Davis Construction Corp. v. FTJ

CourtSupreme Court of Virginia
DecidedMay 14, 2020
Docket190345
StatusPublished

This text of Davis Construction Corp. v. FTJ (Davis Construction Corp. v. FTJ) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis Construction Corp. v. FTJ, (Va. 2020).

Opinion

PRESENT: All the Justices

JAMES G. DAVIS CONSTRUCTION CORPORATION

OPINION BY v. Record No. 190345 JUSTICE STEPHEN R. McCULLOUGH May 14, 2020 FTJ, INC., F/K/A CIESCO, INC.

FROM THE CIRCUIT COURT OF ARLINGTON COUNTY Louise M. DiMatteo, Judge

Relying on the doctrine of unjust enrichment, the trial court held that a general contractor,

James G. Davis Construction Corporation (“Davis”), was liable for construction materials

provided by a supplier to one of Davis’s subcontractors. Davis challenges this judgment on a

number of grounds. For the reasons noted below, we affirm the trial court’s judgment.

BACKGROUND

Davis served as the general contractor for a residential condominium project in Arlington

County. On February 19, 2016, Davis contracted with H&2 Drywall Contractors to complete the

drywall and metal framing for this project. H&2 was required to provide all labor, materials,

supervision, and equipment to complete those aspects of the construction project. The revised

contract between Davis and H&2 called for H&2 to be paid a total of $1,269,396, which was to

be paid in installments. The contract also called for 10 percent retainage, to be withheld until

final payment was due.

H&2 agreed to purchase materials for the project from Ciesco, now known as FTJ, Inc.

H&2 completed a Credit Application and Agreement, in which it agreed to pay Ciesco for

materials delivered to H&2. Renan Buendia, the principal of H&2, also provided a personal

guarantee to pay Ciesco any amounts H&2 owed to Ciesco for building materials. To ensure the smooth operation of the project, Davis and H&2 entered into a joint check

agreement. That agreement provided as follows:

JOINT CHECK AGREEMENT

THIS JOINT CHECK AGREEMENT (“Agreement”) is made this 29 day of April, 2016 by and among (1) JAMES G. DAVIS CONSTRUCTION CORPORATION, whose address is 12530 Parklawn Drive, Rockville, Maryland 20852 (“DAVIS”), (2) H&2 Drywall Contractors (“Subcontractor”) whose address is 6702 Braddock Rd. Annandale VA 22003 and (3) (“Supplier”) Ciesco Inc. whose address is Corporate Office 109 Millers Ln Harrisburg PA 17110

The parties to this agreement hereby agree as follows:

1. Any and all material checks issued by DAVIS to Subcontractor for invoices submitted by Supplier to Subcontractor on sales of materials in connection with the construction project known as Lot 3 Gas line (“Project”) shall be made payable to Supplier and Subcontractor, provided Subcontractor and Supplier agree upon the amount actually owed by Subcontractor to Supplier for such invoices. 2. All such checks issued by DAVIS to Subcontractor shall be immediately endorsed by Subcontractor, then promptly delivered by Subcontractor to Supplier at the above address (or such other address as Supplier may designate in writing). 3. DAVIS will only make payments to Subcontractor and Supplier by joint check to the extent that DAVIS actually owes money to Subcontractor on the Project. 4. The sole purpose of this Agreement is to assist Subcontractor in making payment to Supplier of invoices on sales of all materials furnished by Supplier to Subcontractor for use in connection with the Project. This Agreement does not constitute an assignment of fund. Nothing contained in this Agreement is intended by the parties to create any contractual relationship or equitable obligation between DAVIS and Supplier; this Agreement is solely for the convenience of the parties. This Agreement may be cancelled at any time by DAVIS upon written notice to Subcontractor and Supplier.

JAMES G. DAVIS CONSTRUCTION CORP. SUBCONTRACTOR H&2 drywall contractor

By Michelle Christen By Renan Buendia

2 Michelle Christen - VP Accounting & Renan Buendia PM Financial Reporting SUPPLIER By Jeffrey G. Depew CFO Jeffrey G. Depew II

The agreement thus specifies a method for how Ciesco would be paid for the materials it

shipped to the job. Ciesco would send its invoices to Davis and H&2. Davis would pay via a

joint check made payable to both H&2 and Ciesco and deliver the check to H&2. H&2 would

then endorse the check and turn it over to Ciesco to apply against the invoices for the project.

The joint check agreement specifies that “DAVIS will only make payments [to H&2] and

[Ciesco] by joint check to the extent that DAVIS actually owes money to [H&2] on the

Project.” 1

Joint checking agreements are common in the construction industry. A joint checking

agreement facilitates payment to a supplier, by providing a greater assurance to the supplier that

it will be paid. With a joint check, the subcontractor cannot abscond with money owed to the

supplier. From Ciesco’s perspective, the joint check agreement meant that there was no credit

limit on the amount of materials it would ship to H&2 at one time. The agreement made Ciesco

more confident that it would be paid and alleviated any concerns it might have about shipping a

larger increment of materials.

