Yates v. Industrial Steel Products Co.

399 S.W.2d 892, 1965 Tex. App. LEXIS 2922
CourtCourt of Appeals of Texas
DecidedOctober 19, 1965
DocketNo. 7658
StatusPublished
Cited by3 cases

This text of 399 S.W.2d 892 (Yates v. Industrial Steel Products Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yates v. Industrial Steel Products Co., 399 S.W.2d 892, 1965 Tex. App. LEXIS 2922 (Tex. Ct. App. 1965).

Opinion

CHADICK, Chief Justice.

“This is a suit by a material supplier against a public contractor and his surety under the McGregor Act, Article 5160, Vernon’s Annotated Civil Statutes. Plaintiff Industrial Steel Products, Inc. furnished structural steel and other construction materials to defendant Robert B. Yates for two buildings Yates was erecting for the Dallas Independent School District. These materials were furnished under separate written subcontracts, each specifying the terms of payment as follows: ‘14 of 1% 10 days net 30 days’. The parties construe this language as requiring payment in a lump sum * * *. Defendant National Surety Corporation executed payment bonds for each project under the McGregor Act and the principal questions here are the timeliness and sufficiency of the notices given by plaintiff to the surety.

“Delivery of the materials in question began in June and ended in October, 1961. After allowing for payments and other credits, the balance owed by Yates upon completion was $52,398.44 on one subcontract and $128,527.72 on the other, making a total of $180,925.76, for which recovery is now sought.

“On November 8th, 1961, Industrial delivered to both Yates and the surety the first notices now in question. Each of these was accompanied by a copy of the subcontract and by a ‘statement of account’ giving as dates of delivery ‘January 3, 1961, through October 31, 1961’, and describing the materials as ‘Necessary Structural Steel, Shop Fabricated Miscellaneous Steel Direct and Steel Longspan’. Thereafter on December 1, 1961, Industrial delivered to Yates and the surety additional notices, each of which were accompanied by a more detailed statement of account, specifying the dates of delivery, the items delivered on such dates and the prices attributed to each delivery. The surety admits that the notices of December 1, 1961, were sufficient to fix liability on it for the materials delivered in August, September and October and acknowledges liability for these materials in the amount of $66,784.00, but contends that such notices do not fix liability for items delivered in June and July, because not given ‘within ninety (90) days after the 10th day of the month next following each month in which the material was delivered in whole or in part’, as provided in Section B(a) of Article 5160. The Surety also contends that the notices of November 8, 1961, were not sufficient to fix liability on it for the materials delivered in June and July, because such notices did not give ‘the approximate date or date of performance or delivery on both and describing the labor or materials or both in such a manner so as to reasonably identify said labor or materials’, as provided in Section B(a) (2) of Article 5160.”

The foregoing quotation is from a written opinion filed in the trial court. This summary by the trial judge is adopted and will be supplemented as the need arises. The plaintiff, Industrial Steel Products Company, Inc., was awarded judgment against defendants Yates and National Surety Corporation, jointly and severally, for One Hundred Eighty Thousand Nine Hundred twenty-five and 76/100 ($180,-925.76) Dollars, with interest at the rate of Six (6%) per cent per annum from and after December 1, 1961, until paid, together with an attorney fee of ten thousand dollars for service in the trial court and two thousand five hundred ($2,500.-00) dollars for the same in the appellate courts, and for costs, etc. Yates and National Surety Corporation have appealed.

The Legislature at its Regular Session in 1959 amended Article 5160 and repealed Articles 5161, 5162, 5163, and 5164. The amended Article became effective April 27 [894]*894of that year and systemized statutory policy and procedures governing performance and payment bonds required of construction contractors with the state or its political subdivisions. The comprehensive nature of the statute and the Legislature’s intent is indicated to some extent by the headings the Legislative Bill gave to the various sections of the new enactment, such as, “Contractor’s Bonds for Performance and Payment for Labor and Material”, “Rights of Persons Furnishing Labor and Material”, “Notice Required”, “Claimant Defined”, “Venue”, etc. The Article is subdivided into seven main parts, each prefixed with a capitalized letter of the alphabet. Then each subdivision is further divided with divisions indicated by letters or numerals enclosed in parenthesis. The language of the Article the parties regard as relevant to this case is found in Section B, as follows:

“Rights of Persons Furnishing Labor or Material. Notice Required
“B. Every claimant who has furnished labor or material in the prosecution of the work provided for in such contract in which a Payment Bond is furnished as required herein-above, and who has not been paid in full therefor, shall have the right, if his claim remains unpaid after the expiration of sixty (60) days after the filing of the claim as herein required, to sue the principal and the surety or sureties on the Payment Bond jointly or severally for the amount due on the balance thereof unpaid at the time of filing the claim or of the institution of the suit; provided:
“(a) Notices Required for Unpaid Bills, other than notices solely for Re-tainages as hereinafter described.
“Such claimant shall have given within ninety (90) days after the 10th day of the month next following each month in which the labor was done or performed, in whole or in part, or material was delivered, in whole or in part, for which such claim is made, written notices of the claim by certified or registered mail, addressed to the prime contractor at his last known business address, or at his residence, and to the surety or sureties. Such notices shall be accompanied by a sworn statement of account stating in substance that the amount claimed is just and correct and that all just and lawful offsets, payments, and credits known to the affiant have been allowed. Such statement of account shall include therein the amount of any re-tainage or retainages applicable to the account that have not become due by virtue of terms of the contract between the claimant and the prime contractor or between the claimant and a subcontractor. When the claim is based on a written agreement, the claimant shall have the option to enclose, with the sworn statement of account, as such notice a true copy of such agreement and advising completion or value of partial completion of same.
“(1) * * *
“(2) When the claim is for multiple items of labor or material or both to be paid for on a lump sum basis such notice shall state the name of the party for whom the labor was done or performed or to whom the material was delivered, the amount of the contract and whether written or oral, the amount claimed and the approximate date or dates of performance or delivery or both and describing the labor or materials or both in such a manner so as to reasonably identify the said labor or materials.
«^3) * * *
“(b) * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fidelity & Guaranty Co. v. Parker Brothers & Co.
437 S.W.2d 880 (Court of Appeals of Texas, 1969)
New Amsterdam Casualty Co. v. Texas Industries, Inc.
408 S.W.2d 733 (Court of Appeals of Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
399 S.W.2d 892, 1965 Tex. App. LEXIS 2922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yates-v-industrial-steel-products-co-texapp-1965.