City of Haverhill v. George Brox, Inc.

716 N.E.2d 138, 47 Mass. App. Ct. 717, 1999 Mass. App. LEXIS 1025
CourtMassachusetts Appeals Court
DecidedSeptember 15, 1999
DocketNo. 97-P-1896
StatusPublished
Cited by71 cases

This text of 716 N.E.2d 138 (City of Haverhill v. George Brox, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Haverhill v. George Brox, Inc., 716 N.E.2d 138, 47 Mass. App. Ct. 717, 1999 Mass. App. LEXIS 1025 (Mass. Ct. App. 1999).

Opinion

Spina, J.

George Brox, Inc. (Brox), filed a third-party complaint against Gordon Construction Corp. (Gordon) seeking indemnification under the terms of a public works subcontract for payment made on a negligence claim. A Superior Court judge allowed Brox’s motion for summary judgment and denied Gordon’s cross motion for summary judgment. On appeal, Gordon challenges the judge’s rulings (1) that the subcontract became effective before the effective date of G. L. c. 149, [718]*718§ 29C, and that consequently the statute had no impact on the indemnification clause of the subcontract, and (2) that Maine law, which prohibits such indemnification clauses, does not apply. We affirm, but for reasons different than those relied on by the motion judge.

The material facts are not disputed.1 Brox was awarded a general contract by the Commonwealth’s Department of Public Works (DPW) on January 14, 1985, to resurface Route 125 in the city of Haverhill (city). Gordon, a Maine corporation authorized to do business in Massachusetts, submitted quotes to Brox for subcontracting work, and Brox responded favorably on March 4, 1985, by mailing to Gordon a subcontract and various other forms, including a subcontractor’s certification that Gordon would comply with certain antidiscrimination and affirmative action requirements. Gordon executed the subcontract in Maine on March 8, 1985, and mailed it back to Brox with the other completed forms. Section 19 of the subcontract stated “ [tjhis subcontract shall become effective upon approval of the subcontractor by” the DPW. On March 13, 1985, Brox sent a letter to the DPW requesting approval of Gordon as Brox’s subcontractor. On April 7, 1985, G. L. c. 149, § 29C, set forth in the margin,2 became effective. On June 5, 1985, the DPW approved Gordon as a subcontractor to Brox.

Brox began work on the Haverhill project on March 20, 1985. Gordon began its work under the subcontract on November 19, 1985. On November 20, a reserve police officer from the Haverhill police department was working a paid detail at Brox’s request.3 It was the officer’s job to provide traffic control in the construction area. The police officer was following two Gordon employees down the highway with his automobile when he struck and injured them. The two Gordon employees, who were residents of Maine, received workers’ compensation benefits from Gordon’s workers’ compensation insurer pursuant to the laws of Maine.

[719]*719The two employees filed personal injury actions against the police officer, the city of Haverhill, and Brox. The city settled the claims against it and then brought this action against Brox seeking indemnification under the terms of the general contract between the DPW and Brox. Brox, with contribution from Gordon, settled with the city. Brox then looked tp Gordon for indemnification of the amount it paid, based upon section 7 of the subcontract, which provided that Gordon, as subcontractor, would “indemnify and save harmless [Brox, as general contractor] from any and all claims . . . arising out of the performance of work hereunder.”

1. Central to this case is the meaning of the phrase “effective upon approval” appearing in section 19 of the subcontract. Gordon argues that section 19 created a condition precedent to the formation of the subcontract such that the subcontract did not come into existence until June 5, 1985, when the DPW approved Gordon as a subcontractor on the project. If Gordon is correct, then G. L. c. 149, § 29C, which became effective on April 7, 1985, would operate to nullify the indemnification clause of the subcontract. See Harnois v. Quannapowitt Dev., Inc., 35 Mass. App. Ct. 286 (1993). Brox contends that the subcontract came into existence on March 8, 1985, when it was executed by Gordon, and that section 19 created a condition precedent to the parties’ rights to immediate performance under the subcontract. The motion judge agreed that the subcontract was formed on March 8, 1985, but found that section 19 created a condition subsequent which, if unmet, would void the subcontract. In the view of the judge and Brox, the subcontract came into existence before § 29C became effective and thus escaped its reach. See Jones v. Vappi & Co., 28 Mass. App. Ct. 77, 81 (1989).

