Cheschi v. Boston Edison Co.

654 N.E.2d 48, 39 Mass. App. Ct. 133, 1995 Mass. App. LEXIS 542
CourtMassachusetts Appeals Court
DecidedAugust 21, 1995
DocketNo. 94-P-737
StatusPublished
Cited by23 cases

This text of 654 N.E.2d 48 (Cheschi v. Boston Edison Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cheschi v. Boston Edison Co., 654 N.E.2d 48, 39 Mass. App. Ct. 133, 1995 Mass. App. LEXIS 542 (Mass. Ct. App. 1995).

Opinion

Warner, C.J.

On May 18, 1984, Louis Cheschi, Jr., an ironworker employed by Bechtel Construction, Inc. (Bechtel), was injured while working on a construction project at the Plymouth Pilgrim I Nuclear Power Plant, owned by Boston Edison Company (Edison). As he walked along a catwalk inside a suppression chamber known as the “torus” section of the nuclear reactor, he tripped on a piece of angle iron and fell a considerable distance. Cheschi filed a negligence action against Edison in the Superior Court on July 9, 1985. Edison filed a third-party complaint against Bechtel1 on December 28, 1987, seeking indemnification under a provision of their contract for construction services. (Cheschi had filed two workers’ compensation claims against Bechtel; Bechtel was never named as a direct defendant.) Cheschi’s and Edison’s actions were tried together before a jury. Answering special questions, the jury found that Edison was not negligent. They found Bechtel fifty-eight percent negligent, Cheschi forty-two percent contributorily negligent, and Bechtel’s and Cheschi’s negligence to have proximately caused Cheschi’s injuries.

Edison moved for entry of judgment on its claim for indemnification, seeking its legal fees and costs. Following a hearing, the judge ordered Bechtel to pay Edison $82,989.90 in attorneys’ fees and costs, plus interest, from July 2, 1985.

Cheschi appeals from the judgment for Edison on his negligence claim, contending that the trial judge improperly refused to give his requested jury instruction on vicarious liability and ruled erroneously on several other matters during the jury trial. Bechtel appeals from the indemnification judgment on the ground that Edison failed promptly to notify Bechtel of Cheschi’s claim, as their contract required.

[135]*135 Cheschi’s appeal.

1. Jury instructions. Cheschi requested a jury instruction characterizing Edison and Bechtel as master and servant and imputing Bechtel’s negligence to Edison under an agency theory.2 Instead, the judge characterized Edison’s and Bechtel’s relationship as that of employer and independent contractor. He instructed that Edison could be held liable for injuries Cheschi incurred in the course of working for Bechtel only if Edison retained control over some part of the work and if it exercised that control negligently. The plaintiff renewed his request following the charge, referring to the instruction by number only. This request was insufficiently explicit to preserve the plaintiff’s objection. See Flood v. Southland Corp., 416 Mass. 62, 66-67 (1993) (“[A] post-charge objection to the failure to give an instruction, made simply by reference to the number of the requested charge, normally will not satisfy rule 51 unless the judge requests that counsel follow such a procedure and assures counsel that the objection is understood”); Mass.R.Civ.P. 51(b), 365 Mass. 816 (1974). In any event, the judge’s instructions accurately reflected the theory of recovery raised by the evidence, as summarized below.

The contract governing Bechtel’s construction services, the Maintenance Services Agreement, states explicitly that Bechtel is an independent contractor. It authorizes Bechtel to hire subcontractors, to subcontract services to a particular contractor without Edison’s prior approval, and to exercise control over its employees. It requires Bechtel to prepare a manual describing its organization, division of responsibility and administration, and holds Bechtel to performance standards of “recognized professional engineering and construction firms.” The agreement provides that Edison will issue [136]*136Bechtel work orders specifying the “scope” of the services, a performance schedule, and the estimated cost, and that Edison will have general oversight and give “overall direction.”3

A section of the contract entitled “Safety Procedures for Contractors and Subcontractors Working on Boston Edison Facilities” outlines Edison’s safety requirements. It specifies that each work project will be subject to Edison’s instructions and prior approval concerning safety issues and that uncorrected safety violations could result in Edison’s shutting down a contractor’s work. Contractors are given responsibility for enforcing the safety requirements.

Uncontroverted trial testimony attested to Bechtel’s control of the manner in which it conducted its work. Edison’s Construction Management Group, charged with ensuring that work under the contract was completed, did not include Bechtel personnel in its daily informational meetings with Edison personnel. A member of that group could not remember ever overseeing Bechtel’s work in the torus.

