CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & Others

CourtMassachusetts Superior Court
DecidedDecember 30, 2020
DocketSUCV2018 03440
StatusPublished

This text of CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & Others (CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & Others) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & Others, (Mass. Ct. App. 2020).

Opinion

SUPERIOR COURT

CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & others[1]

Docket: SUCV2018 03440
Dates: December, 2020
Present: /s/Gregg J. Pasquale, Justice of the Superior Court
County: SUFFOLK, ss.
Keywords: MEMORANDUM OF DECISION AND ORDER ON CITY OF BOSTON'S PARTIAL MOTION FOR JUDGMENT ON THE PLEADINGS AND DEFENDANTS' CROSS MOTION FOR JUDGMENT ON THE PLEADINGS

    The City of Boston ("Boston") filed this action seeking judicial review of the September 25, 2018 decision of the Quincy Conservation Commission denying Boston's application for an order of conditions to rebuild the Long Island Bridge. For the reasons discussed below, the City of Boston's Partial Motion for Judgment on the Pleadings is ALLOWED and the Defendants' Cross‑Motion for Judgment on the Pleadings is DENIED.

BACKGROUND

    The following facts are taken from the administrative record. On May 17, 2018, TRC Environmental, on behalf of the City of Boston Public Works Department, filed a Notice of Intent ("NOI@) with the Quincy Conservation Commission ("the Commission") under both the Wetlands Protection Act, G.L.c. 131, ' 40 ("WPA"), and the Quincy Wetlands Protection Ordinance ("the Ordinance") to replace the superstructure of the Long Island Bridge between Moon Island and Long Island, over Boston Harbor and Quincy Bay ("the Bridge"), in order to restore access to the existing Boston Public Health opioid addiction treatment and homeless

--------------------

    [1]John T. Brennion, E. James Iorio, William Keener, Victoria Lebate, Maureen C. Glynn, Jeffrey Graeber, and Tom Carroll, in their official capacity as members of the Quincy Conservation Commission, and Jay Duca, in his capacity as agent for the Quincy Conservation Commission

-1-

facilities on Long Island ("the Project"). The original bridge was constructed in 1950, deemed structurally unsound in 2014, and demolished in 2015 for public safety reasons. The portion of the Project in Quincy involves placing new bridge spans over the existing piers and improving the stormwater system. The proposed Quincy work would occur in coastal wetland resource areas with a temporary impact but no anticipated permanent impact. The Project is subject to the Department of Environmental Protection ("DEP") Stormwater Management Standards set forth at 310 Code Mass. Regs. ' 10.05(6)(k)‑(q),

    The Project involves no temporary or permanent impact to land under ocean because the original bridge piers were left in place in Boston Harbor/Quincy Bay and the Project will utilize those existing piers. The Project will involve a temporary impact to 80 square feet of coastal beach at Moon Island and 512 square feet of coastal bank where the Bridge will meet land on Moon Island. This temporary impact consists of noise, turbidity, and impact to fish and shellfish and fisheries habitat on the ocean bottom and intertidal areas. There will be 592 square feet of temporary alteration of land subject to coastal storm flowage to install four temporary pipe piles during the installation of the Bridge.

    The NOI included a May 2018 Stormwater Management Report prepared for Boston by STV, Inc. The proposed surface area of the Bridge is 2.6 acres. The original bridge had scuppers that drained runoff directly into the harbor below. The Project involves collecting runoff in scuppers but routing it through a closed drainage system back to each island to be treated and then released into Boston Harbor/Quincy Bay. The Report states that DEP Stormwater Management Standards are applicable to the Project only to the maximum extent practicable because the Project is a redevelopment project. With respect to Standard 3 for Stormwater Recharge, because of the steep slope of Moon Island, there cannot be stormwater

-2-

recharge in the vicinity of the Project. Standards 1 (no new untreated discharge), 2 (peak rate attenuation), 9 (operation and maintenance plan) and 10 (prohibition of illicit discharges) are fully met. With respect to Standard 4, Water Quality, the Report attached a long‑term pollution prevention plan, and calculations‑showing that the system meets the 80% TSS removal requirement. With respect to Standard 8, the Report states that a Pollution Prevention and Erosion and Sedimentation Control Plan is not included but will be submitted before land disturbance begins. The Report included an April 30, 2018 Custom Soil Resource Report for Norfolk and Suffolk Counties.