Contract conditions precedent generally are of two kinds. The first involves issues of offer and acceptance which precede and determine the formation of a contract. See Massachusetts Biographical Soc. v. Howard, 234 Mass. 483 (1920); Tilo Roofing Co. v. Pellerin, 331 Mass. 743 (1954). The second arises from the terms of a valid contract and defines an event which must occur before a right or obligation matures under the contract. See Sechrest v. Safiol, 383 Mass. 568, 571 (1981); Massachusetts Mun. Wholesale Elec. Co. v. Danvers, 411 Mass. 39, 45 (1991); Wood v. Roy Lapidus, Inc., 10 Mass. App. Ct. 761, 763 n.5 (1980). See also Corbin, Contracts § 628 (1960 & [720]*720Supp. 1999); 5 Williston, Contracts § 666A (3d ed. 1961 & Supp. 1999); Restatement (Second) of Contracts § 224 (1981). In contrast “[a] condition subsequent is a condition which relieves a party of the obligation of further performance” under a valid contract. Wood v. Roy Lapidus, Inc., 10 Mass. App. Ct. at 764 n.6.

Where the language of a contract is not ambiguous, the words will be given their plain meaning, Freelander v. G. & K. Realty Corp., 357 Mass. 512, 515-516 (1970), or their well-established meaning, Erhard v. F.W. Woolworth Co., 374 Mass. 352, 355 (1978). The phrase “effective upon approval” in section 19 is not without ambiguity. Gordon equates it with existence; Brox, with operation. Where the terms of an instrument are ambiguous, a court must determine meaning from the intent of the parties upon consideration of the words in question, the entire instrument, and surrounding circumstances. See Massachusetts Mun. Wholesale Elec. Co. v. Danvers, 411 Mass, at 45-46. “Justice, common sense and the probable intention of the parties are guides to construction of a written instrument.” Stop & Shop, Inc. v. Ganem, 347 Mass. 697, 701 (1964). “So far as reasonably practicable [a contract] should be given a construction which will make it a rational business instrument and will effectuate what appears to have been the intention of the parties.” Bray v. Hickman, 263 Mass. 409, 412 (1928).

The subcontract at issue has all the components of a valid contract: offer, acceptance, consideration, and terms setting forth the rights and obligations of the parties. It was executed under seal. The parties are content that the subcontract was a complete expression of their agreement and that no other terms were left to negotiate. The condition of the DPW approval was created by express provision of the subcontract, and, upon such condition being met, the rights and obligations of the parties as defined by the subcontract would spring forth without need for any further action by the parties. This could only occur if the subcontract was in existence at the time the condition was met. Contrast Massachusetts Biographical Soc. v. Howard, 234 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patrick Furnari v. John S. Holden, Third.
Massachusetts Appeals Court, 2024
Cp 200 State LLC v. Ciee, Inc.
Massachusetts Appeals Court, 2024
Covidien LP v. Esch
D. Massachusetts, 2019
Public Employee Retirement Administration Commission v. Bettencourt
47 N.E.3d 667 (Massachusetts Supreme Judicial Court, 2016)
Robert and Ardis James Foundation v. Meyers
25 N.E.3d 885 (Massachusetts Appeals Court, 2015)
Rachael's Boutique, Inc. v. Cabral
2013 Mass. App. Div. 115 (Mass. Dist. Ct., App. Div., 2013)
Zurich American Insurance v. Watts Regulator Co.
860 F. Supp. 2d 78 (D. Massachusetts, 2012)
JPMorgan Chase & Co. v. Casarano
963 N.E.2d 108 (Massachusetts Appeals Court, 2012)
Suffolk Construction Co. v. Illinois Union Insurance
951 N.E.2d 944 (Massachusetts Appeals Court, 2011)
ESN, LLC v. Cisco Systems, Inc.
685 F. Supp. 2d 631 (E.D. Texas, 2009)
Castricone v. Mical
909 N.E.2d 29 (Massachusetts Appeals Court, 2009)
Matthews v. Planning Board
892 N.E.2d 797 (Massachusetts Appeals Court, 2008)
Carr v. Entercom Boston, LLC
23 Mass. L. Rptr. 138 (Massachusetts Superior Court, 2007)
Bolt v. Merrimack Pharmaceut
Ninth Circuit, 2007

Cite This Page — Counsel Stack

Bluebook (online)
716 N.E.2d 138, 47 Mass. App. Ct. 717, 1999 Mass. App. LEXIS 1025, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-haverhill-v-george-brox-inc-massappct-1999.