J.F. White Contracting Company v. Commonwealth of Massachusetts, Acting by and Through Its Department of Transportation, Rail and Transit Division

CourtMassachusetts Superior Court
DecidedMarch 9, 2026
Docket2184CV01172-BLS2
StatusPublished

This text of J.F. White Contracting Company v. Commonwealth of Massachusetts, Acting by and Through Its Department of Transportation, Rail and Transit Division (J.F. White Contracting Company v. Commonwealth of Massachusetts, Acting by and Through Its Department of Transportation, Rail and Transit Division) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.F. White Contracting Company v. Commonwealth of Massachusetts, Acting by and Through Its Department of Transportation, Rail and Transit Division, (Mass. Ct. App. 2026).

Opinion

J.F. White Contracting Company entered into a public construction contract to replace, remove, or clean culverts running beneath active commercial rail lines in preparation for South Coast Rail commuter train traffic. The contract with the Massachusetts Department of Transportation (“MassDOT”) had an amended maximum obligation amount of $20.3 million. After essentially completing its work, J.F. White sought an additional $11.5 million for extra costs it claims to have incurred due to unanticipated site conditions and allegedly defective contract documents. It then brought suit asserting various claims for breach of contract or, in the alternative, for recovery on a quantum meruit (or unjust enrichment) theory.

The Court will allow MassDOT’s motion for summary judgment on all claims. MassDOT is entitled to judgment in its favor on the differing site conditions claims as a matter of law because the record establishes that J.F. White failed to provide timely notice, as required by the plain language of the written contract, that it was requesting an equitable adjustment as to any of the culverts. MassDOT is similarly entitled to judgment in its favor on the defective contract documents claims because it is undisputed that J.F. White failed to promptly report alleged errors in the contract specifications and did not seek a contract change order before doing the work.

“Summary judgment is appropriate” in this case because “no material facts are in dispute and the moving party,” MassDOT, “is entitled to judgment as a matter of law.” Tody’s Service, Inc. v. Libert Mut. Ins. Co., 496 Mass. 197, 199 (2025). “The purpose of summary judgment is to decide cases where there are no issues of material fact,” like this one, and to do so “without the needless expense and delay of a trial followed by a directed verdict.” Correllas v. Viveiros, 410 Mass. 314, 316 (1991).

                                                            -1-

1. Differing Site Conditions Claims. J.F. White claims that, under G.L. c. 30, § 39N, and related contract provisions, it is entitled to an equitable adjustment in the contract price to cover extra costs incurred because conditions at culvert work sites differed substantially or materially from those shown on MassDOT’s plans or in other contract documents.

But the record establishes that J.F. White cannot prove that it provided timely advance notice that it was seeking such an equitable adjustment, which is a contractual condition precedent to obtaining such extra payments.

Since J.F. White cannot prove an essential element of these claims, MassDOT is entitled to summary judgment on the breach of contract claim in Count Three of the complaint, the claim for breach of the implied covenant of good faith and fair dealing in Count Four, and the quantum meruit claim in Count Five. See Kourouvacilis v. General Motors Corp., 410 Mass. 706, 715 (1991) (“If the nonmoving party cannot muster sufficient evidence to make out its claim, a trial would be useless and the moving party is entitled to summary judgment as a matter of law.”) (quoting Celotex Corp. v. Catret, 477 U.S. 317, 328 (1986) [White, J., concurring]).

Whether J.F. White would have been entitled to recoup extra costs if it had provided timely written requests for equitable adjustments is thus irrelevant. “A nonmoving party’s failure to establish an essential element of her claim ‘renders all other facts immaterial’ and mandates summary judgment in favor of the moving party.” Roman v. Trustees of Tufts College, 461 Mass. 707, 711 (2012), quoting Kourouvacilis, supra, at 711.

1.1. No Contractual Right to an Equitable Adjustment. J.F. White failed to follow the required procedures for an equitable adjustment in the contract price due to differing site conditions. It is therefore not entitled to obtain any extra compensation on the ground that it encountered differing site conditions. See Glynn v. City of Gloucester, 21 Mass. App. Ct. 390, 396 (1986) (“Glynn II”); D. Federico Co., Inc. v. Commonwealth, 11 Mass. App. Ct. 248, 252–253 (1981); Skopek Bros., Inc. v. Webster Housing Auth.,  11 Mass. App. Ct. 947 (1981) (rescript). As the Appeals Court has explained:

On a public construction contract, if actions or requirements of the public agency necessitate changes in the work as it progresses, thereby causing the contractor to perform extra work or incur added expense, ... the contractor must follow the procedures spelled out in the contract

                                                            -2-

... to adjust the price before unilaterally accruing expenses to be pursued later on breach of contract or quantum meruit theories.

