Reynolds Aluminum Building Products Co. v. Leonard

480 N.E.2d 1, 395 Mass. 255, 1985 Mass. LEXIS 1577
CourtMassachusetts Supreme Judicial Court
DecidedJune 25, 1985
StatusPublished
Cited by22 cases

This text of 480 N.E.2d 1 (Reynolds Aluminum Building Products Co. v. Leonard) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds Aluminum Building Products Co. v. Leonard, 480 N.E.2d 1, 395 Mass. 255, 1985 Mass. LEXIS 1577 (Mass. 1985).

Opinion

Lynch, J.

In this contract action, we must determine the duties of the trial judge when he decides to ameliorate the effects of admissions that have become binding by the operation ofDist. Mun. Cts. R. Civ. P. 36 (1975). The plaintiff, Reynolds Aluminum Building Products Company (Reynolds), brought suit to recover for the sale and installation of a solar hot water heating system in the defendants’ house. The defendants, the Leonards, denied liability because the system allegedly did not function as advertised, and they asserted a counterclaim based on G. L. c. 93A for false advertising. During the course of the proceedings, the Leonards made five requests for admissions, to which Reynolds never responded. 2 After a trial in the District Court the judge found for Reynolds, and dismissed the Leonards’ counterclaim without discussing the requests for admissions. 3 The Leonards’ report to the Appellate Division was dismissed, and they now appeal to this court. We reverse the order dismissing the report, and remand the case to the *257 District Court for further findings, and entry of judgment based on those new findings.

On November 10, 1980, the parties entered into a contract under which Reynolds was to sell and install a solar hot water system in the Leonards’ house. The total price of $3,795 was payable within thirty days after the installation was completed. The Leonards acknowledge that Reynolds completed installation, and that no part of the agreed price has been paid. The Leonards claim that the equipment did not function properly, that it was not installed in a workmanlike manner, that it never supplied the advertised amount of hot water, and that Reynolds never corrected defects in the system despite notification. The Leonards filed a counterclaim alleging that Reynolds falsely advertised the effectiveness of the system and caused $750 damage to the Leonards’ roof during installation. The Leonards also sought removal of the system from their house. At trial, Albert Leonard testified that he was never able to get any hot water from the system, that he made numerous complaints to Reynolds, and that Reynolds’ representatives made three visits to his house but failed to correct the problem. The Leonards also introduced in evidence the five unanswered requests for admissions. Because of Reynolds’ failure to answer these requests, they are considered “conclusively established” under Dist. Mun. Cts. R. Civ. P. 36 (1975).* ** 4 Reynolds’ supervisor *258 testified that on one of his visits to the house, he discovered that the Leonards had diverted hot water from the system to a radiator in order to heat one room, an unintended use of the solar hot water system. Following trial, the Leonards made several requests for rulings, including two which incorporated the information which was the subject of the prior requests for admission.* *** 5 All the requests were denied. The judge found in favor of Reynolds for the full contract price, plus interest, costs, and attorneys’ fees. 6 Giving no effect to Reynolds’ admissions, the judge found that Reynolds had not represented that the system would provide sixty per cent or more of the Leonards’ hot water requirements. In addition, he found that whether a permit was required was irrelevant to the case. Finally, he found that the Leonards failed to sustain their burden of proof on the counterclaim. The Appellate Division dismissed the Leonards’ report.

1. Sufficiency of the report. Reynolds accurately notes that the report does not state any ruling by the judge with regard to Reynolds’ failure to respond to the request for admissions. Reynolds argues that the Leonards had therefore failed to preserve their right of appellate review of this issue in accordance with Dist. Mun. Cts. R. Civ. P. 64 (a) (1975). However, the judge was not required to take any action; simply by operation of rule 36 (a), the matters were deemed admitted after thirty days. There is nothing in the record to suggest that the judge refused to allow the admissions in evidence, or even that *259 Reynolds objected to them. Rule 64 (a) is therefore irrelevant to the preservation of the Leonards’ appellate rights. The Leonards incorporated these admissions into two requested rulings, which were denied. A timely report was claimed, appealing the denial of these rulings. This was sufficient to preserve the Leonards’ right of review in the Appellate Division.

