Garrity v. Conservation Commission

971 N.E.2d 748, 462 Mass. 779, 2012 WL 2866131, 2012 Mass. LEXIS 660
CourtMassachusetts Supreme Judicial Court
DecidedJuly 16, 2012
StatusPublished
Cited by19 cases

This text of 971 N.E.2d 748 (Garrity v. Conservation Commission) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garrity v. Conservation Commission, 971 N.E.2d 748, 462 Mass. 779, 2012 WL 2866131, 2012 Mass. LEXIS 660 (Mass. 2012).

Opinion

Botsford, J.

The Wetlands Protection Act, G. L. c. 131, § 40 (act), requires a conservation commission to issue a decision on a requested order of conditions within twenty-one days after it holds a public hearing on the applicant’s notice of intent to perform work covered by the act. A question raised in this case is whether this deadline may be waived, and if so, the permissible contours of such a waiver.1 We conclude that an applicant seeking an order of conditions may waive the statutory restriction on the time available to the conservation commission to render its decision, but any waiver must be voluntary in fact, its duration must be defined and reasonable in length, and notice of the waiver’s duration must be a matter of public record, available to all interested persons.

1. Background. The plaintiff, Michael Garrity, owns oceanfront property in the town of Hingham (town). In March, 2009, he filed a notice of intent (NOI or application) with the defendant, the conservation commission of Hingham (commission), pursuant to the act and the town’s wetlands protection bylaw. The NOI requested an order of conditions allowing the construction of a pile-supported pier that would extend approximately 175 feet from the mean high water line in front of Garrity’s house, a pile-held floating dock, and a land-based platform or deck from which the pier would extend.2

The commission stamped Garrity’s NOI submission documents as received on March 9, 2009, and scheduled a public hearing on it for March 23, fourteen days later. The act directs that the public hearing be held within twenty-one days of a conservation commission’s receipt of a completed NOI, but Garrity’s representative requested a continuance of the hearing to April 6 (twenty-eight days after the submission date of March [781]*7819), to allow time for the completion of a peer review assessment of the proposed work that the commission had requested.3 The public hearing was held on April 6, and Garrity’s representative presented the project to the commission. After hearing from the town’s conservation officer and comments of several abut-ters, and considering several other items, the commission adjourned the public hearing.

The commission met again on April 27, 2009, twenty-one days after April 6. The members of the commission voted unanimously to deny Garrity’s requested order of conditions. On April 28, twenty-two days after the public hearing closed, a written order of denial was mailed to Garrity; the order stated that the denial was based on the town’s wetlands bylaw. In particular, the commission found that the work proposed could not be conditioned to meet the bylaw’s performance standards designed to protect specific interests, including fisheries, storm damage prevention, pollution prevention, shellfish protection, recreation, and aesthetics.

Garrity’s appeal to the Department of Environmental Protection (department) was received two days later, on April 30, 2009. In his letter of appeal, Garrity claimed that the commission had failed to act within the twenty-one day time period mandated by the act. On July 30, based on the commission’s failure to act within twenty-one days, the department issued a superseding order of conditions that permitted Garrity to construct a landing platform and access stairs with dimensions of eight by eighteen feet; a fixed pier with dimensions of four by 132 feet; a “T-Head” at the end of the pier with dimensions of ten by twelve feet; a ramp of four by forty feet; and a floating dock of ten by twelve feet.4

Before the department issued the superseding order, the com[782]*782mission issued an enforcement order to Garrity dated June 22, 2009, based on observations its members and staff made of certain structures that had been constructed on Garrity’s property.5 The enforcement order charged Garrity with four violations of the act: the construction and installation of (1) a wide stairway, (2) large deck, and (3) granite steps within a protected coastal bank without any order of conditions; and (4) the placement in and crushing of intertidal saltmarsh vegetation with stepping stones, similarly without an order of conditions. The enforcement order required Garrity to “cease and desist from any activity affecting the [b]uffer [z]one and/or resource areas.” It also notified Garrity that he must submit a notice of intent at least ten days prior to the commission’s scheduled meeting on August 10, 2009, to begin rectifying the violations.

