Cumberland Farms, Inc. v. Drehmann Paving & Flooring Co.

520 N.E.2d 1321, 25 Mass. App. Ct. 530
CourtMassachusetts Appeals Court
DecidedMarch 29, 1988
Docket87-90
StatusPublished
Cited by19 cases

This text of 520 N.E.2d 1321 (Cumberland Farms, Inc. v. Drehmann Paving & Flooring Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cumberland Farms, Inc. v. Drehmann Paving & Flooring Co., 520 N.E.2d 1321, 25 Mass. App. Ct. 530 (Mass. Ct. App. 1988).

Opinion

Smith, J.

On November 1, 1979, V.S.H. Realty, Inc. (VSH), brought a complaint in the Superior Court against Drehmann Paving & Flooring Co. (Drehmann) as a result of certain problems that VSH had experienced with a brick and tile floor installed in a dairy plant by Drehmann. In its complaint, VSH charged that Drehmann had violated its implied warranty obligations under the Uniform Commercial Code by selling and installing an acid-proof brick floor for a dairy processing room which began to deteriorate two and one-half years after VSH installed it. The complaint also alleged that the failure of the floor constituted a breach of contract and that Drehmann was negligent in installing the floor. Drehmann denied all the allegations, and the matter was tried before a judge sitting without a jury. After the trial the judge found in favor of Drehmann, and judgment was entered accordingly. VSH has appealed from that judgment.

We summarize the judge’s findings of fact, none of which are challenged by VSH. We supplement the findings with undisputed evidence that is not dependent on assessments of credibility. In January 1976, under the direction of Richard Longton, its vice-president in charge of construction, VSH drafted blueprints for a dairy plant in Florence, New Jersey. *532 VSH then became the general contractor for the construction of the plant.

In November 1976, Longton telephoned John Grelis, the executive vice-president of Drehmann. Longton informed Grel-is that VSH was constructing a dairy plant in New Jersey that required an acid-proof floor. Drehmann had been engaged for many years in the business of manufacturing and installing brick flooring in food and dairy processing facilities. Drehmann held itself out as an expert in that field. Longton requested Grelis to visit the Florence site and submit a proposal. He informed Grelis that the flooring should be similar to the flooring previously installed by Drehmann in VSH’s facility in Canton.

Grelis visited the construction site and spoke to one Joseph Tuch, VSH’s on-site superintendent. Tuch showed Grelis plans of the proposed floor. The plans showed the thickness, the kind and size of bricks to be used, the type of grouting, and the location of expansion joints around the perimeter of the floor. No expansion joints were located at the high points of the floor. In addition, Grelis was specifically informed that the floor to be installed by Drehmann was to be similar to the floor it had installed in Canton.

On November 9, 1976, Grelis sent a written proposal to Tuch and quoted a price of $31,251 for the installation of 9,500 square feet of Drehmann Smooth Surface Brick in the dairy processing room. 2 The proposal included expansion joints around the perimeter of the floor but did not include expansion joints at the high points, or column lines, that would bisect *533 the graded floor. The floor which Drehmann had installed in Canton for VSH did not have expansion joints at the high points. Longton accepted the proposal on condition that the price be reduced to $30,000, and Grelis accepted that modification. The accepted proposal constituted the only contract between the parties.

*532 “For the sum of THIRTY ONE THOUSAND TWO HUNDRED FIFTY ONE DOLLARS ($31,251.00), we will complete the work outlined.
The Work Included in this Proposal
“1. Over the existing graded concrete slab, we will pave Drehmann 4" x 8" x P/ie" Smooth Face brick in a sand and cement bed of uniform thickness.
“2. Upon completion of paving, we will grout initially with liquid Portland cement in order to lock the brick to the setting bed.
“3. The top portion of the joints (approximately Vi") is to be grouted with Drehmann Plastic Floor Grout (epoxy).
“4. We will install beveled turn up brick complete with premolded asphalt expansion joint, topped with elastic sealer at the walls.”

*533 Before the floor was installed, Grelis recommended to Tuch that the floor should have expansion joints at the high points in addition to those around the perimeter. Tuch conveyed the recommendation to Longton, who rejected it. Grelis was not asked, nor did he explain, the ramifications, if any, if the additional expansion joints were not installed.

