United States of America, for the Benefit and on Behalf of Adam J. Lanehart v. United Enterprises, Inc., and Seaboard Surety Company

226 F.2d 359
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 23, 1955
Docket15431
StatusPublished
Cited by9 cases

This text of 226 F.2d 359 (United States of America, for the Benefit and on Behalf of Adam J. Lanehart v. United Enterprises, Inc., and Seaboard Surety Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Benefit and on Behalf of Adam J. Lanehart v. United Enterprises, Inc., and Seaboard Surety Company, 226 F.2d 359 (5th Cir. 1955).

Opinion

CHRISTENBERRY, District Judge.

Pursuant to the Miller Act, § 2, 40 U. S.C.A. § 270b, this action was brought in the name of the United States for the benefit and on behalf of Adam J. Lane-hart, to recover a balance of $11,663.96 alleged to be due on a subcontract performed by Lanehart for United Enterprises, Inc. The District Court rendered judgment in favor of Lanehart in the sum of $3,032.87. 118 F.Supp. 427; Id., D.C., 123 F.Supp. 639.

United Enterprises, Inc., entered into a prime contract with the United States to repair, rehabilitate and remodel the hospital facilities at Camp Polk, Louisiana. United Enterprises, Inc. sublet the painting called for by the general contract to Lanehart at a price of $90,-000, “subject to additions and deductions.”

Seaboard Surety Company, the other defendant-appellee, is the surety on the Miller Act bond of United Enterprises, Inc.

*361 Lanehart alleged that he performed under the contract work amounting to $96,217.96, and extra work in the sum of $1,616.60. United Enterprises, Inc. paid $86,170.60, leaving a balance alleged to be due of $11,663.96, the amount sued for. Defendants disputed plaintiff’s figures and made part of their answer a schedule showing the amount due plaintiff under the subcontract was $87,-978.82, against which payments had been made of $86,170.60, leaving a balance due plaintiff of $1,808.22, which they tendered.

United Enterprises, Inc., and the surety in their answer alleged that certain items of work had not been performed by Lanehart for the reason that these items, under instructions of representatives of the United States, had been eliminated; that appellant knew of the elimination of these items at the time the subcontract was entered into; that the eliminated items totalled $3,294, and that United Enterprises, Inc. paid Lanehart in accordance with computations made by the Government. United Enterprises, Inc. and the surety denied the performance of extra work.

Under the terms of the specifications the Government had the right to increase or diminish the quantities, as follows:

“S.C. 15, Estimated Quantities. The quantities listed below are estimates only. The contractor will be required to complete the work specified herein in accordance with the contract. The contract unit prices will not be changed within the limit of 50 per cent less than the estimated quantities listed below, nor within the limit of 100 per cent more than the estimated quantities listed below.”

The subcontract between United Enterprises, Inc. and Lanehart called for the following work to be performed by Lanehart:

(1) “All the painting specified under part 4 of the specifications, Section 7, entitled Taints and Painting’ ”, for a lump sum of $90,000.

(2) The priming painting, etc., specified under Part 4 of the specifications, Section 1, entitled “Carpentry and Mill-work,” insofar only as those certain items are detailed in the contract, the price for which was to be over and above the lump sum price of $90,000 for the painting under the “Paints and Painting” work above.

With respect to payment to be received by Lanehart, the subcontract provided that:

“Payment for said work to be on a unit price basis, copy of which is attached hereto and made a part hereof of this contract agreement.
“-» * * Differences between unit prices and total lump sum of contract price to be paid subcontractor by general contractor.
“Article XI. The said Contractor agrees to pay to the said Subcontractor for such labor and materials herein undertaken to be done and furnished, the sum of Ninety Thousand and No/100 ($90,000.00) Dollars, subject to additions and deductions as herein provided, and such sum shall be paid by the contractor to the subcontractor as the work progresses in monthly installments, as follows.”

Under the terms of the subcontract, the subcontractor agreed to be bound to the contractor by the terms of the general contract, Article 2 of the subcontract reading as follows:

“Article 2. The subcontractor agrees to be bound to the contractor by the terms of the Agreement, Surety Bond, and General Conditions, Drawings and Specifications, for the entire work (which he has examined and read) insofar as they relate in any part or in any way to the work undertaken herein.”

The subcontract also contains the following provisions:

“Article 3. The work included in this contract is to be done under the direction of said architect (U.S. Engineer) and his decisions, as to- *362 the true construction and meaning of the drawings and specifications shall be final * * *.”

Lanehart, at the commencement of the trial, claimed the differences between the parties to be as follows:

(1) Items 173 and 174 .....$ 3,294.00

(2) Item 143 .............. 3,168.00

(3) Painting under Carpentry ................. 1,070.05

(4) Extras ................ 1,616.60

(5) Difference in counts on items ............... 333.39

(6) Difference between unit prices and total lump sum of contract...... 381.00

(7) Services and material, defendant claims to have furnished plaintiff .... 912.19

$10,775.23

Unaccounted for error ............... 7.30

Total in dispute......$10,767.93

Admittedly due by defendants 896.03

■ — Amount sued for .. .$11,663.96

The District Court, as has been stated, rendered judgment for plaintiff in the sum of $3,032.87. That sum is made up as follows:

Items originally admitted by defendants............ . ..$ 1,808.22 Items 173 and 174...... 200.00 Painting under Carpentry . • • 787.85 Extras ................. 64.40 Difference between unit prices and total lump sum contract .............. of 381.00

$ 3,241.47

Less Counter-claim allowed .......... 208.60

$ 3,032.87

Under the heading “Painting under Carpentry”, the plaintiff abandoned the sum of $282.20, and with respect to services and materials alleged by the defendants to have been furnished plaintiff, the latter recognized the validity of the claim to the extent of $298.60. Giving effect to these adjustments, and to the awards made by the District Court, the differences remaining between the parties, and forming the basis of this appeal, are as follows:

Items 173 and 174 .........$ 3,094.00

Item 143 .................. 3,168.00

Extras .................... 1,552.20

Difference in counts on items 333.39

Total .............$ 8,147.59

All of these differences are affected by the findings of the District Court as to the decisions made by the United States Engineer concerning the interpretation and the performance of both the prime contract and the subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gebhardt & Smith LLP v. Maryland Port Administration
982 A.2d 876 (Court of Special Appeals of Maryland, 2009)
United States v. R. H. Taylor
333 F.2d 633 (Fifth Circuit, 1964)
United States v. Blount
182 F. Supp. 648 (D. Maryland, 1960)
Fred C. McClean Heating Supplies, Inc. v. Jefferson Construction Co.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
FRED C. McCLEAN HEATING SUPPLIES v. JEFFERSON CONSTR.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
United States v. Montgomery
253 F.2d 509 (Third Circuit, 1958)
United States ex rel. Soda v. Montgomery
152 F. Supp. 309 (M.D. Pennsylvania, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
226 F.2d 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-benefit-and-on-behalf-of-adam-j-lanehart-ca5-1955.