This text of 230 Mass. 483 (Marsch v. Southern New England Railroad) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marsch v. Southern New England Railroad, 230 Mass. 483 (Mass. 1918).

Opinion

Pierce, J.

These are four actions of contract, founded upon the alleged failure of each of the several defendants to perform its part of an unsealed written contract entered into on July 20,1912, between the plaintiff and the defendant in the first action, for the construction by the plaintiff of a railroad from Palmer, Massachusetts, to the Rhode Island State line at a point in Blackstone, Massachusetts. In each action the plaintiff alleges that he has constructed the roadway according to the terms of the contract in conformity with the plans and specifications furnished him, and seeks to recover payment for the work done in accordance with'the provision of the contract; which contract, among other things, provides in substance by clauses 1 and 19 that the chief engineer of the Southern New England Railroad Corporation, the defendant in the first action, shall be “sole umpire to decide all such questions, matters, and disputes,” should any misunderstanding arise between the parties “regarding any of the stipulations and provisions contained in this Contract, or the true intent and meaning thereof, or the manner of performance thereof, or of any part thereof,” including “ any arising regarding the amount and quality, character and kind of work performed and material furnished by the Contractor.”

By clause 20 the corporation agreed to pay the plaintiff the amounts set down in the schedule thereto, only upon condition that he did and performed all things to be done and performed on his part “in strict accordance with the plans and specifications and to the entire satisfaction and approval of the Engineer.”

Clause 21 provides for monthly payments as the work progressed and for final payments upon the completion of the whole work, such payments, “less any sums which under any of the provisions [490]*490of this Contract the Corporation may be entitled to deduct therefrom, shall be made . . . upon presentation of written certificate of the Engineer showing the value of such work computed as aforesaid and stating that the work for or on account of which such certificate is granted has been duly performed and executed to his satisfaction and in accordance with the plans and specifications. The presentation of such certificate . . . shall be a condition precedent to the right of the Contractor to receive or be paid the amount so certified as due and unpaid or any part thereof, and such certificate,shall be conclusive as to the amount to be paid to the Contractor.”

Clause 23 provides in substance that such certificate shall be fina.1 and conclusive between the parties as to the measurements ' and valuations appearing therein and shall not be questioned by either party or set aside “on account of any legal defect therein or in this Contract, or on account of any informality, omission, delay or error in proceeding in or about the same or on any other ground or for any other reason, or upon any pretence, suggestion, charge, or insinuation of fraud, coercion, collusion or confederacy . . . and actual fraud only shall disqualify him [the engineer] from acting as aforesaid.”

The liability of the defendant is made conditional upon the presentation of the engineer’s certificate, which presentation is expressly made “a condition precedent to the right of the Contractor to receive or be paid the amount.” certified by the engineer. The allegation in the declarations in the several actions “that he [the plaintiff] has done and performed all acts and things which by the terms of said contract and agreement he was required to do and perform” is insufficient upon which to found a right of action. In addition thereto, it must be averred specifically that' the condition precedent was performed or the want of that performance excused. R. L. c. 173, § 6, cl. 11. Newcomb v. Brackett, 16 Mass. 161. Newton Rubber Works v. Graham, 171 Mass. 352. National Contracting Co. v. Commonwealth, 183 Mass. 89. As his reason for the non-performance of the conditions precedent, the plaintiff alleges in his several declarations that “said engineer did not act in good faith and according to his duty . . . but that he acted wilfully, capriciously, fraudulently, unreasonably and without excuse in refusing to give certificates contain[491]*491ing the proper amounts and quantities under a proper classification as provided under the terms of said contract.”

The defendant in each action moved to strike from the several counts of the several declarations the words “wilfully,” “capriciously,” “unreasonably” and "without excuse,” each of which plainly is a characterization of the conduct of the engineer, and when proved is averred to be sufficient to excuse the non-perform-once of the condition precedent.

The defendant in each action also moved to strike out the paragraph of the several declarations commencing “And the plaintiff further says that said engineer was prevented” and ending with the words “ any other person to act in his stead.”

