Peabody N.E., Inc. v. Town of Marshfield

6 Mass. L. Rptr. 473
CourtMassachusetts Superior Court
DecidedNovember 19, 1996
DocketNo. 9102514
StatusPublished

This text of 6 Mass. L. Rptr. 473 (Peabody N.E., Inc. v. Town of Marshfield) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peabody N.E., Inc. v. Town of Marshfield, 6 Mass. L. Rptr. 473 (Mass. Ct. App. 1996).

Opinion

Chin, J.

This matter arises from a contract entered into by the two parties under which plaintiff Peabody N.E., Inc. (“Peabody”) was to construct a grit, septage, and grease handling facility for the defendant Town of Marshfield (“Marshfield”). Peabody brought suit seeking to recover monies it claims are due and owing to it for work done on the project, and Marshfield challenged this assertion and filed a counterclaim. The Court referred the case to a Master pursuant to Mass.R.Civ.P. 53(h)(1). Upon receiving the Master’s Final Report finding that Peabody materially breached the contract, the Court recommitted the case to the Master for further consideration of the issue of quantum meruit. [4 Mass. L. Rptr. 413.)

Both parties have filed Objections to the Master’s Supplemental Final Report and Motions to Modify the Master’s Supplemental Report and Motions to Enter Judgment. Most recently, Peabody moved this court to reconsider its Order dated July 31, 1995, recommitting the matter to the Master.

For the following reasons, Peabody’s Motion for Reconsideration is DENIED, and Judgment is to enter on the Master’s Report as Modified by this opinion.

FACTUAL BACKGROUND

In 1987, the Massachusetts Department of Environmental Quality Engineering (“DEQE”) issued an administrative order directing Marshfield to close its landfill septage lagoons by December 16, 1990 because the lagoons posed a threat to Marshfield’s groundwater supplies. Following the issuance of this order, Marshfield hired the engineering firm of Metcalf & Eddy (“M&E”) to prepare plans and designs for the “Grit, Septage and Grease Handling Facility” of the Marshfield Wastewater Treatment Plant (“Project”), as well as to serve as engineers during its construction.

[474]*474On or about October 23, 1989, Marshfield entered into a contract with Peabody whereby Peabody was to serve as general contractor for the construction of the project. The contract required Peabody to complete its work in strict accordance with the drawings and specifications and other contract documents, in conformity with the directions of M&E, and to the satisfaction of M&E. Peabody was to complete its work by January 27, 1991, and the contract specifically stated that time was of the essence.

For the period ending August 30, 1991, M&E certified the project as 99.7% complete by measuring the dollar value of completed work against the original contract price. In October of 1991, Peabody notified Marshfield that the project was substantially complete. Marshfield then had M&E recalculate the percentage by using the contract price as adjusted by change orders, and as a result M&E did not declare substantial completion until April 23, 1992.

Peabody filed this action seeking to recover monies it claims are due and owing to it for work on the project. Marshfield brought a counterclaim seeking to recover damages for Peabody’s alleged breaches of contract. By Order dated July 15, 1994, this Court (O’Brien, J.), referred this matter to a Master for Findings of Fact and Recommended Conclusions of Law. The Master heard some fourteen days of testimony and, pursuant to Mass.R.Civ.P. 53(g)(2), submitted to the court a Master’s Final Report containing 449 Findings of Fact with supporting citations and 47 Recommended Conclusions of Law.

This Court (Chin, J.) was provided with a complete transcript of the proceedings before the Master and all the exhibits presented during the hearing. This Court concurred with the Master that Peabody breached a material term of the Contract when it failed to complete work on the Project by January 27, 1991, and this Court held that since a contractor cannot recover on the contract itself without showing complete and strict performance of all its terms, Andre v. Maguire, 305 Mass. 515, 516 (1940), Peabody therefore could not recover on the contract. However, this Court held that “[a] contractor on a building project may collect quantum meruit ‘if he can prove both substantial performance of the contract and an endeavor on his part in good faith to perform fully . . .’ Andre, supra, at 516,” and recommitted the case to the Master for further findings and modifications relative to quantum meruit, including but not limited to whether Peabody’s breach was excused and whether Peabody had a good faith intention to complete the project. [Peabody N.E., Inc. v. Marshfield, 4 Mass. L. Rptr. No. 19, 413 (January 1, 1996).]

