Erickson v. George B. H. Macomber Co.

97 N.E. 615, 211 Mass. 311, 1912 Mass. LEXIS 781
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 29, 1912
StatusPublished
Cited by9 cases

This text of 97 N.E. 615 (Erickson v. George B. H. Macomber Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Erickson v. George B. H. Macomber Co., 97 N.E. 615, 211 Mass. 311, 1912 Mass. LEXIS 781 (Mass. 1912).

Opinion

Sheldon, J.

The question whether the defendant was required to make the third floor water-tight, depending entirely upon the construction of the language of the contract and specifications, was one of law for the court and ought not to have been left to the jury. Globe Works v. Wright, 106 Mass. 207, 216. Goldstein v. D’Arcy, 201 Mass. 312, 317. No doubt, if.the jury had answered the question correctly, this would have been harmless error. [318]*318Bouvé v. Cottle, 143 Mass. 310, 315. But they did not do so. The contract and specifications stated carefully and particularly just what the defendant was required to do, and the details of the manner in which it was to do this. It was not bound to go further and bring about a result which it had not agreed to accomplish. Evidently the plaintiff had expected and intended to obtain a water-tight floor. But he selected himself the exact means and mode of construction upon which he relied for the accomplishment of his purpose, and stipulated that the defendant should follow precisely the course thus marked out for it. The defendant could not be held to guarantee that this mode of construction would produce a water-tight floor, or to go beyond what it had agreed to do for this end. Burke v. Dunbar, 128 Mass. 499.

The stipulation that the floor was “to be guaranteed and kept in repair for two years” does not import an agreement to keep it water-tight. This could not mean more than a guaranty that the work and materials which the defendant was to supply should remain in good order and condition for the specified time. Certainly it could not imply an agreement that the floor should continue to possess a quality which there was no agreement that it should have.

So far as the ordering of a verdict rested upon this ground, it cannot be sustained. On the contrary the judge should have ruled as requested by the defendant that it was not required that the floor should be water-tight.

But the defendant had agreed to execute all its work “in the best and most substantial manner and to the satisfaction of the architect.” The jury have found that the defendant’s conduct in driving nails through the asphalt was a negligent and improper way of complying with the specifications. We assume that this finding was made upon competent evidence and under proper instructions. If so, it settled the question that the defendant, in this respect at least, had failed to carry out its agreement. Unless there was some other issue that also must be passed upon, it would follow that the verdict for the plaintiff rightly was ordered, and . only the amount of damages would remain open.

But there was another issue in the case. There was evidence that the architect had put in as clerk of the works one Willard, whose duty, according to the testimony of the architect, it was, [319]*319to the best of his ability, to look after the interests of the owner and to see that the work went on according to the plans and specifications. These was evidence that when the nails were driven into the asphalt to secure the board flooring, this method was approved by Willard, who said that he could see no other way of fastening the flooring. The manner in which the flooring should be fastened was not fixed by the specifications; but on the evidence another method might have been adopted which would not have made holes in the asphalt. The architect gave certificates for the earlier partial payments and for the final payment to be made under the contract, and the whole amount due thereunder was paid by the plaintiff to the defendant. There was evidence that the final certificate was given after some leaks had been discovered; and on all the evidence of the architect himself and that of Cross,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jim Walsh Plumbing Co. v. Cresta Construction, Inc.
3 Mass. L. Rptr. 29 (Massachusetts Superior Court, 1994)
Cumberland Farms, Inc. v. Drehmann Paving & Flooring Co.
520 N.E.2d 1321 (Massachusetts Appeals Court, 1988)
Biggs v. Densmore
80 N.E.2d 38 (Massachusetts Supreme Judicial Court, 1948)
Medlinsky v. Premium Cut Beef Co.
57 N.E.2d 31 (Massachusetts Supreme Judicial Court, 1944)
Hunter v. Smith
7 Conn. Super. Ct. 157 (Connecticut Superior Court, 1939)
Hunter v. Smith
7 Conn. Supp. 157 (Pennsylvania Court of Common Pleas, 1939)
Mathey v. Louis G. Freeman Co.
1 Mass. App. Div. 167 (Mass. Dist. Ct., App. Div., 1936)
L. E. Fosgate Co. v. Spokane Valley Growers Union
160 N.E. 297 (Massachusetts Supreme Judicial Court, 1928)
H. D. Foss & Co. v. Whidden
149 N.E. 679 (Massachusetts Supreme Judicial Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
97 N.E. 615, 211 Mass. 311, 1912 Mass. LEXIS 781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/erickson-v-george-b-h-macomber-co-mass-1912.