F. & C. ENGINEERING CO. v. Moore

300 S.W.2d 323, 1957 Tex. App. LEXIS 1660
CourtCourt of Appeals of Texas
DecidedFebruary 6, 1957
Docket13107
StatusPublished
Cited by32 cases

This text of 300 S.W.2d 323 (F. & C. ENGINEERING CO. v. Moore) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. & C. ENGINEERING CO. v. Moore, 300 S.W.2d 323, 1957 Tex. App. LEXIS 1660 (Tex. Ct. App. 1957).

Opinion

BARROW, Justice.

This is an appeal by F. & C. Engineering Co., Inc., and the Aetna Casualty & Surety Company, its surety, two of the defendants in the trial court, from the judgment of the District Court of Bee County in favor of W. H. Moore et al., the plaintiffs, and against the defendants, in a case tried to the court without a jury.

Plaintiffs, W. H. Moore et al., formerly doing business as Coast Materials, which at all times for the purpose of this litigation was a partnership, but for clarity and convenience will be called material-man, engaged in the business of supplying ready-mix concrete to users of the same in Bee County and the surrounding area. The defendant F. & C. Engineering Co., Inc., hereinafter called General Contractor, was the general contractor under Navy Contract NOy-81871, for the construction of a high-speed apron refueling system at Chase Field, near Beeville; the defendant Aetna Casualty & Surety Company, hereinafter called Surety, was the general contractor’s surety on the performance and payment bond, guaranteeing among other things that the general contractor would promptly pay for all labor and materials furnished in the prosecution of the work under the contract. The general contractor entered into a contract with the defendant O & W Construction Company, hereinafter called subcontractor, a partnership composed of J. Y. Orms and Gene Weatherford, subcontracting to them part of the work under the general contract. The materialman furnished to the subcontractor ready-mix concrete used in connection with the subcontract, aggregating $10,982.50. The subcontractor and its two partners all became insolvent and were unable to pay the materialman.

At the conclusion of the trial judgment was rendered in favor of the materialman and against the subcontractor, the general contractor and the surety, for the principal sum of $4,982.50, plus interest, and $1,627.-50 attorney’s fees. From this judgment the general contractor and the surety have appealed. The trial court filed findings of fact and conclusions of law.

The appellants have assigned two points claiming error. First, it is contended that rendering judgment for $2,000 received by the subcontractor out of $8,000 paid for the general contractor, by check made payable to both the materialman and the subcontractor, was error. Second, it is contended that rendering judgment against appellants for attorney's fees was err;>r.

Considering the first point, we find that the record reveals: That the facts with reference to the amount due at the time the materialman handled distribution of the checks and the proceeds thereof are with *325 out dispute; and that the manager of the materialman issued a check for $2,000 out of the $8,000 check to the subcontractor, upon the representation by the subcontractor that the money was needed to pay for labor and other miscellaneous expenses.

The question before this Court is whether or not the advancement of this $2,000, by the materialman to the subcontractor, has the effect of releasing the general contractor and its surety from liability to the extent of this amount.

On June 20, 1955, the materialman wrote the general contractor, advising that the subcontractor had an unpaid account of $10,406 (later increased to $10,982.50) due the materialman, enclosing its statement in this amount and asking payment thereof by a check payable to subcontractor and materialman jointly. Under date of June 27, 1955, the general contractor wrote the subcontractor, transmitting its check in the amount of $,8000, payable jointly to the order of the subcontractor and the material-man, which check was an advance against subcontractor’s then current estimate. A copy of this letter was sent to the material-man. The check, which bore material-man’s address, was endorsed to the material-man by the subcontractor and the material-man issued its own check in the amount of $2,000 to the subcontractor, retaining $6,-000 of the proceeds.

It is conclusively established under the authorities, that a creditor who advances money to a subcontractor, even if the money is advanced to pay for labor and materials, is not entitled to the benefit of the liens given laborers and materialmen, nor to the benefit of the bonds required of general contractors to secure the payment for labor and materials. In the case of Verschoyle v. Holifield, 132 Tex. 516, 123 S.W.2d 878, 883, Justice Smedley states the above rule and cites numerous authorities in support of his statement.