    Included in the record are the meeting minutes from the May 16, 2018 public hearing on the Project conducted by the Boston Conservation Commission, which ultimately issued an Order of Conditions for the Project. At this hearing, Special Environmental Counsel for the City of Quincy, John Shea, raised concerns about the Project, including the structural integrity of the piers, and the lack of presentation and evaluation of alternatives to the Project. A representative of Tighe & Bond, the engineering consultant hired by the City of Quincy, recommended that an alternatives analysis be included addressing ferry service, questioned the structural integrity of the piers, and characterized as inadequate the information provided about stormwater management compliance.

    By letter dated June 1, 2018, the Division of Fisheries and Wildlife notified Boston that it had determined that the Project will not adversely affect the resource area habitat of state‑protected rare wildlife species and will not result in a prohibited "take" under the Massachusetts Endangered Species Act.

    The Commission held a public hearing on Boston's NOI on June 6, 2018. STV's design lead for the Project, Mark Ennis, and Sam Moffett from TRC Engineering gave a presentation on

-3-

the Project, explaining that the pier structures will be reinforced after which the bridge spans will be floated into place by barge with zero wetlands impact on land under the ocean. Reinforcement of the pier involves removing the granite cap pieces, drilling posts down through the concrete, and then pouring a concrete cap. Moffett explained that Boston would use the existing foundation of Pier 1 to stage equipment and construct a temporary trestle structure, which requires dragging four steel pipe piles, impacting 80 square feet in the buffer zone of the coastal beach area and 512 square feet of costal bank.


    Special Environmental Counsel for Quincy, John Shea, stated that this was a big project for Quincy and "the Mayor and neighbors are opposed to the access through Quincy for the drug treatment program." Shea stated that water access is a more cost effective alternative with fewer environmental impacts. He noted that Mayor Menino had studied and endorsed water access to Long Island, but Mayor Walsh "apparently, has a different agenda." Shea then stated that he was not asking the Commission to make a political decision about access but rather, to demand sufficient information to evaluate the Project under the WPA and Ordinance. Shea noted that although alternatives analysis and hazardous materials fall under the Massachusetts Environmental Protection Act ("MEPA"), that is not a permitting scheme that can impose substantive requirements on projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DeGrace v. Conservation Commission of Harwich
575 N.E.2d 373 (Massachusetts Appeals Court, 1991)
T.D.J. Development Corp. v. Conservation Commission
629 N.E.2d 328 (Massachusetts Appeals Court, 1994)
Manguriu v. Holder, Jr.
794 F.3d 119 (First Circuit, 2015)
Coghlin Electrical Contractors, Inc. v. Gilbane Building Co.
472 Mass. 549 (Massachusetts Supreme Judicial Court, 2015)
Parkview Electronics Trust, LLC v. Conservation Commission of Winchester
43 N.E.3d 335 (Massachusetts Appeals Court, 2016)
Smyth v. Conservation Commission of Falmouth
119 N.E.3d 1188 (Massachusetts Appeals Court, 2019)
Gove v. Zoning Board of Appeals
444 Mass. 754 (Massachusetts Supreme Judicial Court, 2005)
Oyster Creek Preservation, Inc. v. Conservation Commission
449 Mass. 859 (Massachusetts Supreme Judicial Court, 2007)
Welch v. Sudbury Youth Soccer Ass'n
901 N.E.2d 1222 (Massachusetts Supreme Judicial Court, 2009)
Golchin v. Liberty Mutual Insurance
950 N.E.2d 853 (Massachusetts Supreme Judicial Court, 2011)
Garrity v. Conservation Commission
971 N.E.2d 748 (Massachusetts Supreme Judicial Court, 2012)
Fafard v. Conservation Commission of Reading
672 N.E.2d 21 (Massachusetts Appeals Court, 1996)
FIC Homes of Blackstone, Inc. v. Conservation Commission
673 N.E.2d 61 (Massachusetts Appeals Court, 1996)
Fieldstone Meadows Development Corp. v. Conservation Commission
816 N.E.2d 141 (Massachusetts Appeals Court, 2004)
Hobbs Brook Farm Property Co. v. Conservation Commission
838 N.E.2d 578 (Massachusetts Appeals Court, 2005)
Rodgers v. Conservation Commission of Barnstable
853 N.E.2d 199 (Massachusetts Appeals Court, 2006)
Healer v. Department of Environmental Protection
901 N.E.2d 161 (Massachusetts Appeals Court, 2009)
Delapa v. Conservation Comm'n of Falmouth
108 N.E.3d 474 (Massachusetts Appeals Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & Others, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-boston-v-quincy-conservation-commission-others-masssuperct-2020.