Also, to strike out the paragraph of the several declarations beginning with “And the plaintiff further says that the defendant has wholly failed” and ending with the words “under the terms of said contract.”

Also, to strike out the paragraph of the several declarations between the words “And the plaintiff further says that although he was at all times ready” and the words “to abandon the construction and completion of said roadway.”

Also, to strike out that part of the plaintiff’s several declarations between the words “And the plaintiff further says that the defendant has failed” and the words “as required by the terms of said contract.”'

Also, to strike out that paragraph of the several declarations which commences with the words “And the plaintiff further says that certain portions of the work” and ends with the words "under the terms of said contract.”

Each of these motions was an irregular and anomalous way of raising for decision a pure question of substantive law, which under the common law and our practice act can be determined only on demurrer or by an objection to the admission of evidence when offered in proof of the alleged facts. R. L. c. 173, §§ 14, 16, cl. 2. Montague v. Boston & Fairhaven Iron Works, 97 Mass. 502. Saco Brick Co. v. J. B. Eustis Manuf. Co. 207 Mass. 312, 315. The granting of such a motion may result in legal error; the denial thereof never can. Gardner v. Webber, 17 Pick. 407. Gately v. Taylor, 211 Mass. 60, 65. Powers v. Bergman, 197 Mass. 39. Golding v. Wharton Saltworks Co. [492]*4921 Q. B. D. 374. Duncan v. Hargrove, 22 Ala. 150, 161. The motions were denied; and the issues raised thereby, together with certain other distinct issues raised by demurrers to the several counts of the declaration and hereinafter considered, were reported to this court under R. L. c. 173, § 105.

The questions of law attempted to be raised by the motion to strike out have been fully argued, and we therefore consider such questions on the footing of a demurrer to the allegations of fact in the declarations which the plaintiff asserts constitutes a sufficient excuse for his failure to secure the written certificates of the engineer before bringing his action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

My Bread Baking Co. v. Cumberland Farms, Inc.
233 N.E.2d 748 (Massachusetts Supreme Judicial Court, 1968)
Wes-Julian Construction Corp. v. Commonwealth
223 N.E.2d 72 (Massachusetts Supreme Judicial Court, 1967)
G. L. Rugo & Sons, Inc. v. Town of Lexington
157 N.E.2d 521 (Massachusetts Supreme Judicial Court, 1959)
291 Washington St. Inc. v. School St. Liquors, Inc.
117 N.E.2d 809 (Massachusetts Supreme Judicial Court, 1954)
Galdi v. Caribbean Sugar Co.
99 N.E.2d 69 (Massachusetts Supreme Judicial Court, 1951)
Psaty & Fuhrman, Inc. v. Housing Authority
68 A.2d 32 (Supreme Court of Rhode Island, 1949)
Wershba v. City of Lynn
86 N.E.2d 511 (Massachusetts Supreme Judicial Court, 1949)
Putnam Furniture Building, Inc. v. Commonwealth
80 N.E.2d 649 (Massachusetts Supreme Judicial Court, 1948)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Medlinsky v. Premium Cut Beef Co.
57 N.E.2d 31 (Massachusetts Supreme Judicial Court, 1944)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
M. McDonough Corp. v. Connolly
46 N.E.2d 576 (Massachusetts Supreme Judicial Court, 1943)
MacLennan v. MacLennan
42 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1942)
Bell v. Eames
39 N.E.2d 582 (Massachusetts Supreme Judicial Court, 1942)
First National Bank v. Mathey
31 N.E.2d 25 (Massachusetts Supreme Judicial Court, 1941)
Browne v. Brockton National Bank
26 N.E.2d 360 (Massachusetts Supreme Judicial Court, 1940)
Lowell v. Massachusetts Bonding & Insurance
23 N.E.2d 91 (Massachusetts Supreme Judicial Court, 1939)
Lakube v. Cohen
23 N.E.2d 144 (Massachusetts Supreme Judicial Court, 1939)
J. F. Fitzgerald Construction Co. v. Southbridge Water Supply Co.
23 N.E.2d 165 (Massachusetts Supreme Judicial Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
230 Mass. 483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marsch-v-southern-new-england-railroad-mass-1918.