

[Signed] Joseph L. Caputo

JLC/lg

We accept the above

Continental Const. By [Signed] Joseph G. Ragone, Pres.”

“May 6, 1955

Continental Construction

Company

437 Main Street

Lynnfield Center. Mass.

Attention: Mr. Ragone

As per our recent telephone conversation we informed you that we have located 8x4 angle stock for the catwalk from a stock supplier. Due to additional weight and price factors an additional $950.00 is required to facilitate purchase of this material. It will advance delivery at least 30 days. At your recommendation and agreement to pay this additional sum we have placed an order for the above. Please sign one copy of this letter as confirmation of the above agreement and return for our files. Material cannot be released for delivery without a written order from the contractor.

John McCarthy

JMcC/dt

Accepted:

[Signed] Joseph G. Ragone

Continental Construction Company”

Continental Construction Company

437 Main-Street

Lynnfield Center, Mass.

Re: French King Bridge

In accordance with my agreement with you we made over the telephone, we will furnish 10 x A plate in lieu of the 9 A x A plate for one side of the bridge. We will charge you for the difference in cost between the 10 x A at warehouse price as against the 9 A x A plate at mill price. We also agree to work the men overtime on the expansion dam for half the bridge on each end and charge you for the overtime rate which should be approximately $200.00.

JLC/dt

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Inofin, Inc.
455 B.R. 19 (D. Massachusetts, 2011)
Winlake II, Inc. v. Mercier
21 Mass. L. Rptr. 166 (Massachusetts Superior Court, 2006)
Jim Walsh Plumbing Co. v. Cresta Construction, Inc.
3 Mass. L. Rptr. 29 (Massachusetts Superior Court, 1994)
Schwartz v. Schultz
25 Mass. App. Ct. 941 (Massachusetts Appeals Court, 1988)
Wang Laboratories, Inc. v. Docktor Pet Centers, Inc.
422 N.E.2d 805 (Massachusetts Appeals Court, 1981)
Rokowsky v. Gordon
501 F. Supp. 1114 (D. Massachusetts, 1980)
Antonellis v. Northgate Construction Corp.
291 N.E.2d 626 (Massachusetts Supreme Judicial Court, 1973)
Robert Industries, Inc. v. Spence
291 N.E.2d 407 (Massachusetts Supreme Judicial Court, 1973)
George H. Ferreira Construction Co. v. Pinho
28 Mass. App. Dec. 135 (Mass. Dist. Ct., App. Div., 1964)
Chas. T. Main, Inc. v. Massachusetts Turnpike Authority
196 N.E.2d 821 (Massachusetts Supreme Judicial Court, 1964)
Joseph E. Bennett Co. Inc. v. Fireman's Fund Ins. Co.
181 N.E.2d 557 (Massachusetts Supreme Judicial Court, 1962)
Hanrihan v. Hanrihan
174 N.E.2d 449 (Massachusetts Supreme Judicial Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
162 N.E.2d 813, 340 Mass. 15, 1959 Mass. LEXIS 720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caputo-v-continental-construction-corp-mass-1959.