Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc.

774 P.2d 1372, 160 Ariz. 582, 27 Ariz. Adv. Rep. 60, 1989 Ariz. App. LEXIS 35
CourtCourt of Appeals of Arizona
DecidedFebruary 9, 1989
Docket1 CA-CIV 9835
StatusPublished
Cited by3 cases

This text of 774 P.2d 1372 (Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc., 774 P.2d 1372, 160 Ariz. 582, 27 Ariz. Adv. Rep. 60, 1989 Ariz. App. LEXIS 35 (Ark. Ct. App. 1989).

Opinion

OPINION

HAIRE, Presiding Judge.

The primary issue presented on this appeal is as follows. When a general contractor makes a subcontractor and materialman joint payees on a check for labor and materials furnished, and there is no agreement between the materialman and general contractor as to the allocation of proceeds, will the materialman, by endorsing the check, be deemed to have been paid the money due him up to the amount of the joint check?

FACTS

Beztak Scottsdale Ranch Limited Partnership is the owner of an apartment project in Scottsdale, Arizona. Beztak of Scottsdale is the general partner of the limited partnership. These entities will be referred to jointly as “the owner.” Beztak of Arizona is an affiliated company and the general contractor on the project (“the general contractor”). The general contractor entered into a contract with High Sierra Electric (“the subcontractor”) in which the subcontractor agreed to furnish all necessary material, labor, tools, equipment and supplies to complete the electrical wiring on the project. The subcontractor purchased some of its supplies from Brown Wholesale Electric Company (“the material-man”).

Section 3 of the contract between the general contractor and the subcontractor provided that the general contractor would pay the subcontractor on a monthly basis for all labor and installed materials under a progress schedule, less a ten percent retention. Section 7 of the contract provided that the general contractor had the right to make any payment due to the subcontractor by joint check to the subcontractor and to anyone to whom the subcontractor was indebted for labor or materials. The subcontractor requested that the general contractor issue the payment checks to it and the materialman jointly.

*584 The general contractor issued three checks jointly to the subcontractor and the materialman. The general contractor did not tell the materialman how much of each joint check the materialman should retain. The materialman endorsed each joint check and the subcontractor then issued its check to the materialman in a lesser amount. The first joint check was for $11,123.10, of which the materialman received $6,673.86. The second joint check was for $22,124.57, of which the materialman received $13,-274.74. The, final joint check was for $21,-306.66, of which the materialman received $12,784.00. Each of the amounts received by the materialman represents 60% of the total joint check. At the time each joint check was endorsed by the materialman, the subcontractor’s account with the materialman for this project was in arrears in excess of the amount of the joint check.

The subcontractor eventually defaulted on the contract and was replaced before the project was completed. After the subcontractor’s default, the materialman filed a lien against the project, and sued the owner to foreclose the lien. The owner moved for partial summary judgment based on the joint check rule. The owner argued that the materialman was paid a total of $54,554.33 by means of the joint checks, and that the materialman’s lien must be reduced by that amount. The materialman argued that only the amount it actually received from the subcontractor, $32,732.60, should be credited to the account. The amount in dispute in this action is $21,821.73. 1

The trial court denied the owner’s motion for summary judgment. The court concluded that the joint check rule applies only in the absence of a contrary agreement, and that here there was evidence of a contrary agreement. The court’s conclusion was based on the provision in the contract between the general contractor and the subcontractor relating to progress payments. From the progress payment provision, the court found an intent that the materialman would receive from the proceeds of each joint check 90% of the cost of installed materials where sufficient progress had been made to satisfy a condition of payment. Because the materialman received more than that amount from each joint check, the trial court denied the owner’s motion for summary judgment and entered judgment in favor of the material-man. The owner has appealed from that judgment.

THE JOINT CHECK RULE IN ARIZONA

Arizona courts have not directly addressed the joint check rule. We have recognized that, as a general practice, general contractors issue joint checks to protect themselves from material suppliers’ lien claims. See, e.g., Wells-Stewart Constr. Co. v. Martin Marietta Corp., 103 Ariz. 375, 380, 442 P.2d 119, 124 (1968); Ray Elec. Inc. v. Merchants Bonding Co., 157 Ariz. 374, 758 P.2d 149 (App.1988); cf. United Bank v. Mesa N.O. Nelson Co., 121 Ariz. 438, 442, 590 P.2d 1384, 1388 (1979).

The joint check rule provides that, in the absence of an agreement to the contrary, if a material supplier receives a joint check and endorses it without collecting from the proceeds the amount of the debt then owed by the subcontractor, the material supplier is not entitled to assert a mechanic’s lien or payment bond claim based on that debt. Post Bros. Constr. Co. v. Yoder, 20 Cal.3d 1, 141 Cal.Rptr. 28, 569 P.2d 133 (1977). The material supplier need not retain any amount which is not then due. Medford School District v. Peterson & Jones Commercial Construction, 76 Or.App. 99, 708 P.2d 623 (1985).

The joint check rule has been approved by each state that has addressed this issue. See, e.g., Medford v. Peterson, 76 Or.App. 99, 708 P.2d 623 (1985); Anchor Concrete Co. v. Victor Sav. & Loan, 664 P.2d 396 *585 (Okla.1983); Post Bros. v. Yoder, 20 Cal.3d 1, 141 Cal.Rptr. 28, 569 P.2d 133 (1977). 2 The reasoning behind the rule varies from state to state. Some courts have held that by endorsing the joint check, the material supplier has received full payment of that amount as a matter of law. Post, 141 Cal.Rptr. at 30, 569 P.2d at 135. Other states explain the joint check rule by finding that endorsement of the check signifies the material supplier’s release of the payor from liability for that amount. F & C Engineering Co. v. Moore, 300 S.W.2d 323 (Tex.Civ.App.1957) (creditor who advances money to subcontractor from joint check proceeds is not entitled to lien protection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SFR, INC. v. Comtrol, Inc.
2008 UT App 31 (Court of Appeals of Utah, 2008)
Brown Wholesale Electric Co. v. Beztak of Scottsdale, Inc.
788 P.2d 73 (Arizona Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
774 P.2d 1372, 160 Ariz. 582, 27 Ariz. Adv. Rep. 60, 1989 Ariz. App. LEXIS 35, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-wholesale-electric-co-v-beztak-of-scottsdale-inc-arizctapp-1989.