Wang Laboratories, Inc. v. Docktor Pet Centers, Inc.

422 N.E.2d 805, 12 Mass. App. Ct. 213, 1981 Mass. App. LEXIS 1152
CourtMassachusetts Appeals Court
DecidedJuly 6, 1981
StatusPublished
Cited by19 cases

This text of 422 N.E.2d 805 (Wang Laboratories, Inc. v. Docktor Pet Centers, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wang Laboratories, Inc. v. Docktor Pet Centers, Inc., 422 N.E.2d 805, 12 Mass. App. Ct. 213, 1981 Mass. App. LEXIS 1152 (Mass. Ct. App. 1981).

Opinion

Cutter, J.

The plaintiff (Wang) leased computer equipment to Docktor Pet Centers, Inc. (DPC), and made an agreement with DPC to maintain the equipment. Wang’s action is to recover for rental payments under the written lease agreement. DPC has filed a counterclaim alleging failure of Wang to get the system working on time or satisfactorily and asks consequential damages of various types. The case was heard (jury-waived) by a Superior Court judge, who made findings. Wang appeals from a judgment allowing it only a limited recovery. The counterclaim was dismissed.

The complete evidence, including all exhibits, is before us. Wang introduced in evidence thirty-two requests for admissions under Mass.R.Civ.P. 36, 365 Mass. 795 (1974), [214]*214which the judge found were admitted by DPC because never answered.1 Wang’s affirmative case essentially was based on these unanswered requests.

The evidence indicated that negotiations took place in November and December, 1973, among Wang, Engineering Computer Systems, Inc. (ECS), and DPC for the lease to DPC of Wang computer hardware and ECS software. Because of its financial position, DPC wanted to lease new computer equipment and to have Wang obtain ECS software and provide it under the proposed lease. Compare the situation discussed in Patriot Gen. Life Ins. Co. v. CFC Inv. Co., 11 Mass. App. Ct. 857 (1981).

Over the objection of counsel for Wang, one Charm, then president of DPC, was allowed to testify in very general, ambiguous terms that, during the negotiations, Wang’s representatives stated (a) Wang would obtain software from ECS and would take “systems responsibility” for the hardware and the software, and (b) “the system would operate on two successive operating cycles successfully, so that . . . [DPC] would be comfortable that. . . [it] got what. . . [it] paid for.” An operating cycle was said to be about two months. The ambiguity of the first part of the testimony was somewhat dispelled by a letter of December 26, 1973, from Wang’s representative to Charm at DPC reading in part: “Wang . . . will assume Systems Responsibility. This means that Wang will support hardware. Wang will also stand behind contractural [sic] agreements concerning soft[215]*215ware specifications and completion dates reached between DPC and ECS.” Wang, by counsel, conceded during trial, that it “had systems responsibility.” There was until June 14, 1974, no attempt by Charm or DPC to support by correspondence Charm’s ambiguous testimony about Wang’s asserted representation that “two successful operating cycles would determine acceptance by” DPC, and that “the system would operate on two successive operating cycles successfully.”

In the meantime, a partly printed written lease agreement was signed on April 24, 1974, by Wang and DPC. This agreement contained a provision in capital letters that Wang “makes no warranties regarding products manufactured by it or by others (including without implied limitation warranties as to merchantability, [or] fitness for a particular purpose . . .) express or implied, except as provided herein.” Compare Dekofski v. Leite, 336 Mass. 127, 128-129 (1957). It also provided (in ordinary type) that Wang should not “be liable for incidental or consequential damages . . . arising out of the furnishing, performance or use of any product covered by this agreement.” The sole warranty (§ 2 of Appendix A of the lease agreement) related to defects in materials and workmanship of “all products manufactured by [Wang] but not by others” (emphasis supplied) and extended for ninety days from the date of shipment and, for one year from the end of the warranty period, a promise to replace any such defective part without charge for the replacement part.

The lease agreement at first examination looks like a completely integrated contract between Wang and DPC. It contains no provision suggesting that any significance should be attached to the completion of two successive operating cycles successfully. It also, in § 12(b) in fine print, contains an express provision, “No representations, warranties, promises, guaranties or agreements, oral or written, express or implied, have been made with respect to the lease or equipment, except as expressly provided herein.” This has many aspects of an integration provision.

[216]*216On June 14, 1974, Charm of DPC wrote a long letter to one Carr of the Wang staff in which, referring to a negotiating meeting in April, 1974, he raised three points of which the second was that DPC’s “lease payments were not to commence until after two complete cycles had been completed running parallel2 on the Wang equipment.” No reply to this letter is in the record, but Charm testified that Carr replied orally, “I understand what you said in your letter. I agree . . . that’s what we said.”

