National Contracting Co. v. Commonwealth

66 N.E. 639, 183 Mass. 89, 1903 Mass. LEXIS 718
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 27, 1903
StatusPublished
Cited by13 cases

This text of 66 N.E. 639 (National Contracting Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Contracting Co. v. Commonwealth, 66 N.E. 639, 183 Mass. 89, 1903 Mass. LEXIS 718 (Mass. 1903).

Opinion

Lathrop, J.

This is a petition under the R. L. c. 201, and is in the nature of an action to recover damages for breach of an entire contract for the building of a section of the metropolitan sewer. The petition proceeds upon the theory that the petitioner began work under the contract and was proceeding to do everything required by the contract, when the respondent, by its agents, broke the contract, and the petitioner ceased work, whereupon the respondent repudiated the contract. Four breaches of contract on the part of the respondent are alleged. We shall consider these in their order.

1. The first relates to the order of the engineer in charge of [91]*91the work that oak ribs should be used in place of pine ribs, and that the petitioner should cease to work until oak ribs should be substituted. This is the gist of the complaint, although it alleges that the contract provided that all timber work and lumber should be of spruce, and further sets forth that the engineer, in refusing to allow the use of pine, acted unreasonably and without color of reason. We are unable to see how any clause of the contract relating to spruce justifies the use of pine for ribs. Clause 46 of the specifications of the contract provides : “ Spruce lumber shall be used in the construction of wooden platforms for the foundation of the sewer, for pile caps, cradling, or other purposes, at such points, and of such description, as the engineer may direct.” This has nothing to do with the question before us.

The clauses which apply to the question before us are clauses 5 and 13. Clause 5 is as follows : “ All work, during its progress and on its completion shall conform to the lines and levels given by the engineer, and shall be built in accordance with the contract plan and directions given from time to time by him, subject to such modifications and additions as shall be deemed necessary by him during its execution; and in no case shall any work in excess of the requirements of the plans and specifications be paid for unless ordered in writing by him.” Clause 13 is as follows : “ The contractor shall furnish, put in place and maintain in the tunnel and shafts such sheeting, bracing, wooden ribs, metallic plates or lagging as may be required to support the sides and roof of the excavation (whether above or below sewer grade), and to prevent any movement which could in any way injure the masonry, diminish the width necessary for proper drainage, or otherwise injure or delay the work; all slides or caves to be at his cost. Where deemed necessary by the engineer, the contractor shall at his own cost, as provided in Article M, item a, install and use a metal shield to prevent slides, caves or settlement of the streets. If the engineer is of the opinion that at any point sufficient or proper supports have not been provided, he may order additional supports at the expense of the contractor, and the compliance with such orders shall not relieve or release the contractor from his responsibility for the sufficiency of such supports.” [92]*92We are of opinion that the engineer had the right to require oak ribs in place of pine ones, and that his judgment was final, unless he acted in bad faith, of which there is no suggestion. We are also of opinion that the petition is not strengthened by the allegation that the engineer acted unreasonably and without color of reason. This is disposed of by the recent case of Audette v. L' Union St. Joseph, 178 Mass, 113, 115.

2. The next allegation is in substance that the respondent was required by the contract, if an emergency should demand, to make alterations in the plan of the work; that an emergency did arise, namely, that the earth excavation and refilling in the tunnel was by the contract to be done by the use of compressed air to be pumped into the tunnel and to be held in by the surrounding material; that the surrounding material did not, in fact, hold the compressed air, or make, or allow of or make possible the construction of the earth excavation and refilling in the tunnel in the mode provided in the contract; and that an emergency arose which required the respondent to alter the plans, etc.

The only provision of the contract which provides for an excavation under air pressure is clause 11, which reads as follows : “ The shafts and tunnel are to be excavated under air pressure when necessary to prevent changes in adjacent ground-water levels. The contractor shall provide hydraulic machinery, air-pumps, engines and air locks, and shall make other ample provision (including reasonable duplication of plant) for maintaining the necessary degree of air pressure within the tunnel and shafts and for carrying on the other operations called for by this contract.”

There is nothing in the petition to show that when the alleged emergency occurred, the excavation under air pressure was within clause 11. Nor is there anything in the contract which calls for refilling in the tunnel under air pressure.

If these difficulties could be got over, we are still of opinion that the petitioner does not make out a case. The commissioners who signed the contract in behalf of the Commonwealth did not warrant against underground difficulties, but expressly provided to the contrary in clause 4, which reads as follows: “ The plots of borings, pipes and other underground objects are [93]*93supposed to be approximately correct; but should they be found to be otherwise, or should the contractor encounter quick-sand, springs, demoralized rock or other difficulties, he shall have no claim on that account, it being understood that the commissioners do not warrant the plot of underground objects to be even approximately correct,”

It was further provided that certain prices should be paid by the Commonwealth and received by the contractor in full compensation for work and labor, “for all loss or damage arising out of the nature of the work ... or from any unforeseen obstruction or difficulties which may be encountered in the prosecution of the same; and for all risks of every description connected with the work.”

The petitioner relies upon the emergency clause, so called, which begins thus : “ It is further agreed that if an emergency demands, or if the engineer deems it desirable, he may make alterations in the line, grade, plan, form, position, dimensions or material of the work herein contemplated, or of any part thereof, either before or after the commencement of construction.” The clause then goes on to provide for the method of payment if this is done.

The petitioner contends that the word “ may ” means “ shall,” and that it was the duty of the engineer to make alterations. It is true that the word “ may ” is sometimes construed to mean “shall,” but we are of opinion that the emergency clause, so called, was intended for the benefit of the Commonwealth alone, and that the word “ may ” has its usual meaning.

3. The next breach alleged is that the Commonwealth was required by the contract, once in each week, to make and furnish an approximate estimate of the amount of work done and its value, and to furnish the contractor with an order for the payment of eighty-five per cent of the value estimated as aforesaid; that after the week ending January 6, w'ork was done upon the rock excavation in the tunnel, which was a separate and distinct portion of the contract, and that the Commonwealth did not furnish such estimate or order after the week ending January 6, 1892.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hillman v. Second Bank-State Street Trust Co.
153 N.E.2d 651 (Massachusetts Supreme Judicial Court, 1958)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Coleman Bros. v. Commonwealth
29 N.E.2d 832 (Massachusetts Supreme Judicial Court, 1940)
Marsch v. Southern New England Railroad
230 Mass. 483 (Massachusetts Supreme Judicial Court, 1918)
Dubinsky v. Wells Bros.
218 Mass. 232 (Massachusetts Supreme Judicial Court, 1914)
Hathaway v. Stone
215 Mass. 212 (Massachusetts Supreme Judicial Court, 1913)
C. W. Hunt Co. v. Boston Elevated Railway Co.
85 N.E. 446 (Massachusetts Supreme Judicial Court, 1908)
Norcross Bros. v. Vose
85 N.E. 468 (Massachusetts Supreme Judicial Court, 1908)
Commonwealth v. National Contracting Co.
85 N.E. 86 (Massachusetts Supreme Judicial Court, 1908)
McArthur Bro's v. Commonwealth
83 N.E. 334 (Massachusetts Supreme Judicial Court, 1908)
Ark-Mo Zinc Co. v. Patterson
96 S.W. 170 (Supreme Court of Arkansas, 1906)
Bush v. Jones
144 F. 942 (Third Circuit, 1906)
Hebert v. Dewey
77 N.E. 822 (Massachusetts Supreme Judicial Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
66 N.E. 639, 183 Mass. 89, 1903 Mass. LEXIS 718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-contracting-co-v-commonwealth-mass-1903.