While the situation presented by the facts in this case has never been passed upon by the Courts of this State, the Supreme Court of South Carolina, in the case of City Lumber Company v. National Surety Corporation, 229 S.C. 115, 92 S.E.2d 128, lays down the rule which we believe is controlling in this case.

That was a suit by a materialman against the surety on the performance bond of a construction contract. Under the terms of the bond the contractor and the surety were obligated to pay for all labor, materials and equipment performed and furnished on the job. The materialman, City Lumber Company, furnished paint to the subcontractor, Drake, for which there was a balance unpaid totaling $2,251.74. Drake and the contractor, Southern Construction Company, both refused payment. The trial court held for the materialman, and allowed judgment of $2,251.74.

During the performance of the contract, Drake and the manager of the City Lumber Company went to the vice president of Southern Construction Company and urged him to make payment to Drake on his contract so that Drake might pay on his paint accounts. The vice president stated that he thought it would be some time before a payment would be submitted, and offered little encouragement about an immediate payment. However, on February 15, 1952, a check drawn on the Southern Construction Company was sent to Drake’s foreman on the job, payable to the joint order of Drake and the City Lumber Company in the amount of $3,500, earmarked “advance on contract.”

On the same day of receipt of the check Drake called the manager of the City Lumber Company and told him of the check and asked his permission to endorse the name of City Lumber Company on the back of the check in order that he might collect it and pay his pressing labor bills, and promised to make a substantial payment on the account of City Lumber Company, Mann, the manager of City Lumber Company, agreed to this request, and several days later received from Drake a check for *326 $500 as payment, on the paint account. IJrake still had work to do on the contract and continued purchasing paint from City Lumber Company until February 21, 1952, thereby increasing- the paint account by $234.38 from the date of receipt of the check to the date he discontinued purchasing paint.

Mann testified that he was never given any notice that he was to collect the City Lumber Company’s account from the check, and claimed that had he known he was expected to do so, he would not have authorized the endorsement of the check.

The Court stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plains Builders, Inc. v. Steel Source, Inc.
408 S.W.3d 596 (Court of Appeals of Texas, 2013)
SFR, INC. v. Comtrol, Inc.
2008 UT App 31 (Court of Appeals of Utah, 2008)
Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc.
788 P.2d 73 (Arizona Supreme Court, 1990)
Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc.
774 P.2d 1372 (Court of Appeals of Arizona, 1989)
Iowa Supply Co. v. Grooms & Co. Construction
428 N.W.2d 662 (Supreme Court of Iowa, 1988)
Glidden Coatings & Resins v. SUITT CONST. CO., INC.
349 S.E.2d 89 (Court of Appeals of South Carolina, 1986)
Cameron County Savings Ass'n v. Cornett Construction Co.
712 S.W.2d 580 (Court of Appeals of Texas, 1986)
Anchor Concrete Co. v. Victor Savings & Loan Ass'n
664 P.2d 396 (Supreme Court of Oklahoma, 1983)
Friedman Steel Sales, Inc. v. Texas Utilities Co.
574 S.W.2d 849 (Court of Appeals of Texas, 1978)
United States v. Glassman Construction Co.
397 F.2d 8 (Fourth Circuit, 1968)
United States v. Glassman Construction Company
397 F.2d 8 (Fourth Circuit, 1968)
New Amsterdam Casualty Co. v. Texas Industries, Inc.
414 S.W.2d 914 (Texas Supreme Court, 1967)
Trinity Universal Insurance Co. v. Ponsford Bros.
414 S.W.2d 16 (Court of Appeals of Texas, 1967)
Yates v. Industrial Steel Products Co.
399 S.W.2d 892 (Court of Appeals of Texas, 1965)
H. Richards Oil Company v. WS Luckie, Inc.
391 S.W.2d 135 (Court of Appeals of Texas, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
300 S.W.2d 323, 1957 Tex. App. LEXIS 1660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-c-engineering-co-v-moore-texapp-1957.