Glynn II, supra, at 394–395, quoting Glynn v. City of Gloucester, 9 Mass. App. Ct. 454, 460 (1980).

Since J.F. White failed to follow the procedures mandated by contract and by § 39N, any additional costs due to differing site conditions “were incurred unilaterally at its own expense” and J.F. White has no right to recover them from MassDOT. See Glynn II, supra, at 398. MassDOT is therefore entitled to summary judgment on Count Three.

1.1.1. Proper Notice Was a Condition Precedent. As required by G.L. c. 30, § 39N, the parties’ contract provides that if J.F. White discovered “during the progress of the work” that “actual subsurface or latent physical conditions encountered at the site differ substantially or material from those shown on the plans or indicated in the contract documents,” then it could “request an equitable adjustment in the contract price.” See General Conditions § 8.5.1.

Section 39N provides that the contract awarding authority “may adopt reasonable rules or regulations … concerning the filing, investigation, and settlement” of claims for an equitable adjustment in price due to differing site conditions. MassDOT did so. The contract required J.F. White to provide notice that it was seeking such an equitable adjustment due to differing site conditions “promptly, and before such conditions are disturbed.” Id. § 8.5.3.

J.F. White was required to make such a request “in writing” and do so “as soon as possible after such conditions are discovered.” Id. § 8.5.1. That would provide MassDOT with the opportunity to “make an investigation of such physical conditions” and make an appropriate equitable adjustment in the contract price if the actual conditions differed substantially “and are of such a nature as to cause an increase or decrease in the cost of performance.

Providing notice that meets these conditions was a contractual condition precedent to J.F. White obtaining any equitable adjustment. The contract states that claims for additional compensation due to differing site conditions “shall not be allowed unless [J.F. White] has first given the notice required” by contract, as discussed above. Id. § 8.5.5.

If contracting parties intend “that the giving of notice was a condition precedent” to obtaining some additional payment, they may express that intent by saying that payment may be obtained only “on the condition that,”

                                                            -3-

“provided that,” or “if” the required notice is given, or by using similarly explicit language to express that intent. Massachusetts Port Auth. v. Johnson Controls, Inc., 54 Mass. App. Ct. 541, 544 (2002); see also Massachusetts Mun. Wholesale Elec. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Druker v. Roland Wm. Jutras Associates, Inc.
348 N.E.2d 763 (Massachusetts Supreme Judicial Court, 1976)
Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
Magliozzi v. P & T CONTAINER SERV. CO.
614 N.E.2d 690 (Massachusetts Appeals Court, 1993)
D. Federico Co., Inc. v. Commonwealth
415 N.E.2d 855 (Massachusetts Appeals Court, 1981)
Chiappisi v. Granger Contracting Co. Inc.
223 N.E.2d 924 (Massachusetts Supreme Judicial Court, 1967)
Correllas v. Viveiros
572 N.E.2d 7 (Massachusetts Supreme Judicial Court, 1991)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Vasys v. Metropolitan District Commission
438 N.E.2d 836 (Massachusetts Supreme Judicial Court, 1982)
Alpert v. Commonwealth
258 N.E.2d 755 (Massachusetts Supreme Judicial Court, 1970)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Board of Registration in Medicine v. Doe
933 N.E.2d 67 (Massachusetts Supreme Judicial Court, 2010)
Weiler v. PortfolioScope, Inc.
469 Mass. 75 (Massachusetts Supreme Judicial Court, 2014)
Coghlin Electrical Contractors, Inc. v. Gilbane Building Co.
472 Mass. 549 (Massachusetts Supreme Judicial Court, 2015)
Columbia Pontiac Co. v. Board of Assessors
481 N.E.2d 440 (Massachusetts Supreme Judicial Court, 1985)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Ayash v. Dana-Farber Cancer Institute
822 N.E.2d 667 (Massachusetts Supreme Judicial Court, 2005)
Carey v. New England Organ Bank
446 Mass. 270 (Massachusetts Supreme Judicial Court, 2006)
Curtis v. Herb Chambers I-95, Inc.
458 Mass. 674 (Massachusetts Supreme Judicial Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
J.F. White Contracting Company v. Commonwealth of Massachusetts, Acting by and Through Its Department of Transportation, Rail and Transit Division, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jf-white-contracting-company-v-commonwealth-of-massachusetts-acting-by-masssuperct-2026.