Garrity commenced this action in the nature of certiorari on June 24, 2009, in the Superior Court, before receiving the department’s superseding order of conditions; he amended the complaint after the department’s superseding order was issued. The commission filed a copy of the record of the proceedings before it as its answer on November 17. Thereafter, Garrity and the commission filed cross motions for judgment on the pleadings pursuant to Mass. R. Civ. P. 12 (c), 365 Mass. 754 (1974). The commission argued that Garrity had waived the twenty-one day deadline for issuance of a decision on Garrity’s NOI after the public hearing closed, and therefore its denial of the NOI should govern. A Superior Court judge heard the motions and issued a decision on December 13, 2010. He concluded that Garrity’s purported waiver of the twenty-one day requirement for the commission’s issuance of its decision was ineffective, the decision was therefore not timely because it was not mailed within twenty-one days of the public hearing, and the superseding order of conditions issued by the department applied in its place. With respect to the commission’s enforcement order, [783]*783which Garrity separately challenged in his complaint, the judge concluded that the record contained insufficient evidence to support the order, and reversed it. The commission filed a timely appeal, and we transferred the case from the Appeals Court on our own motion.

2. Discussion. The commission argues that the judge erred in both ruling that Garrity’s waiver of the act’s twenty-one day limitation for issuance of its decision was invalid and concluding that the commission’s separate enforcement order lacked evidentiary support. We consider the two points separately.

a. Waiver. Under the act, no person may “remove, fill, dredge or alter” wetlands and other types of property described in the act that border bodies of water without applying for and receiving an order of conditions from the local conservation commission in the first instance. G. L. c. 131, § 40, first par. The act sets out in some detail the application process for an order of conditions, the review process to be followed by a conservation commission, the time frames in which the conservation commission must act, and the consequences of a failure to act in a timely manner. Of specific relevance here is that the act directs a conservation commission to hold a public hearing on a proposed project within twenty-one days of the commission’s receipt of an applicant’s NOI concerning the project, id., seventeenth par., and further mandates that the conservation commission issue a written order on the proposed project within twenty-one days of the public hearing. Id., eighteenth par. If the commission fails to do so, the applicant (as well as any other interested party described in the act) may request from the department a superseding order of conditions.6 Id., nineteenth par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MARIO NICOSIA & Another v. BURN, LLC, & Others
Massachusetts Supreme Judicial Court, 2025
Carver v. Commissioner of Correction
Massachusetts Supreme Judicial Court, 2023
Brown v. Sav. Bank Life Ins. Co. of Mass.
107 N.E.3d 1163 (Massachusetts Appeals Court, 2018)
Craig v. Conservation Comm'n of Mattapoisett
103 N.E.3d 1237 (Massachusetts Appeals Court, 2018)
Nelson v. Conservation Comm'n of Wayland
94 N.E.3d 436 (Massachusetts Appeals Court, 2017)
Service Employees International Union, Local 509 v. Auditor of the Commonwealth
64 N.E.3d 257 (Massachusetts Supreme Judicial Court, 2016)
MacLaurin v. City of Holyoke
475 Mass. 231 (Massachusetts Supreme Judicial Court, 2016)
Frawley v. Police Commissioner of Cambridge
46 N.E.3d 504 (Massachusetts Supreme Judicial Court, 2016)
Parkview Electronics Trust, LLC v. Conservation Commission of Winchester
43 N.E.3d 335 (Massachusetts Appeals Court, 2016)
Downey v. Chutehall Construction Co., Ltd.
42 N.E.3d 1194 (Massachusetts Appeals Court, 2016)
Figgs v. Boston Housing Authority
14 N.E.3d 229 (Massachusetts Supreme Judicial Court, 2014)
Lopez v. Commonwealth
463 Mass. 696 (Massachusetts Supreme Judicial Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
971 N.E.2d 748, 462 Mass. 779, 2012 WL 2866131, 2012 Mass. LEXIS 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garrity-v-conservation-commission-mass-2012.