During the course of the installation of the floor, Tuch was replaced by one Butterfield as construction supervisor. Butter-field expressed his concern to Longton that expansion joints were not being installed at the high points and recommended their installation. Longton rejected Butterfield’s recommendation. Butterfield observed Drehmann’s work daily and, except for his concern about the lack of expansion joints, never complained to Longton that Drehmann was not performing its work properly. Drehmann completed the work in accordance with its agreement by the end of February, 1977.

Problems developed with the floor about two and one-half years after installation. Some of the bricks came up in pyramid fashion and fell loose at some of the high points on the floor. Cumberland continued to use the room, with the result that areas beneath the heaved bricks were exposed to hot water, corrosive lactic acids, and detergents. In 1979 Grelis, at Longton’s request, inspected the floor. In a letter dated June 21, 1979, Grelis proposed to Longton that Drehmann would repair the floor by adding expansion joints at the high points and replacing the brick and setting bed for a width of sixteen feet on either side of the high points in both the length and width of the processing room. The cost of the repair would be $23,020. Longton consulted with experts and, in a letter dated July 17, 1979, called on Drehmann to repair the floor at its own expense. Drehmann refused to bear the expense.

*534 In September, 1979, another contractor replaced 883 square feet of the existing brick and setting bed at a cost of about $10,000. The floor continued to deteriorate, and in 1982 a different concern repaired a section north of the portion repaired in September, 1979, at a cost of $9,700. In 1983, as the floor continued to deteriorate, Hudson Valley Tile did repair work at a cost of $55,744.84, plus additional sums for material. To date, 6,400 square feet of the original floor have been repaired.

The trial judge found that the cause of the damage to the floor was the lack of expansion joints at the high points and that, if expansion joints had been installed as Grelis had recommended, the damage to the floor would not have occurred. He also found that Drehmann performed the work it was required to do under the contract with VSH in a good workmanlike manner.

1. Recovery under the Uniform Commercial Code. VSH asserted that Drehmann was in breach of the warranties set forth in G. L. c. 106, § 2-314 (implied warranty of merchantability) and § 2-315 (implied warranty of fitness for a particular purpose) of the Uniform Commercial Code (Code).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirk Ramey v. Beta Bionics, Inc.
D. Massachusetts, 2025
Carrozza v. CVS Pharmacy, Inc.
992 F.3d 44 (First Circuit, 2021)
Carrozza v. CVS Pharmacy, Inc.
D. Massachusetts, 2019
Carrozza v. CVS Pharmacy, Inc.
391 F. Supp. 3d 136 (District of Columbia, 2019)
Marvin Lumber & Cedar Co. v. Sapa Extrusions, Inc.
964 F. Supp. 2d 993 (D. Minnesota, 2013)
Hatch v. Trail King Industries, Inc.
656 F.3d 59 (First Circuit, 2011)
Siebe, Inc. v. Louis M. Gerson Co.
908 N.E.2d 819 (Massachusetts Appeals Court, 2009)
Waste Stream Environmental, Inc. v. Lynn Water & Sewer Commission
15 Mass. L. Rptr. 723 (Massachusetts Superior Court, 2003)
Mattoon v. City of Pittsfield
56 Mass. App. Ct. 124 (Massachusetts Appeals Court, 2002)
Commonwealth v. Johnson Insulation
682 N.E.2d 1323 (Massachusetts Supreme Judicial Court, 1997)
Boston Business Forms, Inc. v. Vantage Travel Services, Inc.
7 Mass. L. Rptr. 504 (Massachusetts Superior Court, 1997)
O'Donovan v. Burns
5 Mass. L. Rptr. 317 (Massachusetts Superior Court, 1996)
Malley v. Country Ski & Sport, Inc.
4 Mass. L. Rptr. 582 (Massachusetts Superior Court, 1995)
Penta v. Covino
1994 Mass. App. Div. 4 (Mass. Dist. Ct., App. Div., 1994)
Little, Brown & Co. v. American Paper Recycling Corp.
824 F. Supp. 11 (D. Massachusetts, 1993)
Hendricks v. Comerio Ercole
763 F. Supp. 505 (D. Kansas, 1991)
Itt Corporation v. Ltx Corporation
926 F.2d 1258 (First Circuit, 1991)
ITT Corp. v. LTX Corp.
926 F.2d 1258 (First Circuit, 1991)
ITT Corp. v. LTX Corp.
732 F. Supp. 1225 (D. Massachusetts, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
520 N.E.2d 1321, 25 Mass. App. Ct. 530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cumberland-farms-inc-v-drehmann-paving-flooring-co-massappct-1988.