The trial judge, on the somewhat meager evidence just outlined, found that “in April, 1974, ... it was agreed that lease payments by DPC were not to commence until after the successful running of two complete monthly operating cycles . . . and that the reports to be generated would be demonstrated to the satisfaction of DPC. The equipment was to begin full operation by October 1, 1974, the beginning of DPC’s fiscal year.”3

1. The initial (and essentially conclusive) question is whether the lease agreement of April 24, 1974, is an integrated contract intended by the parties to contain their whole agreement. The provisions from the agreement already quoted, especially § 12(b), would suggest that it was so intended. The testimony of Charm, accepted by the trial judge, is to the contrary. Some objections (concerning the deposit to be made by DPC) appear to have been made to the draft lease agreement as originally tendered, but this problem was corrected. DPC does not appear to have made [217]*217at that time any other objection to the content of the draft lease agreement. Charm also testified that a representative of Wang told him in late March, 1974, that DPC “had to sign the lease agreement ... to keep the documentation and paper flow going.”

It is far from clear to what extent the trial judge (cf. Cormier v. Carty, 381 Mass. 234, 235-238 [1980]) made an adequate and detailed comparison of the lease agreement with the contents of the supposed oral agreement, particularly that relating to the successful completion of two operating cycles. We attempt such a comparison to determine what matters the judge should appropriately have taken into account in deciding whether the lease agreement embodied all prior understandings:

(a) The lease agreement provided for a deposit by DPC of $3,210.93 “as payment of the first and last monthly rentals of the lease term” but that “[subsequent rental payments will be due monthly beginning one month from the date of delivery.” The copy of the lease agreement in the record shows in long-hand the words, “Start July 1, 1974,” obviously a reference to the beginning of monthly rental payments. The “approximate delivery date” was listed as “5-1-74” and delivery in fact occurred on July 11 for Wang’s hardware and on July 15 for the ECS software.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

THERESA BAILEY & Another v. MDM REALTY TRUST.
Massachusetts Appeals Court, 2026
Paul J. Phillips, Jr.
D. Massachusetts, 2025
Guldseth v. Family Medicine Associates LLC
45 F.4th 526 (First Circuit, 2022)
Realty Finance Holdings, LLC v. KS Shiraz Manager, LLC
18 N.E.3d 350 (Massachusetts Appeals Court, 2014)
Chambers v. Gold Medal Bakery, Inc.
982 N.E.2d 1190 (Massachusetts Appeals Court, 2013)
Green v. Harvard Vanguard Medical Associates, Inc.
944 N.E.2d 184 (Massachusetts Appeals Court, 2011)
Friel Development & Construction Co. v. Parrish Painting Development & Construction Co.
2000 Mass. App. Div. 212 (Mass. Dist. Ct., App. Div., 2000)
USTrust v. Henley & Warren Management, Inc.
663 N.E.2d 1238 (Massachusetts Appeals Court, 1996)
Town & Country Fine Jewelry Group, Inc. v. Hirsch
875 F. Supp. 872 (D. Massachusetts, 1994)
Cambridgeport Savings Bank v. Boersner
597 N.E.2d 1017 (Massachusetts Supreme Judicial Court, 1992)
Brennan v. Carvel Corp.
929 F.2d 801 (First Circuit, 1991)
New England Financial Resources, Inc. v. Coulouras
566 N.E.2d 1136 (Massachusetts Appeals Court, 1991)
Ryder v. Williams
558 N.E.2d 1134 (Massachusetts Appeals Court, 1990)
Hillman v. Roman Catholic Bishop of Fall River
24 Mass. App. Ct. 241 (Massachusetts Appeals Court, 1987)
Fred. S. James & Co. of New England, Inc. v. Hoffmann
507 N.E.2d 269 (Massachusetts Appeals Court, 1987)
Reynolds Industries, Inc. v. Mobil Oil Corp.
618 F. Supp. 419 (D. Massachusetts, 1985)
Reynolds Aluminum Building Products Co. v. Leonard
480 N.E.2d 1 (Massachusetts Supreme Judicial Court, 1985)
Shain Investment Co., Inc. v. Cohen
443 N.E.2d 126 (Massachusetts Appeals Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
422 N.E.2d 805, 12 Mass. App. Ct. 213, 1981 Mass. App. LEXIS 1152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wang-laboratories-inc-v-docktor-pet-centers-inc-massappct-1981.