United Savings Ass'n of Texas v. Jim Carpenter Co.

252 Va. 252
CourtSupreme Court of Virginia
DecidedSeptember 13, 1996
DocketRecord 951470; Record 952238; Record 960615
StatusPublished
Cited by3 cases

This text of 252 Va. 252 (United Savings Ass'n of Texas v. Jim Carpenter Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Savings Ass'n of Texas v. Jim Carpenter Co., 252 Va. 252 (Va. 1996).

Opinion

JUSTICE KOONTZ

delivered the opinion of the Court.

In these appeals we consider the applicability of mechanic’s liens to materials furnished for specific construction projects under pre *256 existing, non-binding credit agreements between contractors and materialmen. 1 In each instance, the contractor or its successor-in-interest asserts that the materials were furnished under “open accounts,” 2 thus each delivery of materials constituted a separate contract. The materialmen assert that the materials and deliveries are identifiable to specific projects under “running accounts,” 3 thus constituting a single continuing contract for each parcel. For the reasons which follow, and under the specific facts of these cases, we agree with the materialmen.

I.

BACKGROUND

A. United Savings Association of Texas v. Jim Carpenter Company

In 1983, Kenneth and Keith Ross (Ross Brothers), operating as joint proprietors, completed an application for credit with Jim Carpenter Company (Carpenter) in contemplation of purchasing building materials. In the application Carpenter agreed to extend credit, and Ross Brothers guaranteed payment on any credit extended. Ross Brothers subsequently incorporated, but otherwise continued to function as before.

In 1989, Ross Brothers began construction of houses on two parcels in the Blake Farm subdivision of Stafford County. Ross Brothers *257 ordered materials from Carpenter using separate purchase order job sheets for each parcel. Carpenter furnished the materials with invoices, assigning separate account numbers to each parcel, and submitted regular statements of the accounts to Ross Brothers. Deliveries were made to each parcel beginning on February 12, 1990 and ending on July 26, 1990. Ross Brothers paid for only one delivery. The two completed homes were sold in June and July of 1990.

On August 21, 1990, Carpenter filed memoranda of mechanic’s liens on each parcel which it subsequently sought to enforce by amended chancery actions filed August 12, 1994. The two chancery suits were consolidated and referred to a commissioner in chancery, who concluded the mechanic’s liens were proper. The defendants filed exceptions to the commissioner’s report, including the contention that the liens, or portions thereof, would be barred by the 90 day limitation of Code § 43-4 if each delivery were viewed as a separate contract. The chancellor sustained the commissioner’s findings and awarded judgment to Carpenter. We awarded an appeal to the defendants who are principally represented by United Savings Association of Texas, F.S.B., a mortgage lien holder on one of the properties.

B. Tart Lumber Company, Inc. v. Drewer Development Corporation

Tart Lumber Company, Inc. (Tart) entered into a credit agreement with Drewer Development Corporation (Drewer) to furnish Drewer with materials for building projects. Between August 8, 1990 and November 27, 1990, Tart provided Drewer with building materials for a number of residential construction projects in Loudoun and Fairfax Counties on land owned by Drewer.

For various aspects of each project, Drewer would submit a list of requirements or “takeoff.” Generally, each takeoff would list all the materials for a house or townhouse. Tart would then furnish Drewer with a thirty-day firm offer on the materials it could supply. Tart did not supply complete house packages, and the record does not establish how Drewer obtained those materials which Tart could not furnish. When Drewer accepted Tart’s offer, the materials were furnished along with an invoice referencing the specific project on which the materials were to be used. On occasion, Drewer would submit “fill-in” requests for additional materials which Tart would supply. Tart provided Drewer with regular statements combining charges under invoices for all materials furnished during a given time period.

*258 Beginning in the summer 1990, Drewer experienced financial difficulties and ceased payment on its account with Tart. In response, on December 12, 1990, Tart filed memoranda of mechanic’s liens on twelve properties, organizing in each memorandum all the invoices for a specific parcel.

On June 27, 1991, Tart filed a bill of complaint to enforce the liens. Although Drewer did not file an answer, the secured parties and trustees who financed the construction filed timely pleadings to contest the liens. The cases were consolidated and referred to a commissioner in chancery. The commissioner found that each delivery of materials was a separate contract, and, thus, he concluded that materials delivered more than ninety days before the memoranda were filed were not subject to mechanic’s liens. The chancellor upheld the commissioner’s findings. We awarded Tart an appeal.

C. Addington-Beaman Lumber Company, Inc. v. Roberson Builders, Inc.

On August 16, 1990, Roberson Builders, Inc. (Roberson) completed an application for credit with Addington-Beaman Lumber Company, Inc. (Addington-Beaman). Addington-Beaman furnished Roberson with building materials for the construction of houses on three parcels owned by Roberson in two subdivisions in the City of Chesapeake. Each invoice referenced the original customer number assigned to Roberson’s credit application, but was segregated by parcel.

Although it does not appear from the record that Addington-Beaman sent Roberson periodic statements, invoices for each parcel were separately totaled by Addington-Beaman’s accounting staff and the statements were bundled together by parcel with the adding machine tape showing the total amount due for that parcel. In one instance, an Addington-Beaman employee made a notation on one set of invoices that settlement of the contract for the sale of the home built on that parcel was expected shortly, at which time, presumptively, the invoices for the materials furnished for that project would be paid. Roberson did not pay for any of these materials before or after it conveyed the properties to home buyers.

For Lot 24, the deliveries were made from September 9, 1990 to October 25, 1990. For Lot 122, they were made from September 6, 1990 to October 31, 1990. For Lot 227, they were made from September 18, 1990 to November 13, 1990. Addington-Beaman filed *259 memoranda of mechanic’s liens for Lot 24 and Lot 122 on January 29, 1991 and on Lot 227 on February 28, 1991.

After Addington-Beaman filed bills of complaint to enforce its mechanic’s liens, all three matters were referred to a commissioner in chancery. The commissioner found for Addington-Beaman. The chancellor reversed the commissioner’s findings, ruling that each delivery was a separate contract required to meet the time requirements of Code § 43-4, even if filed under a combined lien. Thus, the chancellor ruled that only those deliveries which fell within the statutory time requirement were subject to the liens and judgment was awarded only for the.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis Construction Corp. v. FTJ
Supreme Court of Virginia, 2020
Center Medical Center v. Ady
77 Va. Cir. 299 (Roanoke County Circuit Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
252 Va. 252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-savings-assn-of-texas-v-jim-carpenter-co-va-1996.