United States v. F. D. Rich Co.

473 F.2d 720
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 22, 1973
DocketNos. 71-1485, 71-1519
StatusPublished
Cited by2 cases

This text of 473 F.2d 720 (United States v. F. D. Rich Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. F. D. Rich Co., 473 F.2d 720 (9th Cir. 1973).

Opinion

JAMES M. CARTER, Circuit Judge:

This is an appeal by F. D. Rich Co., Inc. (hereafter Rich) from a judgment in favor of Industrial Lumber, Inc. (hereafter Industrial), a building materials supplier, against Rich, a prime contractor on a government construction project, and Transamerica Insurance Co., his surety under the Miller Act, 40 U.S.C. §§ 270a-270d (1970). There is also a cross-appeal by Industrial, for interest on unpaid invoices, and attorneys’ fees.

The issues presented on the appeal are:

(1) Was Cerpac, the intermediary who furnished plywood (and, under another agreement, certain millwork), a “subcontractor” for Miller Act purposes ?

(2) Does the agreement of Rich, the prime contractor, to pay Industrial, the plywood supplier, directly, rather than through the intermediary Cerpac, for the last two shipments under the contract, preclude consideration of those two shipments as the “last material for which claim is made” to establish timeliness of the Miller Act notice ?

(3) Is venue proper in California for shipments supplied pursuant to a contract to be performed there, but diverted to South Carolina with the knowledge of all parties?

[722]*722The issues presented on the cross-appeal by Industrial are:

(4) Should pre-judgment interest have been awarded to Industrial at 8 percent, as stated in the invoices, rather than at 7 percent for unliquidated claims pursuant to California statute?

(5) Should attorneys’ fees have been awarded to Industrial under federal law, for this California claim ?

On the appeal, we affirm the District Court’s judgment for the plywood supplier, Industrial, against Rich and against Transamerica Insurance Co., except as to two shipments diverted to South Carolina. On the cross-appeal, we reverse and direct that Industrial be awarded interest at 8 percent, plus reasonable attorneys’ fees, as detailed below. It is first necessary to summarize the salient facts.

Facts

From 1961 through 1968, appellant Rich built numerous federal housing projects, and during 1963-1966, Cerpac furnished most, if not all, of the mill-work and plywood for these projects. Cerpac’s president, Cervi, had close relationships with Rich, its officers and personnel. Principals of Rich held a substantial voting interest in Cerpac stock, were completely familiar with its operations and financial condition, and supplied a substantial share of its working capital.

On October 18, 1965, Rich contracted with the United States to build family housing at Beale Air Force Base, California. Rich’s surety, appellant Trans-america, posted the required payment bond under the Miller Act, 40 U.S.C. § 270a. Rich awarded Cerpac two contracts, one for all custom millwork, and one for all exterior plywood, each incorporating by reference terms of the prime contract. These contracts were similar to those which previously had been completed between the parties on other jobs over the years.

On February 22, 1966, Cervi placed a single order with appellee Industrial for all exterior plywood required by Rich at Beale, designating the order as “Beale 647.” Industrial' then ordered the plywood from its own suppliers, assigned order numbers to specific shipments to be used as necessary, and designated its mill orders as contract “Beale 647.” The shipments to Rich at Beale began approximately March 10, 1966, and as each truckload arrived it was receipted for by a Rich representative.

Shortly thereafter, Rich told Cervi that more plywood was needed for another government project at Charleston, South Carolina, in which the two had similar relationships. Industrial was so advised, and obtained approval from the mill. For the convenience of Rich and Cerpac, then, two truckloads of plywood, still designated as “Beale 647,” were delivered to Innes, South Carolina, and used on the Charleston project.

During April and May, 1966, Cerpac fell behind in its payments to Industrial for the plywood shipments, and Cervi was told that Industrial would not deliver the final two truckloads until assurances of payment were given. The parties subsequently agreed that Rich would pay Industrial directly for the last two shipments, with Cerpac to receive its customary profit as a commission from Industrial. The last two shipments arrived at Beale on May 16 and June 23, 1966. The invoices for these shipments, as all Industrial invoices herein, were payable in full in 30 days, with annual interest of 8 percent after the due date.

On July 13, 1966, having received no payment oh nine separate invoices, Industrial formally gave Rich and Trans-america, the surety, a written notice of claim under the Miller Act, and thereafter timely brought this action. Cerpac filed in bankruptcy in October 1966, and is not a party to this appeal. The nine specific invoices were part of the extensive evidence considered by the trial court, which made detailed findings of fact and conclusions of law. Except as otherwise noted herein, our review shows that those findings and conclusions were correct.

[723]*723The District Court gave judgment for Industrial against Transamerica on the bond, and against Rich and Cerpac as primary obligors, all jointly and severally for the amount of all nine unpaid invoices, $31,402.97, plus 7 percent interest from March 13, 1967, to the date of judgment ($7,974.70), plus costs. Rich appeals the award, and Industrial cross-appeals on questions of interest and attorneys’ fees.

Was Cerpac a Subcontractor?

The Miller Act provides that those who furnish material for government work for which a bond has been given under 40 U.S.C. § 270a, may sue on that bond.

“. . . Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made. ...” Id., § 270b (a).

It is undisputed that Rich had a direct agreement with Industrial only as to payment for the two final shipments of plywood. Unless that agreement extends to the previous shipments as well, and we are not convinced that it did, Industrial cannot recover for them unless it can show that Cerpac was a “subcontractor” under the Act, and the strict requirements of the Act are otherwise met. See Fidelity & Dep. Co. of Md. v. Harris (9 Cir. 1966) 360 F.2d 402, 410. One who furnishes materials to a supplier (as opposed to a subcontractor) has no rights under the Miller Act. Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 104, 64 S.Ct. 890, 88 L.Ed. 1163 (1944).

In MacEvoy, the Supreme Court stated the following definition:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
473 F.2d 720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-f-d-rich-co-ca9-1973.