G. Conway, Inc. v. Tocci Building Corp.

18 Mass. L. Rptr. 565
CourtMassachusetts Superior Court
DecidedDecember 22, 2004
DocketNo. 012261
StatusPublished

This text of 18 Mass. L. Rptr. 565 (G. Conway, Inc. v. Tocci Building Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. Conway, Inc. v. Tocci Building Corp., 18 Mass. L. Rptr. 565 (Mass. Ct. App. 2004).

Opinion

Bohn, J.

INTRODUCTION

The plaintiff/defendant in counterclaim, G. Conway, Inc. (“Conway”), a subcontractor on a project to build a retaining wall as part of the construction of a hotel in Burlington, Massachusetts (the “Project”), sued the defendant/third-party plaintiff, Tocci Building Corporation (“Tocci”) for enforcement of a mechanic’s lien, breach of contract and quantum meruit for money allegedly owed to Conway for work it performed on the Project.

Tocci answered Conway’s complaint, and filed a third-party complaint against Jaworski Geotech, Inc. (“JGI”), the engineering subcontractor on the project, and Keystone Masomy Contractor, Inc. (“Keystone”), the masonry subcontractor. Tocci’s third-party complaint against JGI alleges professional negligence, breach of contract, breach of express warranty, contribution and indemnification arising out of the collapse of the retaining wall.

In response to Tocci’s third-party complaint, JGI filed a counterclaim against Tocci for breach of contract and quantum meruit for unpaid fees that Tocci allegedly owes to JGI.

The matter is now before the court on the motion of Tocci for partial summary judgment as to the fourteenth affirmative defense asserted by JGI in its answer and counterclaim to the third-party complaint and on the motion of JGI for partial summary judgment and for entry of separate and final judgment on its counterclaim against Tocci. The fourteenth affirmative defense to the third-parly complaint contains JGI’s argument that Tocci’s claims are subject to a purported contractual limitation of liability of fifty thousand dollars, or JGI’s total fee on the Project, whichever is greater. Tocci’s position in this regard is that (1) in providing a certificate of insurance showing coverage in the amount of two million dollars, JGI agreed to be liable for up to two million dollars in professional liability; (2) the purported fifty-thousand-dollar limitation of liability provision did not become a part of the Geotechnical Services Contract and, therefore, does not limit JGI’s liability; and (3) JGI’s fourteenth affirmative defense should be rejected on the grounds of contract modification, estoppel and/or waiver.

The motion of JGI for partial summaiy judgment and for entry of separate and final judgment seeks dismissal of the breach of contract and breach of warranty claims asserted against it by Tocci as well as an award in quantum meruit for approximately fifty thousand dollars in unpaid fees that Tocci allegedly owes to JGI. In support of its motion for partial summaiy judgment and for entry of separate and final judgment, JGI argues that (1) JGI’s liability, if any, is limited by the terms of the JGI-Tocci contract; (2) Tocci’s breach of contract and breach of warranty claims fail as a matter of law because they are duplicative of its negligence claim; and (3) JGI is entitled to recover the outstanding fees owed to it on its counterclaim. 1

After a hearing on November 16, 2004, and for the reasons stated below, the motion of Tocci as third-party plaintiff for partial summary judgment will be DENIED; and, the motions of JGI as third-party defendant for partial summaiy judgment and for entry of separate and final judgment will both be DENIED in that there appear to be genuine issues of material fact concerning JGI’s liability to Tocci that must be resolved at trial. Furthermore, JGI’s fourteenth affirmative defense is valid and appropriate, and the court will, sua sponte, order that the contract between Tocci and JGI limits the amount of JGI’s liability, if any, to $50,000.00 or to the total fee for services rendered by JGI on the project, whichever is greater. For that reason, Tocci’s request to strike JGI’s fourteenth affirmative defense will be denied.

BACKGROUND

In evaluating a motion for summary judgment, this Court relies on facts not in dispute as well as disputed facts viewed in the light most favorable to the nonmoving party. Beal v. Board of Selectmen ofHingham, 419 Mass. 535, 539 (1995).

This dispute arises out of the design and construction of a boulder retaining wall (the “Wall Project”) as part of the Candlewood Hotel construction project in Burlington, Massachusetts (the “Hotel Project”). Tocci was the construction manager for the Hotel Project. In that capacity, Tocci retained JGI as the Project’s geotechnical engineer.

On February 2, 1998, JGI sent a letter agreement to Tocci, which proposed that JGI complete a geotechnical investigation and hydrogeologic assessment for the Hotel Project (the “Contract”). The Contract set the total estimated budget at nine thousand [566]*566seven hundred and fifty dollars. Furthermore, the Contract referenced and attached certain Terms and Conditions that contained a “Limitation of Liability” provision (the “Provision”), which states:

CLIENT agrees to limit JGI’s liability to CLIENT and all third parties arising from JGI’s professional acts, errors or omissions, such that the total aggregate liability of JGI to all those named shall not exceed $50,000 or JGI’s total fee for the services rendered on this project, whichever is greater. If CLIENT wishes to discuss higher limits and changes involved, he should speak with JGI. JGI-Tocci Contract ¶15.0

On March 17, 1998, without making any changes to the Provision, Tocci executed the Contract. Shortly after execution of the Contract, Tocci requested that JGI submit a certifícate of insurance. On or about May 29, 1998, JGI submitted the certificate of insurance evidencing professional liability insurance coverage in the amount of two million dollars.

Tocci and JGI executed six change orders to the Contract that resulted in an adjusted Contract price of $46,594.46. Neither party made any changes to the Contract Provision referred to above.

On June 6, 2000, the Hotel Project site experienced an intense rainstorm and the site received approximately 4.5 inches of rainfall in an eight-hour period. Later that evening, as a result of the force and volume of water flowing into the wall and the failure of a catch basin, a section of the retaining wall collapsed. As a result of the collapse, JGI provided additional engineering services on the Hotel Project. On September 13,2001, JGI submitted a statement to Tocci for these additional engineering services totaling $49,576.31.

DISCUSSION

Summary judgment shall be granted where there are no genuine issues as to any material fact and where the moving party is entitled to judgment as a matter of law. Mass.RCiv.P. 56(c); Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976).

The moving party bears the burden of affirmatively demonstrating the absence of a triable issue, and that the summary judgment record entitles the moving parly to judgment as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). The moving party may satisfy this burden either by submitting affirmative evidence that negates an essential element of the opposing party’s case or by demonstrating that the opposing party has no reasonable expectation of proving an essential element of his case at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Freelander v. G. & K. REALTY CORP.
258 N.E.2d 786 (Massachusetts Supreme Judicial Court, 1970)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Urban Investment & Development Co. v. Turner Construction Co.
616 N.E.2d 829 (Massachusetts Appeals Court, 1993)
Beal v. Board of Selectmen
646 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
18 Mass. L. Rptr. 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-conway-inc-v-tocci-building-corp-masssuperct-2004.