G. L. Rugo & Sons, Inc. v. Town of Lexington

157 N.E.2d 521, 338 Mass. 746, 1959 Mass. LEXIS 710
CourtMassachusetts Supreme Judicial Court
DecidedApril 2, 1959
StatusPublished
Cited by14 cases

This text of 157 N.E.2d 521 (G. L. Rugo & Sons, Inc. v. Town of Lexington) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. L. Rugo & Sons, Inc. v. Town of Lexington, 157 N.E.2d 521, 338 Mass. 746, 1959 Mass. LEXIS 710 (Mass. 1959).

Opinion

Spalding, J.

The plaintiff and the defendant entered into a contract in writing dated May 25, 1955, for the erec- 1 tian of a school building in Lexington. During the course of the work disputes arose as to whether the contract called for strapping the ceilings of the first floor classrooms and administration areas, and whether it called for the strapping of the ceilings of the cafeteria and auditorium to be twelve inches on center or sixteen inches on center. Pursuant to article 39 of the supplementary general conditions of the contract the controversy was submitted to the architect, who decided that the contract called for strapping the ceilings of the first floor classrooms and administration areas, and required the strapping of the ceilings of the cafeteria and auditorium to be twelve inches on center. The plaintiff installed the strapping in accordance with the architect’s determination, and submitted the question whether this *748 work constituted an extra to a panel of three arbitrators in the manner provided in article 40 of the supplementary general conditions of the contract. That article reads in part: “. . . Arbitration: If any controversy arises under the contract which may legally be submitted to arbitration, it shall be determined by arbitration pursuant to chapter 251 of the Massachusetts General Laws as amended. . . . The arbitrator or arbitrators shall determine the controversy in accordance with the law of Massachusetts as applied to the facts found by him or them, and at the request of either party shall refer any questions of law to the proper court. In event of any discrepancy between this article 40 and other provisions of the general conditions, the provisions of this article 40 shall govern.”

The panel made an independent examination of the plans and specifications and found, one arbitrator dissenting, that the strapping installed by the plaintiff constituted an extra. The total fair cost of this work was computed at $3,795.92. But the panel concluded that the controversy was governed by the clause in article 39 which provides that the architect “shall decide all questions which may arise as to the interpretation of the plans and specifications and as to the fulfillment of the contract on the part of the contractor, and his determination and decision shall be final and conclusive.” Accordingly, the arbitrators ruled that the architect’s decision on the question of strapping was final and conclusive, and for that reason the plaintiff was not entitled to payment. „ The arbitrators’ award was filed in the Superior Court. See G. L. c. 251, § 8. The plaintiff submitted motions to correct the award and to enter judgment for it on the award, which were denied. The defendant moved for entry of judgment on the arbitrators’ award and the motion was allowed.

The question of the correctness of these rulings is brought here by appeal (G. L. c. 251, § 12) and by exceptions. Since all the questions sought to be raised are open on the exceptions, there is no need to consider the appeal and it is dismissed.

*749 1. The plaintiff’s principal contention is that the contract, properly construed according to the law of Massachusetts, does not sustain the arbitrators’ conclusion that the architect’s decision settled the controversy. This contention is grounded upon an assertion that the clause in article 39 upon which the arbitrators relied was taken out of context, and that article 39, when read as a whole, makes the architect the final arbiter as to questions concerning the quality of the work, but not as to what work was required by the plans and specifications.

That part of article 39 material here provides: “The architect shall decide all questions which may arise as to the quality, quantity, acceptability, fitness and rate of progress of the several kinds of work and materials to be performed and furnished under the contract, and shall decide all questions which may arise as to the interpretation of the plans and specifications and as to the fulfillment of the contract on the part of the . . . [plaintiff], and his determination and decision shall be final and conclusive . . ..”