Ciesco began shipping materials in July 2016. Payment was due within 60 days of the

date of the invoice. When Ciesco experienced repeated delays in the payment of its invoices,

Jolene Finley, an accountant with Ciesco, reached out to Davis at repeated intervals: November

11, 2016, December 13, 2016, and January 10, 2017. Ciesco’s policy was not to ship additional

1 The joint check agreement does not provide that it is subject to the terms of Davis’s subcontract with H&2.

3 materials on accounts that are past due. Each time Ciesco inquired about the past due invoices,

Davis responded that a check had been or would be written. Initially, the parties contemplated

that the check would be written pursuant to the joint check agreement and that is how Davis paid,

writing joint checks to H&2 and Ciesco. Davis sent two “release of liens” forms to Ciesco for

invoices that had been paid. Davis paid the invoices for materials Ciesco provided through

December of 2016. Benjamin Mahoney, who managed the project for Davis, acknowledged that

a supplier who is not paid might cut off supplies, and that there is “always a concern” about

non-payment generating delays. Mahoney explained that Davis’s involvement with Ciesco’s

invoices is “not a typical scenario for us to be in.” He testified that, ordinarily, the subcontractor

is hired “to manage that process, to manage the orders, [and] to manage the invoices.” Davis’

assurances to Ciesco in January 2017 resulted in Ciesco continuing to ship materials to H&2

rather than withholding materials because the account was past due.

As work on the project progressed, Davis noticed that H&2 was in difficulty. In early

2017, Davis learned that H&2 had “payroll payment problems” and was not paying its

employees. As a predictable result of not paying its employees, H&2 was having trouble

supplying enough personnel to complete the project. By March 22, 2019, Davis came to the

conclusion that H&2 would not be able to pay its suppliers. For its part, Ciesco was not aware of

any issues H&2 was having. However, while Davis was communicating with Ciesco about

Ciesco’s unpaid invoices, Davis was concerned about Ciesco cutting off supplies to H&2 based

on, at least in part, H&2’s financial condition.

Ciesco made deliveries of materials from January 10 through March 22. Neither H&2

nor Davis paid for those materials. Ciesco did not deliver any additional materials after March

2017.

4 On March 21, 2017, Davis issued a “notice to cure” to H&2, detailing the issues Davis

was having with H&2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great-West Life & Annuity Insurance v. Knudson
534 U.S. 204 (Supreme Court, 2002)
Mongold v. Woods
677 S.E.2d 288 (Supreme Court of Virginia, 2009)
Schmidt v. Household Finance Corp., II
661 S.E.2d 834 (Supreme Court of Virginia, 2008)
Hamm v. Scott
515 S.E.2d 773 (Supreme Court of Virginia, 1999)
Po River Water & Sewer Co. v. Indian Acres Club of Thornburg, Inc.
495 S.E.2d 478 (Supreme Court of Virginia, 1998)
United Savings Ass'n of Texas v. Jim Carpenter Co.
252 Va. 252 (Supreme Court of Virginia, 1996)
Commerce v. Equity
695 So. 2d 383 (District Court of Appeal of Florida, 1997)
Rosser v. Cole
379 S.E.2d 323 (Supreme Court of Virginia, 1989)
American Standard Homes Corp. v. Reinecke
425 S.E.2d 515 (Supreme Court of Virginia, 1993)
Nedrich v. Jones
429 S.E.2d 201 (Supreme Court of Virginia, 1993)
Evaluation Research Corp. v. Alequin
439 S.E.2d 387 (Supreme Court of Virginia, 1994)
Columbia Wholesale Co. v. Scudder May N.V.
440 S.E.2d 129 (Supreme Court of South Carolina, 1994)
Kern v. Freed Co., Inc.
299 S.E.2d 363 (Supreme Court of Virginia, 1983)
Hendrickson v. Meredith
170 S.E. 602 (Supreme Court of Virginia, 1933)
Flooring Systems, Inc. v. Radisson Group, Inc.
772 P.2d 578 (Arizona Supreme Court, 1989)
Datastaff Technology Group, Inc. v. Centex Construction Co.
528 F. Supp. 2d 587 (E.D. Virginia, 2007)
Morris Pumps v. Centerline Piping, Inc.
729 N.W.2d 898 (Michigan Court of Appeals, 2007)
Morrisville Lumber Co., Inc. v. Okcuoglu
531 A.2d 887 (Supreme Court of Vermont, 1987)
Clapp v. Goffstown School District
977 A.2d 1021 (Supreme Court of New Hampshire, 2009)
Unerstall Foundations, Inc. v. Corley
328 S.W.3d 305 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Davis Construction Corp. v. FTJ, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-construction-corp-v-ftj-va-2020.