Jim Walsh Plumbing Co. v. Cresta Construction, Inc.

3 Mass. L. Rptr. 29
CourtMassachusetts Superior Court
DecidedNovember 8, 1994
DocketNo. 92-1085
StatusPublished
Cited by1 cases

This text of 3 Mass. L. Rptr. 29 (Jim Walsh Plumbing Co. v. Cresta Construction, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jim Walsh Plumbing Co. v. Cresta Construction, Inc., 3 Mass. L. Rptr. 29 (Mass. Ct. App. 1994).

Opinion

Gershengorn, J.

This action arises out of a public construction contract entered into between defendant Cresta Construction, Inc. (“Cresta”) and third-party defendant, Commonwealth of Massachusetts. Plaintiff, Jim Walsh Plumbing Co., Inc. (“Walsh”), pursuant to G.L.c. 149, §29, asserts that Cresta owes it $60,556 for work performed under the parties’ subcontract. In response to Walsh’s claim, Cresta impleaded the Commonwealth as a third-party defendant and asserted various counterclaims against Walsh. In sum, Creta asserts that both Walsh and the Commonwealth are liable to Cresta for delay damages and bonus payments as well as other charges.

Cresta also seeks damages from Walsh’s insurance carrier, Commercial Union Insurance Co. Walsh and Commercial Union, pursuant to Mass.R.Civ.P. 56, have moved for summary judgment on Count I of Cresta’s counterclaim and the Commonwealth has moved for summary judgment on Count II of Cresta’s third-party complaint. For the reasons that follow, Walsh and Commercial Union’s motion for summary judgment is allowed and the Commonwealth’s motion for summary judgment is allowed.

BACKGROUND

The relevant facts pertinent to the disposition of the parties’ motions are not in dispute and can be briefly summarized. In August 1989, the Commonwealth and Cresta entered into a public contract for the Medfield State Hospital project. Subsequently, Cresta and Walsh entered into a subcontract for the HVAC work.

[30]*30The general contract between Cresta and the Commonwealth provided that if Cresta were to complete the project within 270 days from the notice to proceed or by May 18, 1990, Cresta was to receive bonus payments of $3,500.00 per day of early completion. The contract required Cresta to give 45% of the bonus payments to the subcontractors. The project was not completed until August 10, 1990, and neither Cresta nor the subcontractor received any bonus payments.

The general contract further provided that in lieu of actual damages for untimely completion of the project, Cresta could be assessed liquidated damages of $3,500.00 per day for each day the project remained uncompleted after 280 days.1 Despite the fact that Cresta did not complete the project on time (i.e., May 18, 1990), the Commonwealth has not assessed any liquidated damages to date.

Moreover, the general contract contained ano delay damages clause, which provided,

Except as otherwise provided by law the contractor shall not be entitled to damages on account of any hindrances or delays, avoidable or unavoidable; but if such delay be occasioned by the awarding authority, the contractor may be entitled to an extension of time only, in which to complete the work, to be determined by the Designer.
Every contract subject to the provisions of section thirty-nine M of Chapter 30 or subject to section forty-four A of Chapter one hundred forty-nine shall contain the following provisions (a) and (b) in their entirely and, in the event of suspension, delay, interruption or failure to act of the awarding authority increases the cost of performance to any subcontractor, that subcontractor shall have the same rights against the general contractor for payment for an increase in the cost of his performance as provisions (a) and (b) give the general contractor against the awarding authority, but nothing in provisions (a) and (b) shall in anyway (sic) change, modify or alter any other rights which the general contractor or the subcontractor may have against each other.
(a) The awarding authority may order the general contractor in writing to suspend, delay, or interrupt all or any part of the work for such period of time as it may determine to be appropriate for the convenience of the awarding authority; provided however, that if there is a suspension, delay or interruption for fifteen days or more or due to a failure of the awarding authority to act within the time specified in this contract, the awarding authority shall make an adjustment in the contract price for any increase in the cost of performance of this contract but shall not include any profit to the general contractor on such increase; and provided further, that the awarding authority shall not make any adjustment in the contract price under this provision for any suspension, delay, interruption or failure to act to the extent that such is due to any cause for which this contract provides for an equitable adjustment of the contract price under any other contract provisions.
(b) The general contractor must submit the amount of a claim under provision (a) to the awarding authority in writing as soon as practicable after the end of the suspension, delay, interruption or failure to act and, in any event, not later than the date of final payment under this contract and except for costs due to a suspension order, the awarding authority shall not approve any costs in the claim incurred more than twenty days before the General contractor notified the awarding authority in writing of the act or failure to act involved in the claim.

Pursuant to Cresta and Walsh’s subcontract, the parties are bound by the provisions of the general contract. In particular, the subcontract provides,

(a) The Subcontractor agrees to be bound to the Contractor by the terms of the hereinbefore described plans, specifications (including all general conditions stated therein) and addenda No. 1, and 2, and to assume to the Contractor all the obligations and responsibilities that the Contractor by those documents assumes to the Commonwealth of Massachusetts hereinafter called the “Awarding Authority," except to the extent that provisions contained therein are by their terms or by law applicable only to the Contractor.
(b) The contractor agrees to be bound to the Subcontractor by the terms of the hereinbefore described documents and to assume to the Subcontractor all the obligations and responsibilities that the Awarding Authority by the terms of the hereinbefore described documents assumes to the Contractor, except to the extent that provisions contained therein are by their terms or by law applicable only to the Awarding Authority.

DISCUSSION

1. Cresta’s Claim for Bonus Payments

Cresta alleges that Walsh is liable for bonus payments because Walsh’s actions forced Cresta to unseasonably complete the contract and thus lose the bonus payments. Assuming arguendo that Walsh caused the completion of the contract to be delayed, Walsh is only liable to Cresta to the extent that contract provides for liability. The contract is silent as to this issue and plaintiff cannot point to any written specifications which trigger liability for missed bonus payments. Absent an affirmative demonstration that Walsh undertook liability for the bonus payments or that the subcontract was premised on the bonus payments, see and compare Caputo v. Continental ConstructionCorp., 340 Mass. 15 (1959) (oral evidence that subcontract required subcontractor to speedily complete project so as to allow contractor to take advantage of bonus clause in general contract with [31]*31Commonwealth improperly excluded as proffered subcontract did not constitute entire agreement between parties),2 Cresta is bound by the clear terms of the contract. See Fred H. McClean Heating Supplies, Inc. v. Jefferson Construction Co., 339 Mass. 356, 362-63 (1959); Erickson v. George B.H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regency Construction & Management, Inc. v. BBC Co.
22 Mass. L. Rptr. 671 (Massachusetts Superior Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
3 Mass. L. Rptr. 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jim-walsh-plumbing-co-v-cresta-construction-inc-masssuperct-1994.