Commonwealth v. National Contracting Co.

85 N.E. 86, 198 Mass. 554, 1908 Mass. LEXIS 983
CourtMassachusetts Supreme Judicial Court
DecidedMay 20, 1908
StatusPublished

This text of 85 N.E. 86 (Commonwealth v. National Contracting Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. National Contracting Co., 85 N.E. 86, 198 Mass. 554, 1908 Mass. LEXIS 983 (Mass. 1908).

Opinion

Loring, J.

On November 12,1900, the Commonwealth, acting by its board of metropolitan sewerage commissioners, made a written agreement with the National Contracting Company, one of the defendants in this action, for the construction of a specified section of a sewer for the metropolitan system of sewerage provided for by St. 1889, c. 439, and the acts in amendment therof.

The Contracting Company as principal, and the National Surety Company (the other defendant to this action) as surety signed a bond in the sum of $50,000, conditioned in substance for the Contracting Company’s performing its contract and indemnifying and saving the Commonwealth harmless as therein stipulated.

By clause L of the contract the Contracting Company agreed that if the work should be abandoned, “ or if at any time the engineer shall be of the opinion, and shall so certify in writing to the board, that the said work is unnecessarily or unreasonably delayed, . . . the board shall have the power and right to notify the contractor to discontinue all work,” and in that case the board shall have power to complete the same at the expense of the contractor.

It is stated in the beginning of the contract between the Commonwealth and the Contracting Company that “ Wherever the word ‘ Board,’ or a pronoun in place of it, is used in this agreement the same is understood to mean the board of metropolitan sewerage commissioners of Massachusetts,” and that “ Wherever the word ‘ Engineer,’ or a pronoun in place of it, is used in this agreement, the same is understood to mean the chief engineer of the said board, acting either directly or through his properly authorized agents, such agents acting within the scope of the particular duties intrusted to them.”

Work was begun under this contract at one point on December 1,1900, and at the other point on February 1, 1901.

On March 20, 1901, St. 1901, c. 168, was enacted and took effect upon its passage. That act created a board to be known as the metropolitan water and sewerage board. By § 5 of [558]*558that act the metropolitan water board (a board created by St. 1895, c. 488, to construct a metropolitan water supply) and the board of metropolitan sewerage commissioners were abolished, and “ all the powers, rights, duties and liabilities of ” the two boards which were abolished were transferred to the new board. This section ends with this provision: “ No existing contracts, liabilities or suits shall be affected hereby, but the board hereby created shall in all respects and for all purposes whatsoever be the lawful successor of said metropolitan water board and of said board of metropolitan sewerage commissioners.”

On January 16, 1902, one W. M. Brown, as “ Engineer Sewerage Works,” certified that the work done under the contract here in question has been unnecessarily and unreasonably delayed and abandoned,” and recommended “ that the work be taken and completed as provided in Article L.” This certificate was addressed to the new board. Acting under it the new board undertook to complete the work at the expense of the Contracting Company.

On the completion of the work by the new board, a demand was made by it on the Contracting Company for the payment of $178,355, as the excess paid by it for completing the work over and above the contract price. This demand was made on December 2, 19Q3, and on December 8, 1903, this action was brought.

The case was sent to an auditor. He found that $129,069. 73 was the amount of the excess, and reported that in this action on the bond the plaintiff was entitled to recover the penal sum.

The case came on for trial by a jury. Some of the rulings asked for by the defendant were refused and exceptions taken. The only question submitted to the jury was whether the notice required by Section L of the contract was sent to the defendant National Contracting Company on December 2, 1903. This was answered in the affirmative, and thereupon the presiding judge directed a verdict for the plaintiff.

The thirteenth ruling.asked for ended with these words: “ Nor is it proved that any person within the definition of engineer did certify.”

The auditor in his report found: “ After its organization the new board appointed Wm. M. Brown who was and for ten years [559]*559had been the chief engineer of the old board, its engineer of the sewerage works under its charge, and he so continued and still is such engineer.”

At the trial Brown was called as a witness by the defendants and testified “ that in December, 1900, he was chief engineer of the metropolitan sewerage commissioners, that he ceased to hold said position when that board ceased to exist, that that board was succeeded by a consolidated board and that Frederick P. Stearns was the chief engineer of the consolidated board and had held that office since the consolidation, and that he (Brown) was not an authorized agent of Stearns; that at the time of trial he was engineer to the metropolitan sewerage works and that he had charge of the work on section 73

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palmer v. Clark
106 Mass. 373 (Massachusetts Supreme Judicial Court, 1871)
Flint v. Gibson
106 Mass. 391 (Massachusetts Supreme Judicial Court, 1871)
Robbins v. Clark
129 Mass. 145 (Massachusetts Supreme Judicial Court, 1880)
National Contracting Co. v. Commonwealth
66 N.E. 639 (Massachusetts Supreme Judicial Court, 1903)
Norcross v. Wyman
72 N.E. 347 (Massachusetts Supreme Judicial Court, 1904)
Lewis v. Brotherhood Accident Co.
79 N.E. 802 (Massachusetts Supreme Judicial Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.E. 86, 198 Mass. 554, 1908 Mass. LEXIS 983, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-national-contracting-co-mass-1908.