The Master’s Supplemental Findings on the quantum meruit issue include, in part, the following: Peabody substantially completed the contract no later than August 30, 1991; Peabody endeavored in good faith to perform fully the contract; Peabody had a good faith intention to complete fully the project; Peabody refused in good faith to perform extra work. Under Supplemental Recommended Conclusions of Law, the Master held that Peabody could not recover more than the contract price under quantum meruit, and that the measure of Peabody’s recovery under quantum meruit was the total adjusted contract price less Marshfield’s liquidated damages, other applicable deductions, and total payments.

The Master found that the fair and reasonable value of material and labor supplied by Peabody was $3,469,498.00. Marshfield paid to Peabody the amount of $3,198,806.00. Thus the fair and reasonable value of material and labor supplied by Peabody and not paid for by Marshfield was $270,692.00. The Master concluded that since Peabody could not recover more than the total adjusted contract price, the maximum amount that Peabody could recover under quantum meruit was $270,692.00.

The Master then offset Peabody’s recovery under quantum meruit by certain applicable deductions of $4000 and by Marshfield’s liquidated damages of $400 per day for 215 days, or $86,000. The Master found the net amount due and owing to Peabody to be $ 180,692.00, plus interest at the statutory rate of 12% pursuant to G.L.c. 231, §6C, commencing as of January 1, 1992.

The Master left two issues for the Court. First, in the event this Court determines that the law of the Commonwealth does not allow an offset of liquidated damages under a quantum meruit recovery when such damages are incurred as a result of a delay for which the contractor is excused, then such quantum meruit award in the instant case shall be increased by the $86,000 offset. Second, in the event that this Court determines that the law of the Commonwealth provides that the limitation in a quantum meruit damage award includes overhead costs incurred by the contractor where the owner improperly fails to declare the project substantially complete, then such quantum meruit award in the instant case shall be increased by $388,644, representing Peabody’s field and home office overhead costs after August 30, 1991 through April 23, 1992 (see Master’s Report Findings 436 through 440).

DISCUSSION

I. Standard of Review

Pursuant to Mass.R.Civ.P. 53(h)(1), where a matter is referred to a master to be heard without a jury, “the court shall accept the master’s subsidiary findings of fact unless they are clearly erroneous, mutually inconsistent, unwarranted by the evidence before the master as a matter of law, or are otherwise tainted by error of law." “A finding is ‘clearly erroneous’when, although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” Pollock v. Marshall, 391 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
William F. Klingensmith, Inc. v. United States
731 F.2d 805 (Federal Circuit, 1984)
Pollock v. Marshall
462 N.E.2d 312 (Massachusetts Supreme Judicial Court, 1984)
J. A. Sullivan Corp. v. Commonwealth
494 N.E.2d 374 (Massachusetts Supreme Judicial Court, 1986)
Kass v. Todd
284 N.E.2d 590 (Massachusetts Supreme Judicial Court, 1972)
Libman v. Zuckerman
599 N.E.2d 642 (Massachusetts Appeals Court, 1992)
Burke v. Coyne
74 N.E. 942 (Massachusetts Supreme Judicial Court, 1905)
Hooper v. Cuneo
227 Mass. 37 (Massachusetts Supreme Judicial Court, 1917)
Andre v. Maguire
26 N.E.2d 347 (Massachusetts Supreme Judicial Court, 1940)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Peabody N.E., Inc. v. Town of Marshfield
4 Mass. L. Rptr. 413 (Massachusetts Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
6 Mass. L. Rptr. 473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peabody-ne-inc-v-town-of-marshfield-masssuperct-1996.