City of Philadelphia Ex Rel. Allied Roofers Supply Corp. v. Joseph S. Smith Roofing Inc.

599 A.2d 222, 410 Pa. Super. 95, 1991 Pa. Super. LEXIS 3522
CourtSuperior Court of Pennsylvania
DecidedNovember 18, 1991
Docket1914
StatusPublished
Cited by12 cases

This text of 599 A.2d 222 (City of Philadelphia Ex Rel. Allied Roofers Supply Corp. v. Joseph S. Smith Roofing Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Philadelphia Ex Rel. Allied Roofers Supply Corp. v. Joseph S. Smith Roofing Inc., 599 A.2d 222, 410 Pa. Super. 95, 1991 Pa. Super. LEXIS 3522 (Pa. Ct. App. 1991).

Opinion

FORD ELLIOTT, Judge:

This is an appeal from the June 4,1990 order in the Court of Common Pleas of Philadelphia County denying appellants’ post-trial motions and affirming the judgment entered on March 17, 1990 following a non-jury trial before the Honorable Nelson A. Diaz. Appellant, a supplier of roofing materials, initiated the underlying breach of contract action in an attempt to recover monies owed by appellees, the general contractor and its surety, pursuant to joint payment agreements on two separate construction projects.

Appellee, J.J. White, (hereafter referred to as “White”), was a general contractor for two construction projects for the city of Philadelphia: the Queen Lane project and the Divine Providence Village project. White engaged Fireman’s Fund Insurance Company, (hereafter referred to as “Fireman’s Fund”), to act as surety on the Queen Lane Project for the City of Philadelphia. Thereafter, White entered into a subcontract with Joseph Smith Roofing Company, (hereafter referred to as “Smith”), whereby Smith would perform roofing work on both construction projects. Subsequently, Smith entered into a supply contract with appellant, Allied Roofers Supply Corporation, (hereafter referred to as “Allied”), whereby Allied would supply materials to Smith for the two projects.

As a requirement for supplying material to Smith, Allied required the execution of joint payment agreements. Smith and Allied entered into separate but identical joint payment agreements with White on both projects which provided:

(A) All checks drawn in payment for materials shipped by [Allied] to the [project sites], are to be drawn jointly to [Allied] and [Smith].
(B) Payments for the material are to be made in accordance with terms and conditions of [the subcontracts) ].
*100 (C) Payments for the material to [Allied] according to Paragraphs “A” and “B” above are contingent upon Allied’s delivery of the material to the [site] and subcontract noted in “B” above.
(D) Payment is to be mailed to [Allied], 2430 East Tioga Street, Phila, PA 19134.

As set out above, under the language of paragraphs (A) and (B) of the agreement, all checks drawn in payment for materials shipped by Allied to the site were to be drawn jointly to Allied and Smith, and payments for the materials were to be made in accordance with the terms and conditions of the subcontract(s) between Smith and White.

Provision 13 of the subcontracts between Smith and White defined the terms and conditions of payments for work performed as follows:

The Subcontractor, unless otherwise directed by the Contractor, shall submit to the Contractor at the end of each month a requisition containing an itemized estimate of the Subcontract Work done and materials furnished and incorporated into the Project which shall be in such form and be supported by such information, certificates and documents as the Contractor shall require. The amount to which the Subcontractor shall be entitled upon any such monthly estimate shall be the amount approved by the Architect/Engineer and/or Owner and Contractor. The Contractor shall pay to the Subcontractor, on or about the twenty-fifth day of the following month 90% of the amount approved by the Architect/Engineer and/or Owner and Contractor.
The balance due or final payment to the Subcontractor shall be paid, by the Contractor to the Subcontractor, upon the expiration of thirty (30) days from the date of the completion of the Project, when accepted and certified by the Architect/Engineer and/or Owner and Contractor whichever the case may be.
Should it appear at any time that the Subcontractor, or anyone performing any part of the Subcontract Work, has not paid any amount due for labor, materials, equip *101 ment, or services supplied in connection with the performance of the Subcontract Work, the Contractor shall have the right, but not the obligation, to retain out of any payment then due or thereafter to become due the Subcontractor, monies sufficient to pay such amount. If all payments due hereunder have been made to the Subcontractor, the Subcontractor shall refund such amount to the Contractor.

In accordance with this provision, at the end of each month Smith would submit to White a requisition for payment. The requisitions would request that checks be made payable solely to Smith or that checks be made payable jointly to Smith and Allied evidencing materials used and incorporated into the project. Each payment requisition contained a form certification, signed by the president of Smith, that all amounts due and owing for materials had been paid in full except as noted. Each time a joint check was issued, it was mailed to Allied and Allied retained all the proceeds and credited the amount toward Smith’s account.

As a result of this invoicing procedure, Smith submitted a total of six applications for payment on the Queen Lane Project, five of which followed the execution of the joint payment agreement for amounts totalling $25,572.24. At the instruction of Smith, White paid only two of these applications with jointly payable checks for a sum total of $4,817.34. Smith did not complete the work on the Queen Lane Project and White was required to secure another subcontractor for completion of the project. The substitute contractor testified that there were no materials at the job site when he took over the work. Allied claims that it supplied materials in the amount of $19,994.36 on the Queen Lane Project. Having retained all the proceeds of the joint checks issued in the amount of $4,817.34, Allied claims it is still owed $15,177.02.

On the Divine Providence Project, Smith submitted seven invoices for payments, only four of which requested the issuance of jointly payable checks. The sum total of the *102 seven invoices was $74,788.44. Allied claims that it has received $37,364.16 through joint checks for materials supplied on the Divine Providence Project but is still owed $25,143.72. The estimated cost for materials submitted by Smith to White for the project was $33,000. No final payment has ever been issued on the Divine Providence Project.

Allied first argues that White unilaterally modified the joint payment agreement by failing to issue all checks on both projects payable jointly to Smith and Allied and that this breach includes the failure to issue a final payment on the Divine Providence Project made jointly payable to Smith and Allied.

Based on the language of the joint payment agreements, the language of the subcontracts incorporated therein, and the business dealings of the parties, we find no merit to Allied’s argument that White was required to issue all checks on the projects jointly payable to itself and Smith. Rather, we find the conduct of White to be in compliance with the terms of the joint payment agreement, rather than a modification thereof. 1

The joint payment agreement between the parties herein represented nothing more than a joint check arrangement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis Construction Corp. v. FTJ
Supreme Court of Virginia, 2020
Plains Builders, Inc. v. Steel Source, Inc.
408 S.W.3d 596 (Court of Appeals of Texas, 2013)
Sparrow v. PACE/CM, Inc.
22 Pa. D. & C.5th 5 (Lackawanna County Court of Common Pleas, 2011)
Safeco Insurance Co. of America v. Graybar Electric Co.
59 So. 3d 649 (Supreme Court of Alabama, 2010)
HSI North Carolina, LLC v. Diversified Fire Protection of Wilmington, Inc.
611 S.E.2d 224 (Court of Appeals of North Carolina, 2005)
Glen-Gery Corp. v. Warfel Construction Co.
734 A.2d 926 (Superior Court of Pennsylvania, 1999)
Ragan v. Tri-County Excavating, Inc.
62 F.3d 501 (Third Circuit, 1995)
County of Oakland ex rel. Kuhn v. Vista Disposal, Inc.
875 F. Supp. 410 (E.D. Michigan, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
599 A.2d 222, 410 Pa. Super. 95, 1991 Pa. Super. LEXIS 3522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-philadelphia-ex-rel-allied-roofers-supply-corp-v-joseph-s-smith-pasuperct-1991.