Rodgers v. Conservation Commission of Barnstable

853 N.E.2d 199, 67 Mass. App. Ct. 200
CourtMassachusetts Appeals Court
DecidedAugust 24, 2006
DocketNo. 05-P-778
StatusPublished
Cited by9 cases

This text of 853 N.E.2d 199 (Rodgers v. Conservation Commission of Barnstable) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rodgers v. Conservation Commission of Barnstable, 853 N.E.2d 199, 67 Mass. App. Ct. 200 (Mass. Ct. App. 2006).

Opinion

Greenberg, J.

The conservation commission of Barnstable (commission), on the ground that the plaintiffs’ proposed permanent pier interfered with recreational shellfishing, declined [201]*201to issue an order of conditions authorizing its construction. The commission’s decision was based on G. L. c. 131, § 40, the State Wetlands Protection Act, and art. 27 of the Barnstable Wetlands Protection By-law (by-law). On review in the nature of certiorari (G. L. c. 249, § 4), a judge of the Superior Court concluded that the commission’s decision was not supported by substantial evidence and annulled it. We think the commission acted lawfully and reverse the judgment.

1. Background. The plaintiffs, Charles and Francene Rodgers (plaintiffs), own a house at 621 Old Post Road in Cotuit, situated on a 2.7 acre lot with 200 feet of frontage on Cotuit Bay. They filed a notice of intent with the commission on September 19, 2002, for the construction of a pier 121 feet long to be built in three sections, with an attached ramp, and an eight foot by ten foot float extending into the bay. That submission was made in conformity with G. L. c. 131, § 40, and art. 27 of the by-law. The proposed pier was to be constructed at or near a “Shellfish Relay Area,”3 so designated by the town’s shellfish biologist and deputy shellfish constable and the director of the Massachusetts Division of Marine Fisheries. The area was designated a “4” zone in terms of shellfish productivity (out of a scale of 1 to 10).4

During the course of the proceedings before the commission, the plaintiffs modified the design of the pier. They redesigned the pier so that its elevation would be about two and one-half feet higher (eight and one-half feet above the mean low water level), and the over-all length of the pier was shortened by twelve feet. There was considerable resistance to the project from area residents and shellfishermen, many of whom signed a petition in opposition. Those who opposed the pier were [202]*202concerned that it would significantly impede the recreational use of the coastline, including sailing and shellfishing.

At the December 10, 2002, hearing, there was protracted testimony from several objecting parties concerning “prop dredging problems” caused by the construction of a pier. According to the testimony, prop dredging creates large holes in the ocean floor around the pier. One shellfisherman opined that the holes would be so deep that “if you’ve got waders on and you hit one of those holes, you’re not coming back up.” One of the commissioners expressed his concern that prop dredging stirs up the fine sediments of the ocean substrata, which might hamper the growth and development of different kinds of fish and shellfish.

The commission found that although the shellfish surveys submitted in evidence indicated low numbers of shellfish at the site of the proposed pier, those survey results were “an ineffective measure of the productivity and importance of the shellfishery” because “[t]he shellfishing at the locus is subjected to periodic commercial and recreational harvesting.” The commission also recognized that the site has historically been “important in providing quahogs for the [tjown’s recreational and commercial harvests.”

The commission made the following additional findings:

“6. The site is found significant under [G. L. c. 131, § 40,] to the interest of protection of land containing shellfish, and significant under Article 27 of the Town of Barnstable General Ordinances to the interests of shellfish and recreation.
“7. The Commission took testimony and correspondence from recreational shellfishermen who cited likely adverse impacts to the shellfishery should the project ensue.
“8. The Director of the MA Division of Marine Fisheries stated that the locus’ ‘use as a shellfish propagation area will be compromised if the construction of a pier with its attendant use by boats is permitted.’
“9. Article 27 of the Town of Barnstable General Ordinances regulates recreation, which it defines to include shellfishing.
[203]*203“10. Based on the testimony provided, the Commission finds it more likely than not that the proposed pier will inhibit and impede access to the shellfishery by recreational shellfishermen.
“11. Inhibiting and impeding access is found to pose a significant adverse impact to the recreation interest as protected by Article 27.
“12. The locus is but one of approximately 8 parcels which are located along the northerly shore of the Shellfish Relay Area. None of the eight has a pier. The Commission finds the project will have a significant cumulative effect upon recreation and shellfish as regulated under Article 27, as it will lead to the likelihood of additional piers constructed within the Relay Area.”

On February 4, 2003, the commission denied approval of the proposed pier under G. L. c. 131, § 40, “in the interest of protection of land containing shellfish, and under [art. 27] in the interest of shellfish[ing] and recreation.” The plaintiffs appealed the commission’s decision to the Department of Environmental Protection (DEP) pursuant to G. L. c. 131, § 40, which issued a superseding order of conditions (superseding order) on November 17, 2003, permitting the project. The commission filed an appeal from that order with the DEP, requesting an adjudicatory hearing.5 The plaintiffs also filed this action in the Superior Court, seeking, inter alla, relief in the nature of certiorari. In ruling on the plaintiffs’ motion for judgment on the pleadings, the judge found that the commission’s decision was preempted by the DEP’s superseding order and unsupported by substantial evidence, “annulled” the commission’s decision, and ordered entry of judgment for the plaintiffs. Only the appeal by the town and the commission from the Superior Court judgment is before us.

2. Standard of review. When considering a case in the nature of certiorari, “the standard of review may vary according to the nature of the action for which review is sought.” Forsyth Sch. for Dental Hygienists v. Board of Registration in Dentistry, 404 [204]*204Mass. 211, 217 (1989). See T.D.J. Dev. Corp. v. Conservation Commn. of N. Andover, 36 Mass. App. Ct. 124, 128 (1994). “In order to overturn [an agency’s decision], the applicants must establish that it was arbitrary and capricious or unsupported by substantial evidence. See Lovequist v. Conservation Commn. of Dennis, 379 Mass. 7, 18 (1979); FIC Homes of Blackstone, Inc. v. Conservation Commn. of Blackstone, 41 Mass. App. Ct. [681,] 684-685 & n.4 [1996].” Dubuque v. Conservation Commn. of Barnstable, 58 Mass. App. Ct. 824, 828-829 (2003). “If the agency has, in the discretionary exercise of its expertise, made a choice between two fairly conflicting views, and its selection reflects reasonable evidence, a court may not displace [the agency’s] choice.” Conservation Commn. of Falmouth v. Pacheco, 49 Mass. App. Ct. 737, 739-740 n.3 (2000) (citations omitted).

3. The Barnstable by-law. It is settled that the town, under its by-law, could set wetland protection standards that were more demanding than those set forth in the statutory scheme.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nachtwey v. Conservation Comm'n of Kingston
122 N.E.3d 1102 (Massachusetts Appeals Court, 2019)
Conroy v. Conservation Commission
899 N.E.2d 879 (Massachusetts Appeals Court, 2009)
Pheeney v. Houle
24 Mass. L. Rptr. 505 (Massachusetts Superior Court, 2008)
Oyster Creek Preservation, Inc. v. Conservation Commission
449 Mass. 859 (Massachusetts Supreme Judicial Court, 2007)
United States Gypsum Co. v. Executive Office of Environmental Affairs
867 N.E.2d 764 (Massachusetts Appeals Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
853 N.E.2d 199, 67 Mass. App. Ct. 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rodgers-v-conservation-commission-of-barnstable-massappct-2006.