Conroy v. Conservation Commission

899 N.E.2d 879, 73 Mass. App. Ct. 552, 2009 Mass. App. LEXIS 60
CourtMassachusetts Appeals Court
DecidedJanuary 20, 2009
DocketNo. 07-P-920
StatusPublished
Cited by5 cases

This text of 899 N.E.2d 879 (Conroy v. Conservation Commission) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conroy v. Conservation Commission, 899 N.E.2d 879, 73 Mass. App. Ct. 552, 2009 Mass. App. LEXIS 60 (Mass. Ct. App. 2009).

Opinion

Rubin, J.

This case arises from the denial of a permit to Katherine Conroy (plaintiff) by the defendant conservation commission (commission) of the town of Lexington (town) under the town’s general by-law for wetland protection (by-law) and the rules adopted thereunder by the commission (rules).

I.

The plaintiff sought to construct a single-family house on a [553]*55317,700 square foot undeveloped lot in Lexington. The lot is bisected by a stream which the Department of Environmental Protection (DEP) has classified as an intermittent stream, and a protected resource under the Wetlands Protection Act, G. L. c. 131, § 40 (Act). In the proceeding below, the commission also determined that it is an intermittent “stream” as defined in the by-law.2

The by-law is stricter in some respects than the Act. See Fafard v. Conservation Commn. of Reading, 41 Mass. App. Ct. 565, 568 (1996). The by-law specifies the interests that it seeks to protect (by-law interests).3 It includes within its definition of protected areas a buffer zone that includes those areas within “[o]ne hundred feet horizontally lateral from the edge of any bank . . . [or] stream . . . .” By-law § 130-8(C)(4)(a). For construction upon or alteration of such protected areas, the bylaw requires a permit issued by the commission. See by-law § 130-2. To obtain a permit, one must file a notice of intent (NOI). The by-law then provides that:

“[t]he applicant shall have the burden of proving by a preponderance of the credible evidence that the work proposed [in the NOI] will not cause significant individual or cumulative harmful effects to the interest sought to be protected by this by-law. In assessing cumulative harmful effects, the Commission may consider the likely long-term effects of the proposed work as well as the likely effects of the proposed work when taken in conjunction with any prior work and any contemplated future work in the affected area. Failure to provide to the . . . Commission [554]*554adequate evidence for it to determine that the proposed work will not cause significant harm to the interest sought to be protected by this by-law shall be sufficient cause for the . . . Commission to deny such permit or to grant such permit with such conditions as it deems reasonably necessary or desirable to carry out the purposes of this by-law or to postpone or continue the hearing to another date certain to enable the applicant and others to present additional evidence, upon such terms and conditions as seems to the Commission to be just.”

By-law § 130-7.

The by-law grants the commission authority to promulgate “rules and regulations to effectuate the purposes of this by-law.” By-law § 130-6. Pursuant to that authority, the commission has promulgated regulations which are denominated rules. The rules provide that new construction of residential buildings be set back by buffer zones of fifty to one hundred feet, see rules § 5(5)(A)(3), and that, “[o]f contiguous land within the 100-foot buffer zone, construction activities can disturb no more than 50% or the amount not presently supporting a natural community, whichever is greater.” Rules § 5(5)(C)(1).

Although the language in § 5 of the rules appears to impose a flat ban on the residential building and construction activities it describes, the section also includes a “commentary” that, we were informed at argument, was promulgated along with the substantive regulation. It states, “Past experience has shown that construction within these buffer zones is very likely to cause significant harm to the interests sought to be protected by the [by-law]. The . . . Commission will therefore not approve any smaller buffer zone unless it is persuaded by clear and convincing evidence that the smaller buffer zone will secure the protection of those interests.” Rules § 5(5) commentary.

II.

The plaintiff filed her first NOI under both the Act, which also contains an NOI process, and the by-law, in 2001. In 2003, after a hearing, the commission issued an order of conditions denying the project under both the Act and the by-law. The plaintiff appealed to the DEP as to the commission’s conclusion [555]*555under the Act, and filed a separate appeal under G. L. c. 249, § 4, the certiorari statute, to the Superior Court, as to the commission’s conclusion under the by-law. While the matter was pending before the DEP, the plaintiff revised the proposed project. In May, 2004, based on that change, the DEP issued a superseding order of conditions approving the project with conditions under the Act.

In January, 2005, having received this DEP approval, the plaintiff filed a second NOI with the commission based on the new plan, solely under the by-law. The plan proposed construction of a residential building within the fifty-foot buffer zone; the construction would also, the commission found, disturb over fifty percent of the contiguous buffer zone.

The plaintiff submitted to the commission, among other things, a letter from a wetland ecologist stating that under the plaintiffs proposed project, “the functions of the Bank and stream will be maintained by . . . buffer enhancements proposed along the stream corridor.” According to the “Drainage Summary,” submitted with the NOI, “[t]he project drainage design has been approved by the Lexington Town Engineer . . . , and will result in a slight decrease in the peak rate of runoff from the site versus existing conditions.” The plaintiff also submitted a letter by an engineer concerning runoff. The plaintiff asserted that the proposed buffer enhancement plan would actually “improveQ . . . wetland/ watercourse and buffer functions.” She argued, among other things, that the construction would cause no change to the stream or its banks; that planting along the banks would improve protection of the buffer, contributing to the stability of the area and improving its value as a wildlife habitat; that “permeable fill” in the construction would reduce runoff; and that her proposed construction would promote rather than harm by-law interests.

The commission held a public hearing on the NOI over two days. After the first day, the wetland ecologist submitted an additional letter. Both he and the plaintiff’s engineer testified. Abutters also testified regarding their concerns about flooding from the project and future maintenance.

The commission voted to deny the second application. It found that the land abutting the stream is a “bank” subject to protection under the by-law, and concluded that the project was [556]*556not in compliance with the rules for two reasons. First, the home would be constructed closer than the fifty-foot setback, as close as twenty-five feet from the bank. Second, the construction site development and landscaping activities would disturb more than fifty percent of contiguous land within the 100-foot buffer zone. The commission found that within the contiguous buffer zone on the western side of the bank, “construction activities will disturb approximately 78.8 percent of the total area of the contiguous buffer zone presently supporting a natural community.”4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doe v. Sex Offender Registry Board
966 N.E.2d 826 (Massachusetts Appeals Court, 2012)
Hoffman v. Board of Zoning Appeal
910 N.E.2d 965 (Massachusetts Appeals Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
899 N.E.2d 879, 73 Mass. App. Ct. 552, 2009 Mass. App. LEXIS 60, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conroy-v-conservation-commission-massappct-2009.