United States of America for the Use and Benefit of H. O. Kilsby v. John R. George and National Surety Corporation

243 F.2d 83
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 2, 1957
Docket16311
StatusPublished
Cited by3 cases

This text of 243 F.2d 83 (United States of America for the Use and Benefit of H. O. Kilsby v. John R. George and National Surety Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of H. O. Kilsby v. John R. George and National Surety Corporation, 243 F.2d 83 (5th Cir. 1957).

Opinion

RIVES, Circuit Judge.

A subcontractor, H. O. Kilsby, as use plaintiff, brought this suit under the Miller Act 1 against his prime contractor, John R. George, and George’s surety, The record on appeal does not contain any transcript of the evidence because it is conceded that the facts were correctly found by the district court. The general factual background of the controversy is well stated by the learned district judge in his memorandum decision as follows:

“0n or about August 10, 1954, the United States of AmeriCa, acting through the Department of the Army> Corps of EngineerS; Tulsa District, entered into a contract with George, d/b/a B & M Service Contractors, as prime contractor for the construction of certain additions to the water supply system at the Eed Eiver Arsenal in Bowie County, Tex-ag; which contract bears No. DA — 34-066-eng — 4269 and will hereinafter be referre(j to as the prime contract,
“Among other matters covered by said prime contract was the construction of a clear well, i.e., a large underground concrete tank to be used for the purpose of removing undesirable ingredients in the water uged -n tbe water sygtem at the Red Eiyer AraenaL The cIear well was to be 90 feet gquare and n feet deep and wag to haye concrete top or roo£ Qn ^ ”
. , , , , , Ge°rge was requ/red ta and t furmsb a pa^Ae^ bond ,in *be “ , °f fu>750<5 Oas aquiree1 by the Mlller Af ™th the Surety Company as surety thereon.
“On or about September 24, 1954, Kilby> d/b/a trinity Engineer-Builders, entered into a contract George under the terms of which Küsb ag contracto was to perform certain portiong of ^ prime contract, including the construction of the clear well and the doing of certain other concrete work required in the prime contract, which contract between George and Kilsby will hereinafter be referred to as the subcontract. Under the *85 terms of the subcontract as originally entered into, Kilsby was to receive the sum of $52,867.60 for the labor and materials he was to perform and furnish under said contract, but by adjustments made m said contract the amount Kilsby was to receive JT , . , , ,, thereunder was increased to the sum ^ ’
_ “For some time prior to the date of the subcontract, Kilsby had been in the employ of George and Kilsby, as an employee of George, prepared the estimates that formed the basis of the bid submitted by George which resulted in George obtaining the prime contract. Under the terms of said contract, Kilsby agreed te supervise and act for the interest of George in the performance of the prime contract during the term of the subcontract for which service Kilsby was to be compensated in kind by George. In keeping with that provision of the subcontract, George, by letter dated September 20, 1954, advised the Corps of Engineers that he was authorizing Kils-by to act as his representative in all matters pertaining to the prime contract and for compensation for the services rendered by Kilsby as such representative George furnished Kilsby certain equipment,^ including trucks which Kilsby used in the performance of the subcontract. ^ In other words, in so far as the prime contract was concerned Kilsby s reía-tionship with George was a dual one, i.e., with reference to the work to be performed under the subcontract Kilsby was a subcontractor, but in dealing with the Corps of Engineers as ^ to all matters pertaining to the prime contract Kilsby was the representative of George.
“The plans and specifications prepared by the Corps of Engineers for the projects that was the subject matter of the prime contract were made a part of the prime contract. General Provision 6 of the prime contract provided the manner and means by which any dispute concerning a question of fact arising under the contract must be decided. 2 Gen-
„2 Dispute^_Except as other- ^ Med ^ tMg contract an dig_ , . pute concerning a question of fact arisf , ... . , , . __. mg under this contract which is not disposed of by agreement shall be decided fry contracting officer, who shall reduce his decision to writing and send by registered mail, return receipt requested, a COpy thereof to the contractor at his address shown herein. Within 30 days from the receipt thereof, the contractor may appeal in writing to the Chief of Engineers, whose written decision there-0Ilj or that 0f fhjg designated represéntafive or representatives, shall be final and conclusive upon the parties hereto unless, within 30 days after the receipt thereof by the contractor he appeals jn -writing to the Secretary, which appeai shall operate to vacate said decision of chief of Engineers. If the dispute is determined by the Secretary, liis written decision or that of his designated representative or representatives, shall, unless determined by a Court of competent jurisdiction to have been fraudulent, arbitrary, capricious or g0 grogs¡y erroneous as necessarily to imply bad faith, be final and conclusive upon the parties hereto. The Chief of Engineers or the Secretary may designate an individual, or individuals, other than the contracting officer, or a board as ^jg authorized representative to determine appeals under this article. In connection with any appeal proceeding under this clause, the contractor shall foe afforded an opportunity to be heard and offer evidence in support of his appeal. Pending final decision of a dispute hereunder the contractor shall proceed diligently with the performance of the contract and in accordance with the contracting officer’s decision.’
eral Provision 4 of the Contract recognizes that the contractor will be entitled to additional compensation if he is required to perform added *86 labor or furnish additional materials because of subsurface or latent physical conditions at the job site differing materially from those indicated in the contract or because of unknown physical conditions at the job site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract. This General Provision 4 further provides that if the parties cannot agree upon the adjustment to be made of a claim arising under the provisions of that condition the dispute between tile parties shall be determined in the manner provided by General Provision 6. Under the terms of the subcontract in question the provisions of the prime contract, including the plans, specifications and general conditions or provisions, in so far as applicable to the work included in the subcontract, became a part of the subcontract.
(( , , . , .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Premier Roof Co. v. United States
315 F.2d 18 (Ninth Circuit, 1963)
United States v. B. Perini & Sons
159 F. Supp. 911 (N.D. Florida, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
243 F.2d 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-h-o-kilsby-v-john-r-ca5-1957.