2. Failure to obtain permits. The Leonards argue that Reynolds is not entitled to recover under the contract because Reynolds failed to obtain the necessary plumbing permit. See 248 Code Mass. Regs. § 2.04 (3) (1983). Assuming, without deciding, that it was Reynolds’ duty to obtain such a permit, we do not agree that its failure to do so prevents recovery in this case. The Leonards admit that there was no illegality in the formation of the contract, but claim that performance was illegal. Considering all of the circumstances of this case, the Leonards have advanced no reason to question the judge’s conclusion that the conduct complained of was merely an incidental part of the contract and does not entitle the Leonards to the windfall they seek. See Town Planning & Eng’g Assocs. v. Amesbury Specialty Co., 369 Mass. 737, 745-747 (1976); Green v. Richmond, 369 Mass. 47, 51-52 (1975); Arrow Plywood Corp. v. Eighty Boylston St. Corp., 360 Mass. 705, 706-707 (1972).

3. Effect of the admissions. Under Dist. Mun. Cts. R. Civ. P. 36 (1975), Reynolds’ failure to respond to the Leonards’ request for admissions conclusively established the truth of those admissions for this case. This remains true regardless of the importance of the matters thus deemed to be admitted. See Rome v. United States, 450 F. Supp. 378, 383 (D.C. 1978), aff’d, 446 U.S. 156 (1980). See also Wang Laboratories, Inc. v. Docktor Pet Centers, Inc., 12 Mass. App. Ct. 213, 214 (1981) (admitted matter the basis of plaintiff’s affirmative case); Equal Employment Opportunity Comm’n v. Baby Prods. Co., 89 F.R.D. 129, 132 (E.D. Mich. 1981) (admitted matter sufficient basis for granting summary judgment). 7

*260 The judge is empowered by the rule to permit withdrawal or amendment of the admission. The effect of the rule in a given case may be unduly harsh, and the ability of the judge to exert an ameliorating influence is essential to avoid a result in which form triumphs over substance. The judge may ameliorate the effect of the rule when: (1) the presentation of the merits of the action will be advanced, and (2) the party obtaining the admission fails to satisfy the court that withdrawal or amendment will prejudice him in maintaining his action or defense on the merits. See rule 36 (b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lance Toron Hous. v. Hosley
113 N.E.3d 934 (Massachusetts Appeals Court, 2018)
ANJ Corp. v. Ross
2014 Mass. App. Div. 12 (Mass. Dist. Ct., App. Div., 2014)
Jackson v. Byrne
2011 Mass. App. Div. 257 (Mass. Dist. Ct., App. Div., 2011)
Adkins v. Salisbury Nursing & Rehabilitaion Center, Inc.
25 Mass. L. Rptr. 8 (Massachusetts Superior Court, 2008)
Merritt v. United Parcel Service
956 A.2d 1196 (Supreme Court of Delaware, 2008)
Baker Tanks, Inc. v. Construction Management Trust, Inc.
2008 Mass. App. Div. 113 (Mass. Dist. Ct., App. Div., 2008)
Houston v. Houston
834 N.E.2d 297 (Massachusetts Appeals Court, 2005)
Northboro Inn, LLC v. Treatment Plant Board
792 N.E.2d 690 (Massachusetts Appeals Court, 2003)
Yankee Microwave, Inc. v. Petricca Communications Systems, Inc.
760 N.E.2d 739 (Massachusetts Appeals Court, 2002)
Massachusetts Highway Department v. Smith
747 N.E.2d 1235 (Massachusetts Appeals Court, 2001)
O'Kelly v. BASF Magnetics Corp.
13 Mass. L. Rptr. 167 (Massachusetts Superior Court, 2001)
Hastings Associates, Inc. v. Local 369 Building Fund, Inc.
675 N.E.2d 403 (Massachusetts Appeals Court, 1997)
Ellis v. Safety Insurance
672 N.E.2d 979 (Massachusetts Appeals Court, 1996)
Caron v. General Motors Corp.
643 N.E.2d 471 (Massachusetts Appeals Court, 1994)
Meagher v. United States Fidelity & Guaranty Co.
1994 Mass. App. Div. 134 (Mass. Dist. Ct., App. Div., 1994)
Energy North Inc. v. Gelardi
1991 Mass. App. Div. 150 (Mass. Dist. Ct., App. Div., 1991)
Currie v. Doherty
1990 Mass. App. Div. 149 (Mass. Dist. Ct., App. Div., 1990)
Krohn v. Wildfeuer
1987 Mass. App. Div. 202 (Mass. Dist. Ct., App. Div., 1987)

Cite This Page — Counsel Stack

Bluebook (online)
480 N.E.2d 1, 395 Mass. 255, 1985 Mass. LEXIS 1577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-aluminum-building-products-co-v-leonard-mass-1985.