The plaintiff argues that the clause relating to the interpretation of the plans and specifications is subordinate to the clause relating to the quality of the work, and relies upon the decision of this court in Morgan v. Murdough, 216 Mass. 502. The contract involved in that case conferred the power of final decision upon the architect only with regard to questions concerning “. . . the quality, acceptableness and fitness of the Several kinds of work and materials ... to be included in . . . [the] contract . . . .” It was held that this clause did not give the architect power to decide conclusively that certain marble dado work was required by the plans and specifications and was not an extra. His power was limited to disputes relating “to the quality or character of the work performed or the materials furnished,” a dispute of a different nature.

But a case much closer to the case at bar is Norcross v. Wyman, 187 Mass. 25. There the relevant portion of the contract provided: “The architects shall be the sole interpreters of their drawings and these specifications, and *750 . . . their decision upon all questions relative to drawings, specifications or contract for the said building shall be final and binding upon the owner and the contractor.” A question arose as to whether work done in connection with the foundation, due to the existence of an unforeseen quicksand, was an extra. The architects decided that it was, and the parties submitted the dispute to arbitration under E. L. c. 194, a predecessor, in part, of G. L. c. 251. The arbitrator ruled that the architects were authorized to act on the question and that their decision was binding on the parties. On appeal this court upheld the arbitrator’s ruling. The authority of Norcross v. Wyman, supra, was not impaired by anything decided in the Morgan case. In the Morgan case the authority of the Norcross case was recognized but was held not to be controlling on the ground that the grant of power then before it was more restricted than that involved in the Norcross case.

Article 39 of the contract grants to the architect both the power involved in the Morgan case and the power involved in the Norcross case. The plaintiff’s argument that the second power is subordinate to the first power must be rejected. We are of opinion that a natural reading of the contract can result only in the conclusion that the two clauses are independent each from the other. The second clause confers the power to decidé “all questions which may arise as to the interpretation of the plans and specifications” (emphasis supplied). There is no internal evidence that this power was to be exercised only with regard to the quality and quantity of the several kinds of work and materials referred to in the first clause. “The ordinary and natural scope and effect to be attributed to any article are not to be restricted or limited by undue emphasis accorded to some other provision.” J. F. Fitzgerald Constr. Co. v. Southbridge Water Supply Co. 304 Mass. 130, 135.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)
Smith v. Allmon
461 N.E.2d 1237 (Massachusetts Appeals Court, 1984)
J.J. Finn Electrical Service, Inc. v. P & H General Contractors, Inc.
432 N.E.2d 116 (Massachusetts Appeals Court, 1982)
Trustees of Boston & Maine Corp. v. Massachusetts Bay Transportation Authority
294 N.E.2d 340 (Massachusetts Supreme Judicial Court, 1973)
Henry B. Byors & Sons, Inc. v. Board of Water Commissioners of Northborough
264 N.E.2d 657 (Massachusetts Supreme Judicial Court, 1970)
ALBRE MARBLE & TILE CO. INC. v. Goverman
233 N.E.2d 533 (Massachusetts Supreme Judicial Court, 1968)
Fazio v. EMPLOYERS'LIABILITY ASSURANCE CORP. LTD.
197 N.E.2d 598 (Massachusetts Supreme Judicial Court, 1964)
McLaughlin v. New England Telephone & Telegraph Co.
188 N.E.2d 552 (Massachusetts Supreme Judicial Court, 1963)
Salem Glass Co. v. Joseph Rugo, Inc.
176 N.E.2d 30 (Massachusetts Supreme Judicial Court, 1961)
Farm-Rite Implement Co. v. Fenestra Inc.
163 N.E.2d 285 (Massachusetts Supreme Judicial Court, 1960)
Fred C. McClean Heating Supplies, Inc. v. Jefferson Construction Co.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
FRED C. McCLEAN HEATING SUPPLIES v. JEFFERSON CONSTR.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
Campanella & Cardi Construction Co. v. Commonwealth
158 N.E.2d 304 (Massachusetts Supreme Judicial Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
157 N.E.2d 521, 338 Mass. 746, 1959 Mass. LEXIS 710, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-l-rugo-sons-inc-v-town-of-lexington-mass-1959.