Transamerica Insurance Company v. Red Top Metal, Inc.

384 F.2d 752, 4 A.L.R. Fed. 674, 1967 U.S. App. LEXIS 4831
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 18, 1967
Docket22707_1
StatusPublished
Cited by25 cases

This text of 384 F.2d 752 (Transamerica Insurance Company v. Red Top Metal, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transamerica Insurance Company v. Red Top Metal, Inc., 384 F.2d 752, 4 A.L.R. Fed. 674, 1967 U.S. App. LEXIS 4831 (5th Cir. 1967).

Opinion

WISDOM, Circuit Judge:

This case involves the liability of a Miller Act surety for attorneys’ fees.

Red Top Metal, Inc., a subcontractor on a federal construction project at the Bergstrom Air Force Base in Austin, Texas, furnished labor and materials to the Jack Collins Construction Company, the general contractor. Collins withheld certain payments from Red Top because of disputes over various delays and extras on the project. When Collins refused to pay, Red Top brought suit against the general contractor and its surety, the appellant in this case. Before trial, the surety paid the principal claim. The parties stipulated that they would “proceed to judgment only on the question of the recoverability of attorneys fees and that the remainder of plaintiff’s cause of action * * * be dismissed with prejudice”. 1 The parties *754 also stipulated that reasonable attorneys fees would be $1000. The court below found that under the Miller Act and “the substantive law of the State of Texas”, the plaintiff was entitled to attorneys’ fees. We reverse.

I.

The Miller Act, 40 U.S.C. § 270a-270d, requires a “payment bond * * * for the protection of all persons - supplying labor and material in the prosecution of the work” under a government construction contract. A plaintiff suing on the bond is denied his usual option of a state forum. The Act requires him to sue in a United States district court and in the name of the United States. The surety contends that since the Miller Act is silent on the subject of liability for attorneys’ fees, state law controls. We hold (1) that federal law controls; (2) that since the Miller Act is silent on the question of attorneys’ fees, the purpose of the Act must be examined for guidance in the resolution of this question; and (3) that the purpose of the Act suggests incorporation of state law. State law, therefore, does not operate of its own force to determine the scope of the surety’s liability on a Miller Act bond: The primary law is the Miller Act itself.

A. We see the claim for attorneys’ fees as an element of the supplier’s federal statutory right to protection under the Miller Act. This right does not originate in the common law or in Texas statutes. It comes from a congressional statute providing for a “payment” bond giving “protection” to all persons supplying labor and materials on a government contract. It is a federally created cause of action; it must be brought in the name of the United States; and Congress has vested federal courts with exclusive jurisdiction over all suits to enforce the action. In this view of the case, the Court is not construing the subcontract between the general contractor and the supplier. The Court is construing a federal statute and the bond issued in compliance with the statute.

In this Court’s most recent opinion in this area of the law, Judge Rives wrote:

The Miller Act bond, is not limited to the payment for labor and materials *755 * * * but is “for the protection of all persons supplying labor and material etc.” 40 U.S.C.A. § 270a (a) (2). It must be construed liberally in order to effectuate the purpose of Congress. Illinois Surety Co. v. John Davis Co., 1917, 244 U.S. 376, 378, 37 S.Ct. 614, 61 L.Ed. 1206. Article 2226, Vernon’s Civil Statutes of Texas provides for the allowance of attorneys’ fees on claims for labor done and material furnished, inter alia. The Miller Act bond covers this statutory right of a person .supplying labor and materials to the allowance of attorneys’ fees. Boyd Callan, Inc. v. United States, 1964, 5 Cir., 328 F.2d 505, 512 (emphasis added).

We recognize that the Court in that case looked to Texas law as governing resolution of the attorneys’ fees issue, 2 just as we do in this case. We emphasize, however, that state law “governs” only through incorporation into federal law, not through its own force.

The First Circuit, in ruling that the obligation of a surety on a bond furnished under the Act must be determined by federal law, observed:

The Miller Act implements a congressional policy that a bond with surety shall provide protection for persons supplying labor and materials for the construction or improvement of federal property. A suit under the Miller Act does not depend on diversity of citizenship but is a special, federal right of action limited to a federal court. 3 American Auto Ins. Co. v. United States for the Use and Benefit of Luce, 1959, 269 F.2d 406, 408 (emphasis added).

Similarly, the Ninth Circuit has said: “On the issue of Continental’s liability on the payment bond, the federal law should control because the determination of the extent of the liability involves the construction of a federal statute, the Miller Act, under which it was created.” Continental Casualty Co. v. Shaefer, 1949, 9 Cir., 173 F.2d 5, cert. denied 337 U.S. 940, 69 S.Ct. 1517, 93 L.Ed. 1745 (1949). “And even where the rights of the subcontractor against the contractor are determined by state law, the liability of the contractor’s surety will be governed by federal law because the determination of the extent of the liability involves the construction of the Miller Act.” 1A Moore, Federal Practice ft 0.323(16), at p. 1730. See also American Law Institute, Study of the Division of Jurisdiction Between State and Federal Courts, T.D. No. 3, App.C., (1965).

Directly in point is United States ex rel. Crowder v. Fidelity and Deposit Co., W.D.La. 1956, 144 F.Supp. 322. Subsequent to the termination of a subcontract by mutual consent of the subcontractor and the general contractor, the general contractor involved in that case wrongfully obtained an injunction restraining the subcontractor from the use of the subcontractor’s equipment that was on the job at the termination of the subcontract. The question was whether a reasonable attorneys’ fee for dissolving that injunction was an item of damages which might be allowed. The court observed that under Louisiana law recovery of attorneys’ fees would be allowed. But Judge Hunter held, after referring to the Louisiana law, that

the question as to whether or not such attorney’s fees can be collected under the Miller Act in this suit must be determined by the federal law. No authorities have been cited. However, *756

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Community Science Technology, Inc.
574 F.2d 1292 (Fifth Circuit, 1978)
United States v. F. D. Rich Co.
473 F.2d 720 (Ninth Circuit, 1973)
United States v. Yorfino
412 F.2d 329 (Fifth Circuit, 1969)
United States ex rel. Pratt Farnsworth, Inc. v. Talley
294 F. Supp. 1345 (E.D. Louisiana, 1969)
United States v. Wells
403 F.2d 596 (Fifth Circuit, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
384 F.2d 752, 4 A.L.R. Fed. 674, 1967 U.S. App. LEXIS 4831, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transamerica-insurance-company-v-red-top-metal-inc-ca5-1967.