United States v. Fidelity and Deposit Co. of Maryland

144 F. Supp. 322, 1956 U.S. Dist. LEXIS 2761
CourtDistrict Court, W.D. Louisiana
DecidedAugust 22, 1956
DocketCiv. A. 4150
StatusPublished
Cited by11 cases

This text of 144 F. Supp. 322 (United States v. Fidelity and Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Fidelity and Deposit Co. of Maryland, 144 F. Supp. 322, 1956 U.S. Dist. LEXIS 2761 (W.D. La. 1956).

Opinion

HUNTER, District Judge.

Plaintiffs brought this action under the provisions of the Miller’ Act, 40 U.S. C.A. § 270a et seq., in the name of the United States and against the contracting firm of Miller & Long, and Fidelity and Deposit Company of Maryland, the surety on the bond of Miller & Long, to recover for work performed for and equipment supplied to Miller & Long in connection with the performance of its contract with the United States, dated September 27,1951, for the re-location of the Missouri Pacific Railroad Company railroad lines around the Lake Charles Air Force Base.

There is no question here of loss of anticipated profits. Both the subcontractor and the contractor last money. Plain *324 tiffs argue that Miller & Long either wrongfully terminated the subcontract or else the subcontract was terminated by mutual agreement. In brief, they itemize their claim as follows:

“(A) Balance due on borrow and channel excavation $14,437.-09.

“(B) $1,500.00 due on trenching.

“(C) Due for use of equipment during 15 days $8,723.00.

“(D) Extra cost of handling dirt by virtue of poor engineering on the part of Miller and Long’s Engineers $15,000.00.

“(E) Crowder’s share of $46,310.-21 extra payment made by Government on account of additional costs of dirt work because of delay in starting job, $16,000.00.

“(F) Additional costs of $2,500.00 because of dirt having to be hauled around fences.”

Defendants put at issue the material allegations of the complaint, and also filed a counter-claim, wherein it was alleged that the contractor was compelled to terminate the contract because of plaintiffs' refusal to perform it and demanded damages for its breach against plaintiffs. Defendants further say that if the Court should find that the contract was terminated by mutual agreement, that then the evidence, when viewed most favorably to the plaintiffs, would reveal that the following accounting is proper:

Items Claimed by Plaintiffs Total Claimed Proven and Recoverable
1. 92,000 cubic yards of borrow, 3,192 yards of channel $ 59,717.20 $22,079.00
2. Trenching 1.500.00 000.00
3. Equipment rental 8.723.00 5,000.00
4. Poor engineering 15.000. 00 000.00
5. Delay 16.000. 00 000.00
6. Erection of fences 2.500.00 000.00
Total $103,440.20 $27,079.00
Credits Due Defendants by Plaintiffs
1. Payments made on estimates $24,480.30
2. Pay roll advances (stipulation 9) 17,300.31
3. Equipment rental (stipulation 10) 1,835.80
4. Equipment rental (stipulation 12) 4,500.00
5. Equipment rental (stipulation 11) 1,777.83
6. Equipment repairs (stipulation 14) 971.36
7. Fuel bills (stipulation 13) 5,226.17
Total $56,091.79
Balance of Accounts
Credits Due Defendants $56,091.79
Amount Due Plaintiffs 27,079.00
Balance Due Defendants $29,012.79

*325 The case was tried to the Court. We have carefully considered the evidence, the respective briefs, authorities cited, and our clear recollection of the trial proceedings. The Court makes the following findings of fact:

(1) Subsequent to the original contract and on or about October 24, 1951, Miller & Long entered into a written subcontract with J. W. Crowder and Associates, plaintiffs, wherein plaintiffs agreed to do all borrow excavation at a price of Fifty (.50) Cents per cubic yard, and all channel excavation at a price of Thirty-Five (.35) Cents per cubic yard.

(2) All the excavation was to be done in strict accordance with the Plans and Specifications furnished by the United States Corps of Engineers.

(3) Subsequent to execution of the subcontract and before work was begun, plaintiffs advised Miller & Long in writing that they were going to cancel the subcontract. However, this never came to pass, and on or about December 15, 1951, plaintiffs commenced work in accordance with the provisions of the original subcontract.

(4) On March 21, 1952, a supplemental contract was entered into between plaintiffs and Miller & Long, increasing from Fifty (.50) Cents per cubic yard to Eighty-Five (.85) Cents per cubic yard the compensation for all borrow excavation in excess of 46,000 cubic yards.

(5) At the beginning of the subcontract, plaintiffs sent their bookkeeper, Mr. Myers, to act as superintendent for their portion of the job, and shortly thereafter Mr. Harp, an equipment operator, took over and continued to act in a supervisory capacity until June of 1952.

(6) In June of 1952 it became apparent that plaintiffs were in financial difficulty and Mr. Crowder personally took charge of the subcontract and informed Miller & Long that plaintiffs were unable to proceed further with the work unless they received financial assistance from someone. Miller & Long offered such financial assistance at the request of the plaintiffs and undertook the financing of plaintiffs’ operating expenses, including payrolls, fuel bills, equipment rentals, and equipment repairs. In this capacity they advanced to plaintiffs the sum of $17,800.31 for plaintiffs’ payroll (stipulation 9), $8,113.63 as rental for equipment used by plaintiffs (stipulations 10, 11 and 12), $5,226.17 for fuel (stipulation 13) and $971.36 for repairs to plaintiffs’ equipment. In addition to these sums paid to and on behalf of plaintiffs, Miller & Long, as of June 1, 1952, had paid plaintiffs in accordance with partial pay estimates furnished by the Corps of Engineers the sum of $24,480.-32.

(7) By August 13, 1952, it had become apparent that plaintiffs were not getting the work done, and on or about that date, Miller & Long, with the knowledge and consent of plaintiffs, entered into a contract with W. R. Aldrich and Company to assist plaintiffs by starting at the West end of the contract job and do the borrow excavation East to Station 26,050. For this portion of the subcontract, Miller & Long agreed to pay W. R. Aldrich & Company One ($1.00) Dollar per cubic yard, based upon quantities measured and allowed by the Corps of Engineers. Subsequently, Aldrich was allowed a net yardage of 44,177 cubic yards, for which Miller & Long paid W. R. Aldrich & Company $44,177.

(8) The Plans and Specifications on the job called for ballast or sub-ballast (gravel and rock) to be placed in a trench cut in top of the embankment. The cutting of the trench turned out to be rather a costly operation. Crowder did 1,500 feet of it, which cost him approximately $1.00 per foot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
144 F. Supp. 322, 1956 U.S. Dist. LEXIS 2761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-fidelity-and-deposit-co-of-maryland-lawd-1956.