Testimony was elicited regarding both Bechtel’s and Edison’s responsibilities for safety procedures. Bechtel had a comprehensive safety program for its work in the torus, produced a safety manual, had safety personnel on site, and held weekly safety meetings. Edison’s safety inspector did not inspect the torus area because no Edison people worked there. Radiation safety procedures were under Edison’s control. Edison gave seminars on the subject, provided and coordinated the wearing of radiation protective clothing, and monitored the plant’s radiation levels.4

[137]*137The evidence showed that Bechtel controlled the details of its construction work, that Edison maintained general oversight to be sure that the work was done, and that both Bechtel and Edison had responsibility for safety procedures. The judge correctly instructed the jury that Bechtel was an independent contractor. See Corsetti v. Stone Co., 396 Mass. 1, 5-9 (1985), and cases cited at 9. See also Khoury v. Edison Elec. Illuminating Co., 265 Mass. 236, 238-239 (1928); Chase v. Independent Practice Assn., 31 Mass. App. Ct. 661, 665 (1991).

He further instructed the jury under the “retained control” theory set forth in the Restatement (Second) of Torts § 414 (1965), and adopted by the Supreme Judicial Court in Corsetti v. Stone Co., 396 Mass, at 9-11. See also McNamara v. Massachusetts Port Authy., 30 Mass. App. Ct. 716, 718-720 (1991). Section 414 provides: “One who entrusts work to an independent contractor, but who retains the control of any part of the work, is subject to liability for physical harm to others for whose safety the employer owes a duty to exercise reasonable care, which is caused by his failure to exercise his control with reasonable care.”5

The facts of this case, like those in Corsetti v. Stone Co., 396 Mass, at 5-12, raised a jury question as to whether Edison’s involvement in safety procedures resulted in its retaining control over certain aspects of the work and, if so, [138]*138whether such control was exercised with reasonable care. Compare Foley v. Rust Intl., 901 F.2d 183, 184-185 (1st Cir. 1990), discussing Corsetti and related cases. The judge’s instructions were correct.

2. Other issues, a. Cheschi makes a confused argument that Edison was a general contractor, that this designation is material to Edison’s liability for Bechtel’s negligence, and that Cheschi was improperly prevented from making this case.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CARE AND PROTECTION OF DORETTA & others.
101 Mass. App. Ct. 584 (Massachusetts Appeals Court, 2022)
Rodrigues v. Tribeca Builders Corp.
32 Mass. L. Rptr. 535 (Massachusetts Superior Court, 2015)
Carroca v. Welsh
2011 Mass. App. Div. 290 (Mass. Dist. Ct., App. Div., 2011)
AsymmetRx, Inc. v. Biocare Medical LLC
578 F. Supp. 2d 333 (D. Massachusetts, 2008)
Bayliss v. Hannan Construction Corp.
22 Mass. L. Rptr. 188 (Massachusetts Superior Court, 2007)
DSF Investors, LLC v. Lyme Timber Co.
19 Mass. L. Rptr. 411 (Massachusetts Superior Court, 2004)
Commercial Union Insurance v. Gillette Co.
17 Mass. L. Rptr. 726 (Massachusetts Superior Court, 2004)
American Fiber & Finishing, Inc. v. Tyco Healthcare Group, LP
273 F. Supp. 2d 155 (D. Massachusetts, 2003)
Massachusetts Port Authority v. Johnson Controls, Inc.
766 N.E.2d 542 (Massachusetts Appeals Court, 2002)
Chiao-Yun Ku v. Town of Framingham
762 N.E.2d 855 (Massachusetts Appeals Court, 2002)
Cambridge Housing Authority v. Wedge
2000 Mass. App. Div. 235 (Mass. Dist. Ct., App. Div., 2000)
Toledo v. Van Waters & Rogers, Inc.
92 F. Supp. 2d 44 (D. Rhode Island, 2000)
Roy v. Roy
715 N.E.2d 70 (Massachusetts Appeals Court, 1999)
Davis v. Dawson, Inc.
15 F. Supp. 2d 64 (D. Massachusetts, 1998)
Tammaro v. Haliotis
1998 Mass. App. Div. 82 (Mass. Dist. Ct., App. Div., 1998)
Gibson v. Tweed
7 Mass. L. Rptr. 267 (Massachusetts Superior Court, 1997)
Zapata v. Bradley
6 Mass. L. Rptr. 576 (Massachusetts Superior Court, 1997)
FDIC v. Insurance Company
First Circuit, 1997

Cite This Page — Counsel Stack

Bluebook (online)
654 N.E.2d 48, 39 Mass. App. Ct. 133, 1995 Mass. App. LEXIS 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cheschi-v-boston-edison-co-massappct-1995.