United States v. Community Science Technology, Inc.

574 F.2d 1292, 25 Cont. Cas. Fed. 82,463, 1978 U.S. App. LEXIS 10707
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 14, 1978
Docket76-2022
StatusPublished
Cited by2 cases

This text of 574 F.2d 1292 (United States v. Community Science Technology, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Community Science Technology, Inc., 574 F.2d 1292, 25 Cont. Cas. Fed. 82,463, 1978 U.S. App. LEXIS 10707 (5th Cir. 1978).

Opinion

574 F.2d 1292

25 Cont.Cas.Fed. (CCH) 82,463

UNITED STATES of America for the Use and Benefit of
MICRO-KING COMPANY, Plaintiff-Appellee Cross Appellant,
v.
COMMUNITY SCIENCE TECHNOLOGY, INC., Community Science
Technology Development Corporation and Great
American Insurance Company,
Defendants-Appellants Cross Appellees.

No. 76-2022.

United States Court of Appeals,
Fifth Circuit.

June 14, 1978.

John C. Bell, Jr., James E. Slaton, Augusta, Ga., John L. Blandford, Chamblee, Ga., for defendants-appellants cross appellees.

William A. Trotter, III, Augusta, Ga., for plaintiff-appellee cross appellant.

Appeals from the United States District Court for the Southern District of Georgia.

Before GOLDBERG, GODBOLD and SIMPSON, Circuit Judges.

SIMPSON, Circuit Judge:

This is a case brought under the Miller Act, 40 U.S.C. §§ 270a et seq. (1970), by use plaintiff Micro-King, a subcontractor, against the prime contractor, Community Science Technology, Inc. (CST), and the surety supplying its performance and payment bonds for the job, The Great American Insurance Company. The district court found for Micro-King on its claim that CST breached its contract by failing to make a substantial payment for work performed, and awarded damages to it in quantum meruit, offset by the amount over the contract price expended by CST to complete Micro-King's work. Both parties timely appealed. We affirm the judgment of the district court both as to the appeal by CST, and the cross-appeal by Micro-King.

I. THE FACTS

In 1972, CST contracted with the United States Army Corps of Engineers to construct 200 units of family housing at Fort Gordon, Georgia. Initially, CST subcontracted the outside utilities construction work on the project to the Peter C. David Company (David). David performed its work on a profit sharing basis with the Micro-King Company. When David withdrew from the project without fulfilling its obligations, CST on September 20, 1973, contracted with Micro-King to perform the remaining outside utilities work. In pertinent part, the contract provided that Micro-King must perform and complete its work according to plans and specifications incorporated by reference into the primary contract between the Corps of Engineers and CST "to the satisfaction of the architect, the owner (the Corps of Engineers U. S. Army)" and CST. Plaintiff's Exhibit 14, Article III. Article VI of the contract provided for progress payments:

Payment will be made once each month as the work progresses, providing that all work has been in full accordance with all the terms of this agreement. Progress payments shall be prepared on the basis of the percentage of work completed and submitted to (CST's) Project Manager or Superintendent for approval.

Micro-King proceeded to work on the sanitary sewer lines, storm drainage system and gas and water distribution systems for the project, submitting applications for partial payments. For its part, CST, up to and including April 22, 1974, paid all sums as requested. On August 5, 1974, Micro-King submitted a payment application for $9,060.62, stating that its contractual requirements were 100 percent complete. Plaintiff's Exhibit 4. This application was signed and approved by Dominick Rufrano, the project manager, T. 181-82; Defendant's Exhibit 30; but no payment was made. On September 13, 1974, Micro-King, again stating that its work was complete, left the job site to perform work on an unrelated project in California. On October 7, 1974, it submitted a bill to CST for the amount outstanding under the contract plus an additional $12,780 for extra work outside the contract, performed by Micro-King at CST's request. Finally, in response to the August 5 invoice, CST sent Micro-King a check for $5,726.73, dated October 19, 1974. According to CST, the Corps of Engineers that month refused to approve the work done by Micro-King, noting numerous deficiencies. CST estimated the costs it would incur to correct these deficiencies and deducted that amount from the sums owed to Micro-King under the contract, leaving the $5,726.73 ultimately paid to Micro-King. CST used its own crews and other subcontractors to complete, repair, and test the outside utilities work which Micro-King had agreed to perform.

On February 14, 1975, Micro-King filed suit against CST under the Miller Act, 40 U.S.C. §§ 270a et seq., seeking to recover the balance due on the contract price, compensation for work done outside the contract, and attorneys' fees. CST counterclaimed to recover the costs it had incurred beyond the contract price in order to complete, repair, and test the work covered by its contract with Micro-King, to the satisfaction of the Corps of Engineers. Prior to trial, the parties stipulated that CST had paid Micro-King $72,801.71 of the adjusted agreed price, $93,800.

After a three day trial, the jury delivered its verdict by answering 12 special interrogatories, propounded by the court as provided by Rule 49(a), F.R.Civ.P. As to breach of contract, the jury found that, although Micro-King did not complete "all that it was required to do under its contract to the reasonable satisfaction of the defendant and the Corps of Engineers", this failure was caused by CST's failure to pay Micro-King "a substantial sum due . . . under the contract for work performed. . . ." The amount of damages suffered by Micro-King as a result of CST's failure to pay was found by the jury to be "undeterminable". As to work "beyond the scope of the contract" done at the request of CST, the jury found that Micro-King conferred a benefit of $15,052.75 upon CST for which it had not been paid. The jury also found that CST had expended $9,843.50 to complete Micro-King's work under the contract. Finally, the jury found that reasonable attorneys' fees for the services rendered by counsel for either party were $6,500.00. The court entered judgment on the jury's verdict, awarding Micro-King $5,209.25 in damages, representing the difference between $15,052.75 and $9,843.50, and $6,500.00 in attorneys' fees. The court subsequently denied CST's post-trial motions. CST timely filed a notice of appeal to this Court, and Micro-King has cross-appealed.

II. THE ISSUES RAISED

1. The Award of Attorneys' Fees :

"The so-called 'American Rule' governing the award of attorneys' fees in litigation in the federal courts is that attorneys' fees 'are not ordinarily recoverable in the absence of a statute or enforceable contract providing therefore'." F. D. Rich Co., Inc. v. United States for the Use of Industrial Lumber Co., Inc., 417 U.S. 116, 126, 94 S.Ct. 2157, 2163, 40 L.Ed.2d 703 (1974), citing Fleischmann Distilling Corp. v. Maier Brewing Co., 386 U.S. 714, 717, 87 S.Ct. 1404, 1407, 18 L.Ed.2d 475 (1967).1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Russell Weiss
599 F.2d 730 (Fifth Circuit, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
574 F.2d 1292, 25 Cont. Cas. Fed. 82,463, 1978 U.S. App. LEXIS 10707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-community-science-technology-inc-ca5-1978.