Crosby v. Paul Hardeman, Inc.

414 F.2d 1, 1969 U.S. App. LEXIS 11323
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 28, 1969
Docket19440_1
StatusPublished
Cited by4 cases

This text of 414 F.2d 1 (Crosby v. Paul Hardeman, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crosby v. Paul Hardeman, Inc., 414 F.2d 1, 1969 U.S. App. LEXIS 11323 (8th Cir. 1969).

Opinion

414 F.2d 1

Gene C. CROSBY as Administrator of the Estate of Ray Crosby,
Deceased, Appellant,
v.
PAUL HARDEMAN, INC., a Michigan Corporation; Paul Hardeman,
Inc., a Delaware Corporation; Arkansas Power & Light
Company, Appellee, The Aetna Casualty and Surety Company;
and Jelco, Incorporated, Appellees.

No. 19440.

United States Court of Appeals Eighth Circuit.

July 28, 1969.

John Harris Jones, Pine Bluff, Ark., for appellant.

Donald T. Jack, Jr., of House, Holmes & Jewell, Little Rock, Ark., for appellees.

Before BLACKMUN, GIBSON and BRIGHT, Circuit Judges.

Floyd R. GIBSON, Circuit Judge.

This is an appeal from a summary judgment entered by Chief Judge Oren Harris, United States District Judge for the Eastern District of Arkansas, against the appellant Gene Crosby, Administrator of the estate of Ray Crosby, in a suit seeking compensation for the use or rental of certain heavy construction equipment.

Originally, Ray Crosby filed this complaint against Paul Hardeman, Inc., Aetna Casualty Insurance Company, Arkansas Power & Light Company, and Jelco, Incorporated, in the Arkansas state court. Crosby and Arkansas Power & Light (hereafter referred to as APL) were Arkansas citizens but all the other defendants were citizens of states other than Arkansas. The diverse defendants removed the suit to the federal district court. Crosby questioned the validity of the removal as there was a lack of complete diversity and he contended that there was no separate and independent claim or cause of action asserted against any of the diverse defendants so as to satisfy the requirements for removal when complete diversity is lacking under 28 U.S.C. 1441(c) (1948). The motion to remand was denied.

After Ray Crosby's death Gene Crosby, as administrator of Ray Crosby's estate, was substituted as plaintiff. The plaintiff's claims against Paul Hardeman, Inc. and its surety Aetna were settled and a judgment of dismissal was accordingly entered against those defendants. Thereafter the motion of APL and Jelco for summary judgment was granted.

Two issues are raised on this appeal: (1) the validity of the District Court's action in overruling the motion to remand to the state court; and (2) the validity of the summary judgment.

We will first consider the remand issue. Plaintiff contends the removal of the case from the state court was improvidently granted as there was no diversity jurisdiction against APL and there was only one cause of action stated arising out of the interlocked series of transactions alleged in the complaint.

The right of removal is statutory and the party seeking removal must show that he comes within the provisions of the statute. Edwards v. E.I. Du Pont De Nemours & Co., 183 F.2d 165 (5 Cir. 1950). The allegations of the complaint as set forth at the time the petition for removal was filed are controlling. Pullman Co. v. Jenkins, 305 U.S. 534, 537-538, 59 S.Ct. 347, 83 L.Ed. 334 (1939).

The complaint as originally filed alleged a general contract between Hardeman and APL for the construction of approximately 141 miles of transmission line, with Aetna Casualty Insurance Company as surety for Hardeman, the execution of a performance bond by Hardeman and Aetna, and a sub-contract of Hardeman with the plaintiff for use of a piece of heavy equipment, called a dragline, at a rental of $590 per week which Hardeman agreed to pay until the dragline was returned to plaintiff's equipment yard at DeWitt, Arkansas, and asserted that the dragline was furnished August 22, 1964 and remained in the possession of defendants until July 22, 1965. Plaintiff claimed $28,025 for 47 1/2 weeks' rental. In addition, plaintiff claimed $7,315.17 for other labor and equipment furnished to Hardeman under dates of September 10 and October 1, 1964, and some further sums for transportation and repair of the vehicle, bringing the total recovery sought to $39,022.17.

APL terminated its contract with Hardeman on or about November 28, 1964, apparently because of unsatisfactory progress under the general contract, and APL proceeded to make arrangements with defendant Jelco, Incorporated, to complete the construction of the transmission line. The plaintiff had received no payment at all for his equipment and services and he contacted APL in early December 1964 concerning his problem. He was notified by letter of December 15, 1964 that APL was making arrangements with Jelco to take over and complete the construction work undertaken by Hardeman and that Jelco was in the process of making a survey of the equipment on the job to determine which equipment it desired to retain and use. The letter also stated that after the survey Jelco would get in touch with plaintiff if it desired to retain and use the equipment and, if Jelco determined to use the owner's equipment, Jelco would be responsible for future rental payments. The letter indicated a probability that Jelco would desire to retain and use plaintiff's equipment but stated, 'Until Jelco advises you that it desires to use your equipment and you have made arrangements with them for the lease rental, all rental and other charges will be obligations of Paul Hardeman, Inc.' The letter assured the plaintiff that APL would 'do everything within its power both to collect what is already due you and to persuade Jelco to continue with the rental of your equipment.' Jelco, however, never contacted plaintiff, and both APL and Jelco ignored monthly billings sent by plaintiff.

Plaintiff did not pick up the dragline until July 22, 1965 when Aetna wrote to plaintiff that the dragline might be removed from its location on the construction job. Thus, in addition to seeking the sum of $39,022.37 from Hardeman and Aetna, the complaint charged APL and Jelco with liability for $18,880 of the total sought (for rental during the period from December 15, 1964 to July 22, 1965) in the event full recovery was not obtained from Hardeman and Aetna.

Since the diversity jurisdiction of the federal district courts is statutory and there is obviously a lack of complete diversity, this case would be removable only if a separate cause of action is stated against one or more of the diverse defendants so as to make removal to the federal courts appropriate under 28 U.S.C. 1441(c) (1948), which reads:

'Whenever a separate and independent claim or cause of action, which would be removable if sued upon alone, is joined with one or more otherwise nonremovable claims or causes of action, the entire case may be removed and the district court may determine all issues therein, or, in its discretion, may remand all matters not otherwise within its original jurisdiction.'

Present 1441(c) is part of the 1948 amendments to the Judicial Code.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Calderon v. Aldi, Inc.
D. Nebraska, 2023
Clark v. Ameritas Investment Corp.
408 F. Supp. 2d 819 (D. Nebraska, 2005)
Adams v. Bank of America, N.A.
317 F. Supp. 2d 935 (S.D. Iowa, 2004)
Jamaica Savings Bank v. Lefkowitz
390 F. Supp. 1357 (E.D. New York, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
414 F.2d 1, 1969 U.S. App. LEXIS 11323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crosby-v-paul-hardeman-inc-ca8-1969.